Ellington Properties · Dubai Islands
Meriva Sunset Construction Updates
An Island B Build Record That Opens at the February 2026 Baseline
Meriva Sunset's DLD register record opened at 0% on 25 February 2026, a collection-wide baseline that every later reading for The Meriva Collection will be measured from.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
Meriva Sunset at a Glance
Meriva Sunset is the G+20 residence the developer places at the top of Ellington Properties' The Meriva Collection on Island B, holding 377 of the collection's 903 residences. Its construction figures do not have a DLD record of their own: they sit inside project 4346, a single register entry shared by every building in the collection, so the 0% reading of 25 February 2026 describes the whole plot rather than this one building. The registered construction start of 03 April 2026 is dated after that inspection, and each anchor below is printed exactly as the register records it.
4346 (The Meriva Collection)
Active
03 April 2026 (DLD)
377 residences, part of 903 in The Meriva Collection
144,845.68 sq m
31 December 2031 (DLD)
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
Meriva Sunset Construction Update Timeline
So far this record holds one dated reading: 0% on 25 February 2026, taken on a plot where the inspection found no construction activities started. The register then logged a construction start of 03 April 2026 and project registration on 14 April 2026, both after that inspection date. The single dot on the track below is that baseline, and the table row links the February 2026 monthly update where the inspection is covered in full.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| February 2026 | 0% | 25 February 2026 | View the February 2026 update |
Pace Analysis
How Fast Meriva Sunset Has Been Built
A pace needs two dated readings, and the Meriva Sunset record has one. What the record does support is set out below, with the arithmetic kept separate from anything measured:
- 25 Feb 2026: first and only DLD register reading for project 4346, 0%No measured pace yet
- 25 Feb 2026 to 31 Dec 2031 registered completion: 100 points over 2,135 days (arithmetic, not a forecast)About 1.41 points per 30-day month
One point at zero cannot show acceleration, taper or a gap between inspections; what it fixes is the starting line for The Meriva Collection's first measured movement. The 1.41 figure is not a rate anyone has observed on the plot: it simply spreads the full 100 points evenly across the 2,135 days between the 25 February 2026 reading and the registered completion date. For an end user, the practical signal will be the second dated reading and how far it sits above 0%. For an investor, the more immediate markers are the plan's four construction-linked instalments at 20%, 30%, 40% and 50% construction of the project, none of which had been triggered at the February 2026 reading.
Get the Next Inspection Figure First
Tell me you are tracking Meriva Sunset and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About Meriva Sunset at Island B
The February 2026 baseline only means something next to what is planned for the plot. The full project guide covers what Meriva Sunset buyers are tracking toward on this page:

Meriva Sunset: Ellington's Building in The Meriva Collection
Meriva Sunset is an Ellington building of 20 residential floors on Island B, holding 377 apartments and penthouses by the beach.
View the Meriva Sunset Project GuideConsidering a Pre-Construction Entry?
Availability at Meriva Sunset keeps moving while the record still sits at its baseline, and entering now means the longest runway to the Q2 2030 handover. If the record on this page is what brought you here, ask me for current availability before choosing a layout.
Ask About Remaining Availability on WhatsAppStage Record
Meriva Sunset Build Stages, Mapped to the Inspections
Only the first of the five stages below has a dated entry in this record, the 0% baseline of 25 February 2026; the other four carry no reading yet and will be anchored to real inspection dates as the register for project 4346 moves.
Register Baseline and Project Registration
The 25 February 2026 inspection found no construction activities started and the register read 0%; the DLD then recorded a construction start of 03 April 2026 and registration on 14 April 2026.
Enabling Works and Basement
The first register reading above 0% for project 4346 will open this stage, which covers the basement beneath Meriva Sunset's ground floor.
Ground Floor and 20-Floor Structure
This stage will carry Meriva Sunset's ground floor, 20 residential floors and rooftop, the G+20 configuration the developer sets out for the building.
Facade, Fit-Out and Amenity Floors
Enclosure and fit-out of 377 residences, plus the amenity decks the developer plans on the 12th, 13th and 17th floors.
Completion and Handover
The final 30% of the 70/30 plan falls due on completion, with handover of Meriva Sunset anticipated by Ellington Properties in Q2 2030.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Meriva Sunset's own record.
Buyer Position
Tracking Your Position at Meriva Sunset
This page is one of four project resources that together cover a Meriva Sunset purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Meriva Sunset Construction Updates
This page: the DLD register record for Meriva Sunset, opening at 0% on 25 February 2026.

Meriva Sunset Golden Visa: Island B Residences Above the Line
Ellington Properties' Meriva Sunset, 377 residences in The Meriva Collection, sits above the threshold at all six tiers.
Read the Meriva Sunset Golden Visa Guide
Meriva Sunset Escrow: Ellington's Island B Account at Sharjah Islamic Bank
Ellington's Meriva Sunset escrows 939 units with Sharjah Islamic Bank as DLD project 4346, certified 0% in February 2026.
Verify the Meriva Sunset Escrow AccountApproaching Handover
Between 0% and Handover: What Meriva Sunset Buyers Should Do Now
At the 25 February 2026 reading nothing had been built on the collection plot, yet half of a Meriva Sunset price falls due within 360 days of reservation under the 70/30 plan. That timing, not the site, sets the urgency: the time-linked payments run from each buyer's own reservation date whether or not the register has moved, so the three steps below belong before the first transfer, not after it.
First, match every transfer to the trust account registered for project 4346; the Meriva Sunset escrow account checks show how to confirm the Sharjah Islamic Bank details before money leaves your account.
Second, read your SPA against the four 5% instalments due on completion of 20%, 30%, 40% and 50% construction of the project, and compare them with the collection-wide register reading, which the Meriva Sunset February 2026 inspection update records at 0%.
Third, if residency is part of the plan, settle it early through the Meriva Sunset Golden Visa eligibility guide, since every tier from AED 3.06M ≈ USD 832K sits above the property threshold and the guide explains how an off-plan purchase is assessed.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore Island B Structure
A baseline record from February 2026 says little on its own; what surrounds the plot says more. These three pages place Meriva Sunset's baseline in its island, community and developer context:

Island B: Seven Waterfront Projects by Nakheel, Ellington and Beyond
Island B, on the eastern side of Dubai Islands, is a villa and beachfront residence district with seven projects for sale.
See Island B Properties for Sale
Island B Community Overview
Discover Island B within Dubai Islands, featuring waterfront residences, beach access, hospitality destinations, promenades, and planned lifestyle infrastructure by Nakheel.
Explore the Island B Community
Ellington Properties: Design-Led Boutique Residences With Curated Interiors
Ellington Properties, founded in 2014, is a design-led developer of apartments, villas and waterfront homes, with 30 developments launched and delivered.
View the Ellington Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
Meriva Sunset Construction Updates Frequently Asked Questions
Meriva Sunset is part of DLD project 4346, registered as The Meriva Collection with status Active, and its latest DLD register reading is 0%, dated 25 February 2026, when the inspection found no construction activities started on the collection plot. On 29 September 2026 that reading was 216 days old, so the live register entry is the place to confirm it; the full record is in the inspection timeline above.
The Meriva Sunset record holds one reading: 0% on the DLD register, dated 25 February 2026. With no earlier figure there is no point change to report, and the first measured movement will arrive with the next dated reading for project 4346. The February inspection itself is covered in the Meriva Sunset February 2026 construction update.
The DLD register shows a registered completion date of 31 December 2031 for project 4346, the record covering The Meriva Collection as a whole, and that date has not passed. Ellington Properties anticipates completion of Meriva Sunset in Q2 2030, the handover date used on this page, and the record here is updated as each new register reading is published.
Meriva Sunset has 377 residences, part of 903 residences in The Meriva Collection, arranged over a ground floor, 20 residential floors and a rooftop above a basement and served by 6 lifts. Homes run from 1 bedroom apartments to 4 bedroom penthouses, and the developer places amenity decks on the 12th, 13th and 17th floors.
No. A measured pace needs two dated readings, and the Meriva Sunset record holds one: 0% on 25 February 2026. As arithmetic, not a forecast, the 100 points between that reading and the registered completion date of 31 December 2031 span 2,135 days, about 1.41 points per 30-day month. The pace analysis will carry a measured figure once a second reading exists.
DLD project 4346, registered as The Meriva Collection, spans several buildings. Its registered scope lists a basement-plus-ground-plus-20 high-rise residence, matching the developer's configuration for Meriva Sunset, alongside two B+G+10 mid-rise residences, two B+G+6 residences, a B+G+2 residence, a B+G+5 hotel and supporting amenities, so the 0% reading of 25 February 2026 describes the whole collection rather than one building.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the Meriva Sunset construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.