Emaar · Grand Polo Club and Resort
Montura 2 at Grand Polo Club & Resort Construction Updates
The Verified Build Record for 206 Villas Beside the Polo Fields
Montura 2 recorded 5.01% construction at its 06 July 2026 RERA inspection, the first dated reading on a 206-villa Emaar parcel still working through its foundations.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
Montura 2 at Grand Polo Club & Resort at a Glance
Montura 2 is Emaar's 206-villa parcel inside Grand Polo Club and Resort, registered with the Dubai Land Department as project 3704 and built on plot 2503 in Dubai Investment Park Second. Fourteen months separate the 30 April 2025 construction start from the 5.01% recorded in July 2026, and the anchors behind that reading are below. Because this parcel sits between the original Montura cluster and Montura 3 on the eastern edge of the masterplan, its record doubles as a read on how fast Grand Polo's second villa wave is being pushed out from the polo fields.
3704
Active
30 April 2025
206 villas
31 May 2029 (DLD)
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
Montura 2 at Grand Polo Club & Resort Construction Update Timeline
One dated inspection anchors this record so far: 06 July 2026, at 5.01%. The register also carries an earlier figure of 1.99% as the previous reading, but publishes no date beside it, so the 3.02 point gain sits on the record with no interval to measure it over. The track below therefore plots the dated reading only, and the table row links the full July 2026 report.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| July 2026 | 5.01% | 06 July 2026 | View the July 2026 update |
Pace Analysis
How Fast Montura 2 at Grand Polo Club & Resort Has Been Built
With a single dated figure on the register, the useful pace read is not a velocity between inspections but the distance between what has been recorded and what the programme still has to deliver:
- 30 April 2025 start to the 06 July 2026 inspection: 0% to 5.01%About 0.4 points per month, derived
- 06 July 2026 to the 31 May 2029 registered completion: 5.01% to 100%About 2.7 points per month required
- Certified completion levels carried in the published payment schedule: 20%, 50%, 90%Nov 2026, Aug 2027, Jun 2028
Those two rates are the whole early-stage picture. The first is derived from the construction start rather than measured between two inspections, because only one reading carries a date; it describes fourteen months in which mobilization, access into the parcel, and foundation setting out consumed the calendar without moving the percentage far. The second is the requirement: closing 94.99 points inside roughly thirty-five months asks about seven times the rate recorded so far, which is the normal shape once 206 villa plots leave enabling together and superstructure starts running in parallel rather than one plot at a time. For an end user the figure worth watching is not July's 5.01% but whether 20% certified completion lands near the November 2026 point in the schedule; for an investor, that same checkpoint is the first hard evidence that the required run rate is real.
Get the Next Inspection Figure First
Tell me you are tracking Montura 2 at Grand Polo Club & Resort and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About Montura 2 at Grand Polo Club & Resort at Grand Polo Dubai
A build percentage only means something next to what is being delivered. The full project guide covers what buyers on this page are tracking toward:

Montura 2 at Grand Polo Club & Resort, Villas with Lifts
Montura 2 at Grand Polo Club & Resort is a 206 villa release pairing 3 bedroom homes with 5 bedroom villas.
View the Montura 2 at Grand Polo Club & Resort Project GuideConsidering an Early-Stage Entry?
Plot position, orientation, and villa type are at their widest choice while a parcel is still at foundation stage, and what Emaar holds moves between releases. If the record on this page is what brought you here, tell me and I will send the current list.
Ask About Remaining Availability on WhatsAppStage Record
Montura 2 at Grand Polo Club & Resort Build Stages, Mapped to the Inspections
Two of the five stages below are recorded facts on the DLD register; the rest are still ahead of Montura 2 and are anchored to the certified completion levels the published payment schedule already carries dates against.
Registration and Construction Start
Project 3704 was entered on the DLD register on 22 April 2025 and construction start was recorded on 30 April 2025, with buyer payments held in the trust account at Abu Dhabi Commercial Bank.
Mobilization, Infrastructure, and Foundations
The July 2026 inspection recorded mobilization ongoing, infrastructure works progressing through the parcel, and enabling and foundation works at early stages across plot 2503.
Villa Superstructure Across 206 Plots
Ground and first floor structure to the G plus one plus roof description carried in the RERA record, repeated across 206 plots. The payment schedule dates its 20% certified completion instalment to November 2026.
Envelope, Roofs, and Parcel Infrastructure
External walls, roofs, and the road, utility, and landscape corridors serving the parcel. The schedule dates its 50% certified completion instalment to August 2027, a little over a year past the July 2026 reading.
Fit-Out, Landscaping, and Delivery
Interior finishing, systems testing, and community landscaping toward the 90% level dated June 2028 in the schedule and the registered completion date of 31 May 2029, inside the Q2 2029 handover window.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Montura 2 at Grand Polo Club & Resort's own record.
Buyer Position
Tracking Your Position at Montura 2 at Grand Polo Club & Resort
This page is one of four project resources that together cover a Montura 2 at Grand Polo Club & Resort purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Montura 2 at Grand Polo Club & Resort Construction Updates
The dated inspection record for Montura 2, tracked from the April 2025 start to handover.

Montura 2 at Grand Polo Club & Resort Golden Visa: Every Villa
Montura 2 at Grand Polo Club & Resort, 206 Emaar villas, splits into 3 and 5 bedroom formats that both qualify.
Read the Montura 2 at Grand Polo Club & Resort Golden Visa Guide
Montura 2 at Grand Polo Club & Resort: Second Release Escrow
Montura 2 at Grand Polo Club & Resort, DLD project 3704: Abu Dhabi Commercial Bank escrow, 5.01% certified July 2026.
Verify the Montura 2 at Grand Polo Club & Resort Escrow AccountApproaching Handover
Between 5.01% and Handover: What Montura 2 at Grand Polo Club & Resort Buyers Should Do Now
Nothing vertical stands on plot 2503 yet, so what a buyer can act on at this point is paperwork and plot position rather than progress. With 94.99 points left to record before handover, three items are worth closing while the next reading is still ahead.
First, confirm that each instalment lands in the escrow account registered against project 3704 with the Dubai Land Department, and that your own schedule reads against certified completion levels rather than calendar dates alone; the Montura 2 escrow account page covers the account and how milestone releases work.
Second, if the villa is meant to support residency, read the eligibility path now on the Montura 2 Golden Visa guide, because an off-plan purchase running to 2029 follows a different route than a completed one.
Third, follow the record itself: the inspection calendar belongs to RERA rather than to Emaar, so the next figure arrives when it is audited, and the notes behind the current one sit in the July 2026 Montura 2 construction update.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore Grand Polo Dubai Structure
A build record is only half the picture; the other half is what is rising around it. These three pages put Montura 2's progress in its masterplan, community, and developer context:

Grand Polo Dubai Properties for Sale
Browse villas and townhouses for sale at Grand Polo Club & Resort, comparing Equiterra, Selvara and Chevalia.
See Grand Polo Dubai Properties for Sale
Grand Polo Dubai Community Overview
Read the Grand Polo Club & Resort guide: Emaar's 60 million sq ft equestrian estate community of villas and townhouses.
Explore the Grand Polo Dubai Community
Emaar Properties: Burj Khalifa, Downtown Dubai and Twenty Master Communities
Emaar, founded in 1997, built Burj Khalifa and Downtown Dubai and has delivered over 85,000 homes across twenty master communities.
View the Emaar Properties Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
Montura 2 at Grand Polo Club & Resort Construction Updates Frequently Asked Questions
Montura 2 is an active DLD-registered project (number 3704) in its enabling and foundations phase, recorded at 5.01% at the inspection of 06 July 2026. The dated record is in the inspection timeline above.
The 06 July 2026 inspection recorded 5.01% construction progress, 3.02 points above the previous figure of 1.99% that the register carries without a date of its own. The inspection notes behind that reading are in the July 2026 Montura 2 site report.
The DLD-registered completion date for project 3704 is 31 May 2029, inside the Q2 2029 handover window, and the latest inspection on 06 July 2026 recorded 5.01%. That leaves 94.99 points still to record, and the figures on this page are updated as each new inspection enters the register.
DLD registration records show 206 villas, split into 195 three bedroom and 11 five bedroom homes, described in the RERA record as G plus one plus roof. Average built-up areas are 2,981 sq ft for the three bedroom villa and 5,303 sq ft for the five bedroom villa. Layout detail sits in the Montura 2 at Grand Polo project guide.
Registration of project 3704 was recorded on 22 April 2025 and construction start on 30 April 2025. The first dated reading on the register followed on 06 July 2026 at 5.01%, fourteen months after the start date.
At the 06 July 2026 inspection the record showed mobilization ongoing, infrastructure works progressing through plot 2503, and enabling and foundation works at early stages. No villa superstructure is recorded at the 5.01% reading.
Only one reading carries a date, so no velocity between inspections can honestly be stated. Measured from the 30 April 2025 start, 5.01% by 06 July 2026 works out at about 0.4 points per month, while reaching 100% by the registered date of 31 May 2029 would require about 2.7 points per month. The working is in the pace analysis above.
The parcel is plot 2503 in Dubai Investment Park Second, set east of the polo fields and clubhouse with the first Montura release on one side and Montura 3 on the other. That position means the villas here are being built while the surrounding amenities are, rather than after them. Community context is on the Grand Polo community overview.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the Montura 2 at Grand Polo Club & Resort construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.