Emaar · Grand Polo Club and Resort
Montura 3 at Grand Polo Club & Resort Construction Updates
Reading the Inspection Record on Grand Polo's Eastern Villa Parcel
Montura 3 recorded 1.06% construction at its 21 April 2026 RERA inspection, the enabling works reading that opens the build record for these 219 Grand Polo villas.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
Montura 3 at Grand Polo Club & Resort at a Glance
Montura 3 is Emaar's 219-villa third phase of the Montura line inside Grand Polo Club and Resort, built on plot 2078 and recorded by the Dubai Land Department under Dubai Investment Park Second. Thirteen months separate the 13 March 2025 construction start from the 1.06% logged at the April 2026 inspection, and the anchors below are the registered figures behind that short record. Almost every other project tracked on this site is being measured on how much is finished; this one is still being measured on how much has been set up.
3703
Active
13 March 2025
219 villas
30 June 2029 (DLD)
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
Montura 3 at Grand Polo Club & Resort Construction Update Timeline
This record currently holds a single dated reading: 1.06%, logged on 21 April 2026, thirteen months after the March 2025 start. A figure of 0.55% also appears in the register carrying no date, and because the track and the table below only ever plot verified dates, that earlier number stays in prose here rather than on the chart. Every future cycle joins the same table as it publishes.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| April 2026 | 1.06% | 21 April 2026 | View the April 2026 update |
Pace Analysis
How Fast Montura 3 at Grand Polo Club & Resort Has Been Built
With a single dated inspection on file, Montura 3 has no measurable velocity between readings yet. What can be stated honestly is the distance covered since the start date and the distance the registered completion date implies:
- Mar 2025 start to Apr 2026 inspection: 0% to 1.06%, derived from the start dateAbout 0.1 points per month
- Undated register movement from 0.55% to 1.06%: no interval recorded0.51 points, interval unstated
- Apr 2026 to the 30 June 2029 registered completion: 98.94 points remainingAbout 2.6 points per month implied
Every figure above is derived arithmetic rather than observed pace, and saying so matters more on this page than on any other in the portfolio. A villa cluster at 1.06% has spent its first year on mobilization, access and services, which is exactly where the percentage moves slowest and where the certified number understates the work actually done on the ground. The reading that will tell buyers something is the next one: a second dated inspection turns two points on a chart into a real rate, and the gap between that rate and the 2.6 points per month the June 2029 date implies is the number worth watching. For a buyer part way through an 80/20 schedule, that comparison is the earliest honest signal of whether the milestone instalments will fall due when the plan says they will.
Get the Next Inspection Figure First
Tell me you are tracking Montura 3 at Grand Polo Club & Resort and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About Montura 3 at Grand Polo Club & Resort at Grand Polo Dubai
A percentage means little without the thing it is building toward. The 219 villas this record is measuring are set out in full here:

Montura 3 at Grand Polo Club & Resort, on the Eastern Edge
Montura 3 at Grand Polo Club & Resort is a limited run of 219 villas along the eastern edge.
View the Montura 3 at Grand Polo Club & Resort Project GuideConsidering an Early-Stage Entry?
Limited villas are listed as available at Montura 3, and the selection at this stage still spans both formats and plot positions rather than whatever is left near completion. If the record on this page brought you here, I can send you what is currently open.
Ask About Remaining Availability on WhatsAppStage Record
Montura 3 at Grand Polo Club & Resort Build Stages, Mapped to the Inspections
Each stage below carries either a date already sitting on the Montura 3 register entry or the completion milestone that releases it. At 1.06% that is a more honest map than a standard build sequence would be, because most of what follows has not happened yet.
Commencement and Registration
Construction commencement was recorded on 13 March 2025 and project 3703 entered the DLD register on 23 April 2025, with the escrow account opened at Emirates Islamic Bank.
Enabling Works and Site Mobilization
The April 2026 inspection classified Montura 3 under enabling works, with mobilization underway and infrastructure works progressing across the plot 2078 parcel.
Foundations and Villa Superstructure
The stage where the 219 G plus 1 plus roof villas first appear in the certified record, and where the payment plan's 30% completion instalment is triggered.
Envelope, Roads and Community Works
External walls, roofs and the internal road network across the cluster, running against the two instalments the schedule attaches to 50% and 70% completion.
Finishing, Landscaping and Handover
Internal finishes, private gardens and pool terraces, and community landscaping, closing on the 90% instalment and the 30 June 2029 registered completion date.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Montura 3 at Grand Polo Club & Resort's own record.
Buyer Position
Tracking Your Position at Montura 3 at Grand Polo Club & Resort
This page is one of four project resources that together cover a Montura 3 at Grand Polo Club & Resort purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Montura 3 at Grand Polo Club & Resort Construction Updates
The certified progress record for Montura 3, running from 13 March 2025 through each published inspection.

Montura 3 at Grand Polo Club & Resort Golden Visa: Single Villa
Montura 3 at Grand Polo Club & Resort, a 219-villa Emaar release, qualifies at both its 4 and 5 bedroom typologies.
Read the Montura 3 at Grand Polo Club & Resort Golden Visa Guide
Montura 3 at Grand Polo Club & Resort Escrow at Emirates Islamic
Emirates Islamic holds Montura 3 at Grand Polo Club & Resort escrow, DLD project 3703: 219 units, 1.06% certified April 2026.
Verify the Montura 3 at Grand Polo Club & Resort Escrow AccountApproaching Handover
Between 1.06% and Handover: What Montura 3 at Grand Polo Club & Resort Buyers Should Do Now
Five of the nine instalments on this schedule are released by construction completion milestones rather than by calendar dates, which makes the certified percentage the trigger mechanism for most of what you still owe. The stretch before the 30% trigger arrives is the quiet part of this build, and it is the right time to settle the three checks below rather than running them against a payment deadline.
First, confirm where your money lands: every instalment on this project should reach only the DLD-regulated account held with Emirates Islamic Bank, and the Montura 3 escrow account page sets out how to run that lookup against the register for project 3703.
Second, map your own instalment schedule against the readings published here, starting with the April 2026 progress reading, so you know which of the 30%, 50%, 70% and 90% triggers are still ahead of you rather than assuming from the calendar dates.
Third, if residency is part of why you bought, settle eligibility early through the Golden Visa guide for Montura 3, since the route differs before and after the title deed exists and handover is years out.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore Grand Polo Dubai Structure
One cluster's percentage says little about the masterplan forming around it. These three pages hold the Montura 3 reading against its neighbouring releases, its community, and the developer building all of them:

Grand Polo Dubai Properties for Sale
Browse villas and townhouses for sale at Grand Polo Club & Resort, comparing Equiterra, Selvara and Chevalia.
See Grand Polo Dubai Properties for Sale
Grand Polo Dubai Community Overview
Read the Grand Polo Club & Resort guide: Emaar's 60 million sq ft equestrian estate community of villas and townhouses.
Explore the Grand Polo Dubai Community
Emaar Properties: Burj Khalifa, Downtown Dubai and Twenty Master Communities
Emaar, founded in 1997, built Burj Khalifa and Downtown Dubai and has delivered over 85,000 homes across twenty master communities.
View the Emaar Properties Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
Montura 3 at Grand Polo Club & Resort Construction Updates Frequently Asked Questions
Montura 3 is an active DLD-registered project (number 3703) sitting in its enabling works phase, recorded at 1.06% at the RERA inspection of 21 April 2026. The single dated reading behind that figure is set out in the inspection timeline above.
The 21 April 2026 inspection recorded 1.06% construction progress and classified the project under enabling works, with the inspector finding mobilization underway and infrastructure activity across the parcel. The register also holds 0.55% with no date beside it, which leaves the 0.51 point difference unattached to any measurable period. The site report sits in the Montura 3 April 2026 construction update.
The DLD register carries 30 June 2029 as the completion date for project 3703, which falls inside the Q2 2029 handover window quoted to buyers. Set against the 1.06% recorded on 21 April 2026, 98.94 percentage points of certified progress remain to be logged between that reading and completion, and this record is rewritten as each cycle lands.
RERA describes the development as 219 villas built to a G plus 1 plus roof format, dividing into 187 four bedroom homes and 32 five bedroom homes. Built-up area runs at approximately 3,840 sq ft for the four bedroom villa and 5,137 sq ft for the five bedroom villa.
Only one dated reading exists so far, which means velocity between inspections cannot be measured yet. Averaged across the 13 months from the 13 March 2025 construction start to the 1.06% of 21 April 2026, the derived rate is about 0.1 percentage points per month, while closing the remaining 98.94 points by 30 June 2029 implies roughly 2.6 points per month from here. Both numbers are derived rather than observed, and the working is in the pace analysis above.
Construction commencement was recorded on 13 March 2025, with DLD registration of project 3703 following on 23 April 2025. The first dated reading in the register arrived thirteen months after that start, on 21 April 2026, at 1.06%.
At 1.06% the certified record covers site works rather than villas, with the RERA progress indicator set to enabling works and mobilization and infrastructure activity logged on the parcel. Nothing above ground level has entered the record yet, and the payment schedule's first construction-linked trigger at 30% completion remains ahead.
Montura 3 is the third Montura release inside the community, built on plot 2078 and recorded by the DLD under Dubai Investment Park Second. Its position on the eastern flank of the masterplan means the roads, utilities and services reaching the cluster are being formed over the same years as the 219 villas themselves. Layout detail is covered in the Montura 3 at Grand Polo project guide.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the Montura 3 at Grand Polo Club & Resort construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.