
Meraas · Nad Al Sheba Gardens
Nad Al Sheba Gardens Phase 12 Construction Updates
The DLD Record for 97 G+2 Villas in Nad Al Sheba, Opening at 0%
Nad Al Sheba Gardens Phase 12 stood at 0% on the DLD register at its 27 January 2026 inspection, the baseline its 97 villas are measured from.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
Nad Al Sheba Gardens Phase 12 at a Glance
Registered with the Dubai Land Department as project 4352, Nad Al Sheba Gardens Phase 12 brings 97 G+2 villas to the gated Meraas community in Nad Al Sheba, every one a 4 Bedroom or 5 Bedroom home. What sets its record apart is the order of events: the only inspection so far, a 0% reading dated 27 January 2026, came before the register's own start and registration entries of March 2026, so this page opens on a pre-construction baseline rather than on a site already at work. The image at the top of the page is a project rendering of the planned villas, not a view of the site.
4352
Active
01 March 2026
97 G+2 villas
56,182.98 sq m
01 August 2029 (DLD)
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
Nad Al Sheba Gardens Phase 12 Construction Update Timeline
A single reading makes up this record so far: 0% on 27 January 2026, logged while the inspector found no construction activities under way and filed the status Not Started. The one dot on the track and the one row in the table carry that date, and the row links the January 2026 update where the visit is set out in full. The register's own dates come after the reading rather than before it: a registered start of 1 March 2026, registration on 6 March 2026, and a registered completion of 1 August 2029, which sits inside the Q3 2029 handover quarter.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| January 2026 | 0% | 27 January 2026 | View the January 2026 update |
Pace Analysis
How Fast Nad Al Sheba Gardens Phase 12 Has Been Built
A pace figure is the change between two dated readings over the time that separates them, and Phase 12 has only one reading so far. This is what the record holds today:
- 27 Jan 2026: first and only reading, DLD register 0%, inspection status Not StartedBaseline, no pace yet
- Measured pace between consecutive dated readingsNeeds a second reading
That gap is information in its own right. A 0% baseline taken 33 days before the registered start cannot be turned into a meaningful monthly rate, and averaging it across the years to 1 August 2029 would yield a number about the calendar rather than the site. The figure worth waiting for arrives with the next inspection entry for project 4352: the first reading above zero will show when work on the 97 villas began to register, and the span from 27 January 2026 to that date becomes the first measured interval this page can report. For an end user weighing a Q3 2029 move, or an investor deciding when to enter, the record today proves the starting line, not the speed.
Get the Next Inspection Figure First
Tell me you are tracking Nad Al Sheba Gardens Phase 12 and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About Nad Al Sheba Gardens Phase 12 at Nad Al Sheba Gardens
The January 2026 reading of 0% only gains meaning beside what will eventually stand on the parcel. The project guide, shown here through a project rendering rather than a site image, covers what Phase 12 buyers are waiting on:

Nad Al Sheba Gardens Phase 12: 97 Meraas Villas Built G+2
Nad Al Sheba Gardens Phase 12 is a Meraas release of 97 four and five bedroom villas inside the master community.
View the Nad Al Sheba Gardens Phase 12 Project GuideConsidering a Pre-Construction Entry?
Phase 12 is listed as a new launch, and which villas remain open across the two sizes changes as reservations are made. If the 0% reading of 27 January 2026 is your reason for looking now, ask me what is currently available before the choice narrows.
Ask About Remaining Availability on WhatsAppStage Record
Nad Al Sheba Gardens Phase 12 Build Stages, Mapped to the Inspections
On the evidence so far, Phase 12 has entered only the first of these five stages. Each card shows where the 27 January 2026 reading places the build and what kind of reading will move it on, so the record can be read forward as each new inspection of the 97 villas arrives.
Pre-Construction Baseline and Registration
The 27 January 2026 inspection found no construction activities started and filed Phase 12 as Not Started at a 0% register reading; the register then logged a 1 March 2026 start and 6 March 2026 registration.
Site Preparation and Foundations
Not yet in the record: the first inspection to move off zero will date the start of ground works for the 97 villas on the Phase 12 parcel.
G+2 Villa Structures
Ground-plus-two frames for every 4 Bedroom and 5 Bedroom villa; no reading had reached this stage at the January 2026 baseline.
Envelopes, Services and Plot Landscaping
Facades, glazing, building services and garden works across the phase; readings in this band will show how close the villas stand to the Q3 2029 window.
Finishing, Final Inspections and Handover
Interior finishing and closing inspections before keys, set against a Q3 2029 handover and the registered completion of 1 August 2029 in the DLD record.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Nad Al Sheba Gardens Phase 12's own record.
Buyer Position
Tracking Your Position at Nad Al Sheba Gardens Phase 12
This page is one of four project resources that together cover a Nad Al Sheba Gardens Phase 12 purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Nad Al Sheba Gardens Phase 12 Construction Updates
This page: every DLD register reading for Phase 12, opening at 0% on 27 January 2026.

Nad Al Sheba Gardens Phase 12 Golden Visa: 97 G+2 Villas
Meraas's Nad Al Sheba Gardens Phase 12, 97 G+2 villas, clears the threshold at both 4 and 5 bedroom types.
Read the Nad Al Sheba Gardens Phase 12 Golden Visa Guide
Nad Al Sheba Gardens Phase 12 Escrow: Meraas's Newest Account
Meraas's Nad Al Sheba Gardens Phase 12, DLD project 4352, escrows 97 units at Emirates NBD, 0% certified January 2026.
Verify the Nad Al Sheba Gardens Phase 12 Escrow AccountApproaching Handover
Between 0% and Handover: What Nad Al Sheba Gardens Phase 12 Buyers Should Do Now
At Phase 12 the distance to cover is not between a high reading and handover but between the 27 January 2026 baseline and the first inspection that shows work on the villas, and money paid in that interval is paid before the register records any work on the parcel. That is why the three checks below belong before your first transfer, not after the next reading arrives.
First, confirm where your payments go: the Nad Al Sheba Gardens Phase 12 escrow account page shows which account receives funds for project 4352 and how releases follow verified construction progress.
Second, if residency is part of the plan, settle the question early through the Nad Al Sheba Gardens Phase 12 Golden Visa eligibility guide, which sets out how an off-plan villa is assessed before its Q3 2029 handover.
Third, keep the starting point on file: the Nad Al Sheba Gardens Phase 12 January 2026 inspection record documents the 0% reading and the Not Started status that every later figure on this page will be measured against.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore Nad Al Sheba Gardens Structure
The Phase 12 record follows one parcel. These three pages place it among the homes already listed in Nad Al Sheba Gardens, the community whose shared facilities its owners will use, and the developer accountable for the build:

Nad Al Sheba Gardens: Phase 11 Townhouses and Villas Near Meydan
Nad Al Sheba Gardens is a gated, low-density Meraas community of 1,817 planned homes across 12 phases, close to Meydan.
See Nad Al Sheba Gardens Properties for Sale
Nad Al Sheba Gardens Community Overview
Discover Nad Al Sheba Gardens by Meraas, a 13 million sq ft master community featuring 12 residential phases, luxury villas and townhouses, landscaped parks, family amenities, and prime connectivity near Downtown Dubai.
Explore the Nad Al Sheba Gardens Community
Meraas: Lifestyle Destinations From City Walk to Port de La Mer
Meraas is the name behind City Walk, Bluewaters Island and Madinat Jumeirah Living, from beachfront communities to luxury mixed-use districts.
View the Meraas Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
Nad Al Sheba Gardens Phase 12 Construction Updates Frequently Asked Questions
Nad Al Sheba Gardens Phase 12, DLD project 4352, is listed as Active, and its latest register reading is 0%, recorded at the inspection of 27 January 2026 with the status Not Started. That reading was 258 days old at this page's October 2026 revision, so the Dubai REST entry for project 4352 is where to confirm whether a newer inspection has since been added; the full record sits in the Phase 12 inspection timeline.
One. The Nad Al Sheba Gardens Phase 12 record holds a single dated reading, 0% on 27 January 2026, and no earlier inspection exists, so there is no point change to report. The visit behind it is set out in the Nad Al Sheba Gardens Phase 12 construction update for January 2026, and each further reading will join this record with its own date.
Pace needs two dated readings, and Nad Al Sheba Gardens Phase 12 has one: 0% on 27 January 2026. Spreading a zero baseline across the months to the registered completion of 1 August 2029 would describe the calendar rather than the site, so no rate is published until the next inspection adds a second date and figure. The reasoning is laid out in the Phase 12 pace analysis.
They are separate records that agree. Nad Al Sheba Gardens Phase 12 is scheduled for handover in Q3 2029, and 1 August 2029 is the completion date stored in the DLD register for project 4352, which falls inside that quarter. The register date had not passed by this page's October 2026 revision, and any change to it would show in a later Dubai REST entry.
The Dubai Land Department lists Nad Al Sheba Gardens Phase 12 as registered on 6 March 2026, with its registered start dated 1 March 2026. Both entries post-date the only inspection on file, dated 27 January 2026, so the 0% reading sits ahead of the register's own dates in this record, and the sequence is shown here in the order the register gives it.
The record for Nad Al Sheba Gardens Phase 12 covers 97 villas, all G+2, built in 4 Bedroom and 5 Bedroom sizes, and the 27 January 2026 reading of 0% applies to all of them. Both villa sizes are tracked together under the one DLD project number, 4352, so each percentage describes the whole phase rather than either type on its own.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the Nad Al Sheba Gardens Phase 12 construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.