Pearl House 4 by Imtiaz in Jumeirah Village Circle project rendering used for the October 2026 construction update showing the planned residential tower with illuminated podium and palm trees in Dubai - Presented by Tohid Fetrat

Imtiaz · Jumeirah Village Circle · Construction Update

Pearl House 4 Construction Update - October 2026

October 2026 DLD Register Reading Records Pearl House 4 at 17.93% Construction Progress in Jumeirah Village Circle

Substructure, superstructure and MEP works were all under way at Pearl House 4 when RERA inspected on 7 October 2026, with the DLD register recording 17.93 percent.

Direct advisor access. Every message answered personally, never by a call center.

17.93%DLD Register Reading
7 October 2026Inspection Date
Q1 2028Expected Handover
4129DLD Project Number

DLD Register Data

Pearl House 4 Construction Snapshot

A 4.68 point rise on the previous DLD register reading of 13.25% puts Pearl House 4 at 17.93% on 7 October 2026, late in the enabling and foundations band, with the frame of the tower under way at inspection. The register does not date the 13.25% reading, so the rise cannot be turned into a monthly pace.

Project Name

Pearl House 4 by Imtiaz

Project Number

4129

Project Status

Active

Construction Progress

17.93%

Inspection Date

7 October 2026

Construction Start

30 October 2025

Total Units

209 residential units

Total Built Area

14,832.10 sq m

Expected Completion

29 February 2028

Data source: the Dubai Land Department project register for project 4129, which shows the 17.93% reading against the RERA inspection of 7 October 2026, and the RERA Independent Progress Monitoring Report of the same date, which records site activity but prints no percentage. Construction tracking against RERA inspection data runs across the full tohidfetrat.com project portfolio and is reviewed after every published cycle. The image at the top of this page is a developer rendering of the planned tower, not a site photograph. Last updated: October 2026.

Want each new reading the day it publishes? Message me on WhatsApp and I will send it to you directly: one message per inspection cycle, nothing else. Message me on WhatsApp

This Inspection Cycle

Pearl House 4 Construction Progress Summary

Pearl House 4 entered the DLD register on 11 October 2025 and construction started on 30 October 2025, so the 7 October 2026 reading reflects 342 days of recorded works. RERA's monitoring report for that visit lists the main contract as progressing: the ground has been prepared and the foundations are in, and the effort on site has moved to the substructure, the frame, and the building services that run through it.

Completed
  • Enabling works, recorded as completed in the RERA report of 7 October 2026
  • Foundation works, recorded as completed at the same inspection
  • DLD registration on 11 October 2025 and construction start on 30 October 2025
In Progress at 17.93%
  • Substructure works for the G+4P+13 retail and residential tower
  • Superstructure works, the frame that will carry the 209 residences
  • MEP works: mechanical, electrical, and plumbing, ongoing alongside the frame
  • Main contract, reported by RERA as progressing
Ahead of Handover
  • Completing the frame through the residential floors to the roof
  • Facade, interior finishes, and the furnished apartments specified by Imtiaz
  • The Level One kids' pool and the rooftop sky pool amenity decks
  • Handover expected in Q1 2028, with a registered completion date of 29 February 2028
Next inspectionPosted in the DLD project register after the next RERA site visit; no date is published in advance, and this record adds each reading once it appears.
Completion targetHandover expected in Q1 2028; the registered completion date of 29 February 2028 sits 510 days after this inspection.
Remaining distance82.07 percentage points separate the 17.93% reading of 7 October 2026 from 100%.
Pace arithmetic17.93 points over the 342 days since the recorded start averages about 1.57 points per month; reaching 100% by 29 February 2028 works out at about 4.83 points per month over the remaining 510 days. Arithmetic, not a forecast.

Payment Timing and Progress

What 17.93% Progress Means for Pearl House 4 Buyers

Pearl House 4 runs on a 60/40 plan tied to calendar dates rather than construction stages, so no register reading triggers a payment; what the reading shows is how far the building has moved against the money already scheduled. On the developer's dated schedule, 40% of the price had been called by the 7 October 2026 reading, and 50% had fallen due by 21 October 2026 once the 15 October 2026 instalment passed. At this early stage, four actions matter most.

Before Your Next Instalment

Verify the escrow account

Every instalment should go only to the DLD regulated escrow account registered for project 4129 with First Abu Dhabi Bank. Pearl House 4 escrow account verification is the check to run before any transfer; the lookup takes about two minutes against the official DLD project record, where the project is listed as Pearl House Iv By Imtiaz.

Before Signing

Reread your SPA payment schedule

Check how your sale and purchase agreement dates each instalment and defines the 40% due on completion, and map those clauses against the Q1 2028 handover. Not sure how your installments map to this reading? Send me your SPA schedule and I will map it against the recorded register readings.

Within Weeks of Booking

Confirm your Oqood registration

An off plan purchase is recorded with the Dubai Land Department through Oqood registration, which ties your unit to project 4129 in the register. Ask for your Oqood registration confirmation and check that the unit, price, and buyer names match your SPA before the next dated instalment.

Every Cycle

Track the readings against the schedule

Several readings will be posted before the Q1 2028 handover, while the next dated instalment is 5% on 15 February 2027. The Pearl House 4 construction updates hub logs each dated reading so you can compare the building with the payments still ahead.

General framework, not legal advice: instalment dates, completion definitions, and registration obligations are set by your individual SPA and the DLD record, and both should be read directly.

Buying at 17.93%?

Entering this early trades certainty for time: the frame is still rising and handover is expected in Q1 2028, and because the plan is date based, a buyer signing now settles the instalments already due under the developer's current terms. Every payment goes to the DLD-registered escrow account for project 4129, released as construction progress is recorded through RERA inspections.

Entering Now at 17.93%
  • Enabling and foundation works recorded as completed by RERA on 7 October 2026
  • Handover expected in Q1 2028
  • 40% of the 60/40 plan held back until completion
Typical Late Stage Entry
  • Frame and facade largely in place, fewer open construction questions
  • A shorter wait between signing and handover
  • Less payment runway, often at later release pricing
AED 765K ≈ USD 208KStarting Price
60/40 Plan40% Due on Completion
Q1 2028Expected Handover
Ask What Is Available at Pearl House 4

Limited units available, per the project page as of this update; availability shifts between cycles.

About the Development

Pearl House 4 Project Details

Pearl House 4 by Imtiaz in Jumeirah Village Circle project rendering of a residential tower with stacked balconies, a curved podium facade and palm-lined landscaped street in Dubai - Presented by Tohid Fetrat
Jumeirah Village Circle · Imtiaz

With enabling and foundation works recorded as completed and the frame under way, Pearl House 4 is an early stage G+4P+13 tower of 209 apartments that Imtiaz delivers fully furnished, above ground floor retail units. Starting prices: AED 765K ≈ USD 208K.

For buyers entering at this stage, the trade off is the longest remaining wait, to a Q1 2028 handover, against developer pricing and a 40% balance that stays deferred until completion.

Pearl House 4 by Imtiaz Project Guide

Site Context This Cycle

Explore Pearl House 4 Location on Dubai Map

Pearl House 4 occupies a single tower plot inside the ring road layout of Jumeirah Village Circle, and the developer's aerial location map shows it surrounded by established buildings rather than open land. That setting frames this cycle: with enabling and foundation works recorded as completed on 7 October 2026, substructure, superstructure, and MEP packages were proceeding together within one contained plot.

Because JVC already runs as a lived-in community, with Circle Mall nearby and, per Imtiaz, schools, shops, and cafes within easy reach, the tower is being built into a functioning neighborhood rather than ahead of one. For early stage buyers that moves the main uncertainty onto the building itself, which is why the dated readings matter more than district plans between now and the Q1 2028 handover. See the plot's position on the interactive Dubai real estate map. See the project’s position on the interactive Dubai real estate map.

Interactive Dubai real estate map preview
Click to view Pearl House 4 by Imtiaz on Dubai Map

Buyer Resources for This Project

Investing in Pearl House 4 During Early Construction

While the foundations give way to the frame, the questions that matter most are whether your instalments are protected and what the purchase can unlock for residency. Each resource below is matched to where Pearl House 4 stands in October 2026.

Pearl House 4 by Imtiaz in Jumeirah Village Circle construction updates cover image featuring a project rendering of a residential tower, landscaped street and palm trees in Dubai - Presented by Tohid Fetrat
You Are Here

Pearl House 4 Construction Updates

This page: the October 2026 DLD register reading for Pearl House 4 and RERA site notes.

Pearl House 4 by Imtiaz in Jumeirah Village Circle Golden Visa concept graphic with a gold card above a project rendering of tiered residential balconies and skyline in Dubai - Presented by Tohid Fetrat

Pearl House 4 by Imtiaz Golden Visa: A Retail and Residential Tower

Pearl House 4, Imtiaz Developments' 209-residence freehold retail and residential tower in Jumeirah Village Circle, registered under Oqood now.

Read Pearl House 4 Golden Visa Guide
Pearl House 4 by Imtiaz in Jumeirah Village Circle escrow account concept graphic with a shield and padlock above a rendered rooftop pool terrace and lounge seating in Dubai - Presented by Tohid Fetrat

Pearl House 4 Escrow: Imtiaz Developments in JVC

Imtiaz's Pearl House 4 is DLD project 4129, 211 units escrowed at First Abu Dhabi Bank, 17.93% certified October 2026.

Verify Pearl House 4 Escrow Account

Update Timeline

Other Pearl House 4 Construction Updates

October 2026 is the first monthly record for Pearl House 4 on this site; each later register reading joins the timeline as it is posted, so the build can be followed reading by reading through to handover.

All Pearl House 4 Construction Updates

FAQs

Pearl House 4 Construction Progress in October 2026: Frequently Asked Questions

The Dubai Land Department project register shows Pearl House 4 at 17.93% against the RERA inspection of 7 October 2026. The RERA monitoring report for that visit prints no percentage of its own, so 17.93% is the DLD register reading for project 4129, not a figure taken from the report.

Yes, as of the 7 October 2026 record. Handover is expected in Q1 2028, and the registered completion date in the DLD register is 29 February 2028, which falls inside that quarter. Registered dates can be revised between inspection cycles, and any change would appear with a later reading; how the schedule is followed from cycle to cycle is covered on the Pearl House 4 construction updates hub.

The register's inspection card dated 7 October 2026 shows a previous inspection reading of 13.25% next to the current 17.93%, but it does not show when that earlier reading was taken. Because the interval between the two is unknown, no monthly pace can be calculated from them.

The RERA Independent Progress Monitoring Report records enabling works and foundation works as completed, with substructure, superstructure and MEP works ongoing at the time of inspection. It describes the project as G+4P+13F+R, retail and residential, gives the progress status as Main Contract, Progressing, and carries inspection photographs from the visit.

The DLD register records Pearl House 4 as registered on 11 October 2025 and gives 30 October 2025 as the construction start, 19 days later. The 17.93% reading of 7 October 2026 therefore arrives 342 days after the recorded start of works.

No. The image is a developer rendering of the planned Pearl House 4 tower, used to identify the project, and it shows no construction stage. The evidence for the site on 7 October 2026 is the RERA report and its inspection photographs, which belong to the official record and are not reproduced on this page.

A Question the FAQ Can Not Answer?

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is helping you read the October 2026 inspection record for Pearl House 4 correctly before your next payment decision. Client identities and transactions are never published or referenced. Message me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.