Pearl House 4 by Imtiaz in Jumeirah Village Circle construction updates cover image featuring a project rendering of a residential tower, landscaped street and palm trees in Dubai - Presented by Tohid Fetrat

Imtiaz · Jumeirah Village Circle

Pearl House 4 Construction Updates

One JVC Tower, Logged Reading by Reading from the Foundations Up

Pearl House 4 by Imtiaz stood at 17.93% in the DLD register on 7 October 2026, an opening reading that fixes where this JVC tower's climb begins.

Construction tracking against RERA inspection data, updated after every recorded inspection.

Direct advisor access. Every message answered personally, never by a call center.

17.93%Construction Progress
07 October 2026Latest RERA Inspection
209 residential unitsTotal Units
Project 4129DLD Registration

Construction Snapshot

Pearl House 4 at a Glance

Pearl House 4 by Imtiaz is a single G+4P+13 retail and residential tower of 209 apartments in Jumeirah Village Circle, entered in the DLD register as project 4129 on 11 October 2025, with works starting 19 days later on 30 October 2025. Its record therefore opens almost at ground level: the first dated register reading, 17.93% on 7 October 2026, arrived with enabling works and foundations reported as completed by RERA and the substructure, frame and building services all running at once on one compact JVC plot. The six anchors below are the register entries this page measures every later reading against.

DLD Project Number

4129

Project Status

Active

Construction Start

30 October 2025

Total Units

209 residential units

Total Built-Up Area

14,832.10 sq m

Registered Completion Date

29 February 2028 (DLD)

Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.

Inspection Record

Pearl House 4 Construction Update Timeline

This record holds one dated reading so far: 17.93% against the RERA inspection of 7 October 2026, taken 342 days after the 30 October 2025 start. The same register card also lists a previous reading of 13.25% without a date, so it appears on the track as an unlabelled dot and not as a table row; the 4.68-point rise between the two cannot be timed. Each later reading for this tower will join the table with its own date and a link to its monthly update.

Inspection MonthConstruction ProgressInspection DateFull Update
October 202617.93%07 October 2026View the October 2026 update

Pace Analysis

How Fast Pearl House 4 Has Been Built

With a single dated reading there is no inspection pair to time yet, so the two figures below are arithmetic on the register dates, not a forecast:

  • 30 Oct 2025 to 07 Oct 2026: enabling works, foundations and the start of the frame, from the construction start to 17.93% at the 7 October 2026 readingAbout 1.57 points per month
  • 07 Oct 2026 to 29 Feb 2028: the remaining 82.07 points from the 7 October 2026 reading to 100% at the registered completion dateAbout 4.83 points per month

The first figure spreads 17.93 points across 342 days, and those days were spent mostly at or below ground level: clearing and preparing the plot, then foundations, then the substructure that RERA found under way on 7 October 2026. The second figure covers the 510 days left to the 29 February 2028 registered completion date, which carries the frame through the residential floors to the roof, the facade, and the fit-out of furnished apartments. The two numbers describe different kinds of work, so the gap between them is a question the next dated reading starts to answer rather than a verdict. For an investor, that second reading will give this tower its first measured pace; for an end user planning a move, the registered date sits inside the Q1 2028 handover quarter, and each new row in the timeline shows how the build is tracking toward it.

Get the Next Inspection Figure First

Tell me you are tracking Pearl House 4 and I will send you the next recorded figure and site photos directly, ahead of the page update.

Get the Next Update on WhatsApp

Project Profile

About Pearl House 4 at JVC

A 17.93% reading on 7 October 2026 means most of this tower is still to come. The project guide shows what that remaining build turns into:

Pearl House 4 by Imtiaz in Jumeirah Village Circle project rendering of a residential tower with stacked balconies, a curved podium facade and palm-lined landscaped street in Dubai - Presented by Tohid Fetrat

Pearl House 4: Imtiaz Homes Over Retail in Jumeirah Village Circle

Pearl House 4 by Imtiaz is a JVC tower of 209 fully furnished studio, one and two bedroom apartments above retail.

View the Pearl House 4 Project Guide

Considering an Early-Stage Entry?

Pearl House 4 is selling while its frame rises, and the units on offer shift from one register reading to the next. If the record on this page is what brought you here, ask me what is available today and how the dated plan applies to a purchase made now.

Ask About Remaining Availability on WhatsApp

Stage Record

Pearl House 4 Build Stages, Mapped to the Inspections

Each stage below is pinned to the register dates and the 7 October 2026 RERA notes for this tower, so the card marked current shows exactly where Pearl House 4 stood at its 17.93% reading and the later cards show what that reading has not reached yet.

11 Oct 2025 to 30 Oct 2025

Registration and Site Start

Project 4129 entered the DLD register on 11 October 2025, and construction started 19 days later, on 30 October 2025.

30 Oct 2025 to 07 Oct 2026

Enabling Works and Foundations

Site enabling and foundation works, both recorded as completed in the RERA report of 7 October 2026, 342 days into the build.

Current PhaseUnder way at 17.93% on 07 Oct 2026

Substructure, Frame, and MEP

At the 7 October 2026 inspection the substructure, superstructure and MEP works were ongoing together, with the main contract reported as progressing.

After 07 Oct 2026, no reading yet

Facade, Fit-Out, and Amenity Decks

Enclosing the G+4P+13 tower, finishing the furnished apartments Imtiaz specifies, and building the Level One kids' pool and rooftop sky pool decks.

To 29 Feb 2028, handover Q1 2028

Completion and Handover

The register's completion date of 29 February 2028 sits inside the Q1 2028 handover quarter, 852 days after the recorded construction start.

What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Pearl House 4's own record.

Buyer Position

Tracking Your Position at Pearl House 4

This page is one of four project resources that together cover a Pearl House 4 purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Pearl House 4 by Imtiaz in Jumeirah Village Circle construction updates cover image featuring a project rendering of a residential tower, landscaped street and palm trees in Dubai - Presented by Tohid Fetrat
You Are Here

Pearl House 4 Construction Updates

This page: every dated DLD register reading for Pearl House 4 since the October 2025 start.

Pearl House 4 by Imtiaz in Jumeirah Village Circle Golden Visa concept graphic with a gold card above a project rendering of tiered residential balconies and skyline in Dubai - Presented by Tohid Fetrat

Pearl House 4 by Imtiaz Golden Visa: A Retail and Residential Tower

Pearl House 4, Imtiaz Developments' 209-residence freehold retail and residential tower in Jumeirah Village Circle, registered under Oqood now.

Read the Pearl House 4 Golden Visa Guide
Pearl House 4 by Imtiaz in Jumeirah Village Circle escrow account concept graphic with a shield and padlock above a rendered rooftop pool terrace and lounge seating in Dubai - Presented by Tohid Fetrat

Pearl House 4 Escrow: Imtiaz Developments in JVC

Imtiaz's Pearl House 4 is DLD project 4129, 211 units escrowed at First Abu Dhabi Bank, 17.93% certified October 2026.

Verify the Pearl House 4 Escrow Account

Approaching Handover

Between 17.93% and Handover: What Pearl House 4 Buyers Should Do Now

Pearl House 4 runs on a 60/40 plan fixed to calendar dates, so the schedule moves whether or not the register does. On the developer's dated schedule, 40% of the price had fallen due by the 7 October 2026 reading of 17.93%, and 50% by 21 October 2026, with the next 5% set for 15 February 2027. That date arrives well before the frame is finished, so the three checks below belong in the months ahead of it, not the week of the transfer.

First, make sure each transfer goes to the trust account registered for project 4129; the Pearl House 4 escrow account page shows how to confirm the bank and the account before you pay.

Second, if residency is part of your plan, read the Pearl House 4 Golden Visa eligibility breakdown before you settle on a tier, since the apartment prices on the current list fall short of the property threshold on their own.

Third, set the remaining 40% due on completion against your own budget using the full schedule, layouts and furnished specification in the Pearl House 4 by Imtiaz project overview.

Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.

The Wider Picture

Explore JVC Structure

One early reading reads better beside its surroundings. These three pages place the Pearl House 4 build in its market, its community and its developer's portfolio:

Aerial view of Jumeirah Village Circle properties for sale in Dubai showing residential homes, landscaped greenery and the circular community layout, Presented by Tohid Fetrat

Jumeirah Village Circle: Five Imtiaz and Binghatti Towers in New Dubai

Jumeirah Village Circle, Nakheel's freehold ring of ten districts in New Dubai, lists apartments in five Imtiaz and Binghatti towers.

See JVC Properties for Sale
Aerial view of Jumeirah Village Circle (JVC) in Dubai showcasing circular urban planning residential villas green spaces and high-rise buildings with the Dubai skyline in the background. Presented by Tohid Fetrat.

JVC Community Overview

Read the Jumeirah Village Circle guide: Nakheel's freehold community of apartments, townhouses and villas with strong rental yields.

Explore the JVC Community
Exterior view of INARA by Imtiaz featuring a contemporary luxury residential tower with elegant balconies, refined façade design, and landscaped surroundings in Dubai, Presented by Tohid Fetrat

Imtiaz Developments: Fully Furnished Residences in Dubai Islands, JVC and Meydan

Imtiaz Developments, founded in 2011, has completed and under-construction design led residential projects in Meydan, JVC and Dubai Islands.

View the Imtiaz Developments Developer Profile

Construction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.

FAQs

Pearl House 4 Construction Updates Frequently Asked Questions

Pearl House 4 by Imtiaz is an active DLD-registered project, number 4129, recorded at 17.93% in the Dubai Land Department project register against the RERA inspection of 7 October 2026. At that inspection the enabling and foundation works were reported as completed, while the substructure, superstructure and MEP works were ongoing. The dated record sits in the inspection timeline above.

Every percentage on this page is a DLD register reading for project 4129, listed on Dubai REST under the register name Pearl House Iv By Imtiaz. The register's inspection card dated 07-10-2026 shows the 17.93% reading of 7 October 2026, while the RERA monitoring report of the same date describes site activity and prints no percentage. Each new dated reading becomes a timeline row linked to its monthly update, starting with the Pearl House 4 October 2026 construction update.

The DLD register gives Pearl House 4 a completion date of 29 February 2028, which falls inside the expected Q1 2028 handover quarter, so the two dates agree. That registered date was still 510 days away at the 7 October 2026 reading of 17.93% and has not lapsed. Registered dates can be revised by the developer through the register, and this record notes any change when a later reading shows it.

Pearl House 4 has averaged about 1.57 points per month since its 30 October 2025 start: 17.93 points over the 342 days to the 7 October 2026 reading. Reaching 100% by the 29 February 2028 registered completion date works out at about 4.83 points per month over the remaining 510 days. Both figures are arithmetic, not a forecast, and a measured pace becomes possible once a second dated reading is posted; the working is set out in the pace analysis above.

Pearl House 4 holds 209 residential units: studio, 1 bedroom and 2 bedroom apartments that Imtiaz delivers fully furnished, alongside retail units at ground level. The Imtiaz fact sheet gives the building configuration as G+4P+13, and the RERA report of 7 October 2026 describes the project as G+4P+13F+R, retail and residential. The developer's plans place a kids' pool at Level One and a sky pool, clubhouse and outdoor cinema on the roof.

The Pearl House 4 timeline runs from DLD registration on 11 October 2025 and a construction start on 30 October 2025 to the first dated reading, 17.93% on 7 October 2026, then on to a registered completion date of 29 February 2028 and an expected Q1 2028 handover. Start to registered completion spans 852 days, and the 7 October 2026 reading came 342 days into that span.

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is keeping the Pearl House 4 construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.