Safa One de GRISOGONO by DAMAC Properties in Safa Park project rendering used for the July 2026 construction update showing the planned twin tower design in split daytime and sunset aerial views beside Sheikh Zayed Road and the Dubai coastline in Dubai - Presented by Tohid Fetrat

DAMAC · Safa Park · Construction Update

Safa One de GRISOGONO Construction Update - July 2026

July 2026 DLD Register Reading Lifts Safa One to 68.66% Construction Progress in Safa Park

Glazed facades, plastered internal walls and exposed corridor ceiling services featured in Safa One's 15 July 2026 inspection, with envelope, finishes and MEP works still progressing.

Direct advisor access. Every message answered personally, never by a call center.

68.66%DLD Register Reading
15 July 2026Inspection Date
Q4 2026Expected Handover
2374DLD Project Number

Verified DLD Inspection Data

Safa One Construction Snapshot

A 9.83 point rise since the 24 March 2026 reading took Safa One to 68.66% on 15 July 2026, the top of the envelope and MEP band and 1.34 points short of the finishing band, where snagging and completion clauses move to the front of a buyer's file.

Project Name

Safa One de GRISOGONO by DAMAC

Project Number

2374

Project Status

Active

Construction Progress

68.66%

Inspection Date

15 July 2026

Construction Start

1 June 2022

Total Units

511 residential units

Total Built Area

70,342.70 sq m

Expected Completion

30 December 2025

Data source: the Dubai Land Department project register reading dated 15 July 2026, the day of the RERA inspection, whose report records the stage notes and prints no percentage. Safa One is registered on the DLD project register as DAMAC CITY, project 2374. The registered completion date of 30 December 2025 had lapsed 197 days before this inspection; the handover quoted for buyers is Q4 2026. This is the latest reading in the supplied record and was 76 days old when the page was prepared on 29 September 2026, so re-verify project 2374 on Dubai REST before relying on it. The image at the top of this page is a project rendering of the planned twin towers, not a photograph of the site. Construction tracking against RERA inspection data runs across the full tohidfetrat.com project portfolio and is reviewed after every published cycle. Last updated: July 2026.

Want each new reading the day it publishes? Message me on WhatsApp and I will send it to you directly: one message per inspection cycle, nothing else. Message me on WhatsApp

This Inspection Cycle

Safa One Construction Progress Summary

Between the 24 March and 15 July 2026 register readings, Safa One moved from 58.83% to 68.66%, a 9.83 point gain over 113 days, or about 2.61 points a month. That is nearly twice the whole-build average of about 1.37 points a month since the 1 June 2022 start; both are derived arithmetic on a 30-day month, not a forecast.

Completed
  • Enabling works across the site, substantially completed
  • Foundation works beneath both towers, substantially completed
In Progress at 68.66%
  • Substructure, superstructure and internal works on Tower A (G + 4P + 57) and Tower B (G + 4P + 40), at an advanced stage
  • Envelope works, with glazed facade sections in the inspection photographs
  • Finishes, including plastered internal walls still under scaffold
  • MEP services, with ceiling runs exposed along corridors
  • Mobilization on site, still noted as ongoing
Ahead of Handover
  • The remaining 31.34 points to 100%
  • Closing out envelope, finishes and MEP across both towers
  • Owner handover in Q4 2026
Next inspectionNo later dated reading is in the supplied record; the next one appears in the DLD project register after the next RERA site visit, and this cluster updates with it.
Completion targetOwner handover Q4 2026, a quarter that closes on 31 December 2026, 169 days after this reading. The registered completion date on the DLD record, 30 December 2025, had lapsed 197 days before this inspection.
Remaining distance31.34 percentage points separated the 15 July 2026 reading from 100%.

Payment Linked Progress

What 68.66% Progress Means for Safa One Buyers

Safa One's payment plan runs 20% on booking, 40% during construction and 40% on completion, so at the 68.66% July reading the 40% completion payment was still ahead, due at the Q4 2026 handover on the terms of your sale and purchase agreement. With the finishing trades still open, four actions came to the front after this inspection.

Before the Next Transfer

Verify the escrow account

Any instalment still owed before the Q4 2026 handover should be paid only into the DLD regulated escrow account registered for project 2374. Safa One escrow account verification is the check to run first; the lookup itself takes about two minutes against the official DLD project record.

Before Completion Instalments

Reread your SPA milestone schedule

Find the clauses that schedule the 40% during construction, tie the final 40% to completion and set the handover notice period, then read them against the 68.66% reading and the lapsed 30 December 2025 registered date. Not sure how your instalments map to this reading? Send me your SPA schedule and I will map it against the recorded milestones.

Window Open Now

Book the snagging window

With the Q4 2026 handover inside nine months of the 15 July 2026 reading, Safa One entered the usual booking window for a pre handover inspection even at 68.66%, and duplexes with private pools and interiors on two levels need a longer slot. The Safa One snagging inspection guide sets out what to book before you accept a unit.

Every Cycle

Track the remaining cycles

31.34 points were left after July, and each further dated reading shows how envelope, finishes and MEP works close that distance before Q4 2026. The Safa One construction updates hub lists every reading in date order.

General framework, not legal advice: milestone definitions, notice periods, and fee obligations are set by your individual SPA and the DLD record, and both should be read directly.

Buying at 68.66%?

Entering after the July 2026 reading means buying into twin towers whose structure and internal works were recorded at an advanced stage, with envelope, finishes and MEP still progressing and handover set for Q4 2026 rather than years away. Every payment goes to the DLD-registered escrow account for project 2374, released against construction progress recorded by the Dubai Land Department.

Entering at 68.66%
  • Substructure, superstructure and internal works at an advanced stage on 15 July 2026
  • Handover scheduled for Q4 2026, months rather than years ahead
  • 40% of the 60/40 plan due on completion, not spread over years
Typical Launch Entry
  • Full construction risk carried from the first excavation
  • Handover typically several years after booking
  • Longer instalment runway at launch pricing
AED 2.40M (approx. USD 653K)Starting Price
60/40 Plan40% Due on Completion
Q4 2026Expected Handover
Ask What Is Available at Safa One

Which residences remain open is confirmed per enquiry rather than listed in the inspection record; availability shifts between cycles.

About the Development

Safa One Project Details

Safa One by DAMAC in Safa Park luxury residential towers overlooking Sheikh Zayed Road during daytime in Dubai - Presented by Tohid Fetrat
Safa Park · DAMAC

By the July 2026 inspection Safa One's two towers, 57 and 40 levels above a four-level podium, had frames and internal works at an advanced stage, holding 511 residences from 1 bedroom apartments to 5 bedroom penthouses. Starting prices on the current list: AED 2.40M (approx. USD 653K).

For buyers entering at this reading, the trade off is less instalment runway against a much shorter wait, with the final 40% of the plan due on completion, owner handover set for Q4 2026 and the finishing trades carrying most of the remaining work.

Safa One de GRISOGONO Project Guide

Site Context This Cycle

Explore Safa One Location on Dubai Map

Safa One stands on the Sheikh Zayed Road edge of Safa Park, and the floor-plan brochure turns its upper levels toward Business Bay, the park and western sunset views, so the glazed envelope recorded at the July 2026 inspection is the layer that will frame those outlooks once finishes close inside both towers.

The developer brochure places Dubai International Financial Centre 9 minutes and Dubai Harbour 14 minutes away and describes Safa Park as home to some 200 bird species, so buyers weighing a Q4 2026 handover are moving into a settled central district rather than waiting for its roads and services to arrive. See the project’s position on the interactive Dubai real estate map.

Interactive Dubai real estate map preview
Click to view Safa One de GRISOGONO by DAMAC on Dubai Map

Buyer Resources for This Project

Investing in Safa One During Envelope and Finishes Progress

At 68.66% with handover set for Q4 2026, escrow checks, residency planning and snagging preparation all fall due in the same stretch. Each resource below is matched to where Safa One stood in July 2026.

Safa One de GRISOGONO Construction Updates showing the illuminated twin tower exterior along Sheikh Zayed Road in Dubai Presented by Tohid Fetrat
You Are Here

Safa One Construction Updates

This page: the 15 July 2026 register reading for Safa One, measured against March 2026.

Safa One de GRISOGONO Golden Visa illustration featuring the development with a UAE Golden Visa card in Dubai Presented by Tohid Fetrat

Safa One de GRISOGONO Golden Visa: Jeweller-Branded, Every Tier

DAMAC's Safa One de GRISOGONO, a pair of towers holding 511 units at Safa Park, qualifies at all five tiers.

Read Safa One Golden Visa Guide
Safa One de GRISOGONO Escrow Account illustration featuring the development with security lock and shield symbols in Dubai Presented by Tohid Fetrat

Safa One de GRISOGONO Escrow: DAMAC's Safa Park Account

DAMAC's Safa One de GRISOGONO escrows 511 units at Emirates NBD as DLD project 2374, 68.66% certified July 2026.

Verify Safa One Escrow Account
Safa One de GRISOGONO by DAMAC Properties in Safa Park snagging inspection cover image featuring a luxury bedroom interior with full height glazing overlooking the coastline in Dubai - Presented by Tohid Fetrat

Safa One de GRISOGONO Snagging for the Twin Towers at Safa Park

Safa One de GRISOGONO is DAMAC Properties' freehold twin-tower development on Sheikh Zayed Road, with 511 residential units.

Book Safa One Snagging

Update Timeline

Other Safa One Construction Updates

The July 2026 reading is the latest in the dated Safa One record on this site, following the March 2026 inspection that logged 58.83%.

All Safa One Construction Updates

FAQs

Safa One Construction Progress in July 2026: Frequently Asked Questions

The Dubai Land Department project register moved Safa One from 58.83% on 24 March 2026 to 68.66% on 15 July 2026, a gain of 9.83 points across 113 days. Both figures are register readings shown in the Dubai REST app for project 2374; the RERA inspection reports from those two visits record stage notes but print no percentage. The July entry lists 58.83% as its previous inspection, which ties the two dates into one measured interval.

Spread over the 113 days between the two readings, the 9.83 point gain works out to about 2.61 points a month on a 30-day month. Measured from the 1 June 2022 construction start, the whole build averaged about 1.37 points a month by 15 July 2026, up from about 1.27 at the March reading. These figures are derived arithmetic, not a forecast: one dated interval does not fix the pace of the next.

31.34 percentage points separated the 15 July 2026 reading from 100%, and the handover quoted for buyers is Q4 2026, a quarter that closes on 31 December 2026, 169 days after that reading. The registered completion date on the DLD record, 30 December 2025, had lapsed 197 days before the July inspection, and the supplied record shows no amended date. Under Safa One's 20% / 40% / 40% payment plan, the 40% on completion was the payment still ahead at that reading, falling due at the Q4 2026 handover as each buyer's SPA sets out. These are recorded facts set side by side, not a delivery forecast; the completion and delay clauses of your SPA define your position if the date moves, and the full reading history sits on the Safa One construction updates hub.

The RERA inspection report from 15 July 2026 records envelope, finishes and MEP works progressing at different stages, and lists substructure, superstructure and internal work at an advanced stage, with enabling and foundation work substantially completed and mobilization still ongoing. Its photographs show a tower with a glazed facade beside its sister tower, a plastered internal wall with scaffold still standing, and a corridor with MEP services running through an open ceiling. The register entry for that date carries 12 inspection photographs, against 9 on the March 2026 entry.

Yes, for booking purposes. The practical window for arranging a pre-handover inspection is usually treated as open once a build passes about 70% or its handover is under nine months away; at 68.66% on 15 July 2026 Safa One sat just below the first marker, but its Q4 2026 handover fell well inside nine months. The inspection itself happens once units are finished and the handover notice is issued, and duplexes and penthouses with private pools and interiors on two levels need a longer slot than a standard apartment. What to check and when is set out in the Safa One snagging inspection guide.

Search project 2374 in the Dubai REST app, where Safa One is registered under the name DAMAC CITY, and open its inspection report list: the 15 July 2026 entry shows 68.66% as current progress and 58.83% as the previous inspection. The reading was 76 days old on 29 September 2026, so a newer entry may have replaced it, and the registered completion date shown beside it, 30 December 2025 at this reading, should be checked for any amendment. The downloadable RERA report for the same date gives the stage notes and a main contract status of progressing rather than a percentage.

A Question the FAQ Can Not Answer?

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is helping you read the July 2026 inspection record for Safa One de GRISOGONO correctly before your next payment decision. Client identities and transactions are never published or referenced. Message me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

Get Progress Alerts