DAMAC · Safa Park
Safa One de GRISOGONO Construction Updates
The Dated Register Record Behind DAMAC's Jeweller-Branded Towers at Safa Park
Safa One reached 68.66% on the DLD register at its 15 July 2026 inspection, a climb moving both Safa Park towers into envelope, finishes and MEP work.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
Safa One de GRISOGONO at a Glance
Safa One de GRISOGONO by DAMAC is a 511-residence pair of towers on the Sheikh Zayed Road edge of Safa Park, Tower A rising 57 floors and Tower B 40 floors above a shared four-level podium. The register dates its construction start to 1 June 2022, yet the first dated reading in the supplied record only arrives on 24 March 2026 at 58.83%, so close to four years of enabling, foundation and frame work stand behind one opening figure. The anchors below come from that register record and frame the 68.66% logged on 15 July 2026.
2374
Active
1 June 2022
511 residential units
70,342.70 sq m
30 December 2025
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
Safa One de GRISOGONO Construction Update Timeline
Two dated register readings anchor the Safa One record so far: 58.83% on 24 March 2026 and 68.66% on 15 July 2026, a 9.83 point climb across 113 days. The March entry also lists 42.06% as an earlier inspection figure with no date, so it appears on the track below as a plain dot and stays out of the table. Each table row links the monthly update that carries that visit's inspection notes.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| July 2026 | 68.66% | 15 July 2026 | View the July 2026 update |
| March 2026 | 58.83% | 24 March 2026 | View the March 2026 update |
Reading the dates: the registered completion date for project 2374 on the DLD record is 30 December 2025, and it had lapsed 197 days before the latest reading of 68.66% on 15 July 2026. The handover quoted for buyers is Q4 2026. The supplied record carries no amended registered date, so both dates are shown exactly as recorded.
Pace Analysis
How Fast Safa One de GRISOGONO Has Been Built
Safa One's record holds one measured interval and one lifetime average, and the gap between the two says more than either figure alone:
- 24 Mar 2026 to 15 Jul 2026: envelope, finishes and MEP phase, 58.83% to 68.66% over 113 daysAbout 2.61 points per month
- Jun 2022 to Jul 2026: whole-build average from the 1 June 2022 start to 68.66% over 1,506 daysAbout 1.37 points per month
- Jun 2022 to Jul 2026: whole-build average from the 1 June 2022 start to 68.66% over 1,505 daysAbout 1.37 points per month
The early years of this build are a blank in the dated record: nothing is logged between the 1 June 2022 start and the 58.83% reading of 24 March 2026, so the whole-build rate of about 1.27 points a month at that date folds enabling works, foundations and two tower frames into one number. The single measured interval that follows, March to July 2026, ran at about 2.61 points a month, close to double the lifetime rate, and in 113 days it lifted that lifetime average to about 1.37. That is the pattern of a project whose frames were recorded at an advanced stage and whose envelope, finishes and MEP trades are now carrying the percentage across Tower A and Tower B. Set beside it, 31.34 points remained at the July reading and the handover quoted for buyers is Q4 2026; both are recorded figures placed side by side, and every rate here is derived arithmetic on a 30-day month, not a forecast. For an end user, the next dated reading shows how the finishing trades close that distance; for an investor, it shows whether the March to July rate was a phase or a trend.
Get the Next Inspection Figure First
Tell me you are tracking Safa One de GRISOGONO and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About Safa One de GRISOGONO at Safa Park
A register percentage means something different for a jeweller-branded tower pair with duplexes and penthouses than for a standard apartment block. The project guide covers what the 68.66% is building toward:

Safa One de GRISOGONO: DAMAC's Twin Towers at Safa Park
Safa One de GRISOGONO is DAMAC's twin-tower development at Safa Park on Sheikh Zayed Road, 511 units designed by Killa Design.
View the Safa One de GRISOGONO Project GuideConsidering a Late-Construction Entry?
Safa One's July 2026 reading left 31.34 points to build before the Q4 2026 handover, and which residences remain open keeps changing as that gap narrows. If the record on this page is what brought you here, ask me for current availability before remaining inventory narrows further.
Ask About Remaining Availability on WhatsAppStage Record
Safa One de GRISOGONO Build Stages, Mapped to the Inspections
Each stage below is pinned to the register dates and the two RERA inspection reports in the Safa One record, so the long undated stretch before March 2026 is shown as exactly that rather than filled in.
Registration and Site Start
The DLD record shows the project registered on 18 March 2022 and construction started on 1 June 2022, with a registered completion date of 30 December 2025, since lapsed.
Enabling Works and Foundations
No dated reading covers these years; the 24 March 2026 inspection recorded enabling and foundation works as substantially completed beneath both towers.
Two Tower Superstructures
Tower A at G + 4P + 57 and Tower B at G + 4P + 40: both superstructures, with internal works, were recorded at advanced stages at the March inspection.
Envelope, Finishes and MEP
A 9.83 point gain to 15 July 2026, when envelope, finishes and MEP works were each at a different point of progress, with glazed facades, plastered walls and open corridor ceilings in the inspection photographs.
Completion and Handover
31.34 points separated the July 2026 reading from 100%; the handover quoted for buyers is Q4 2026, and the supplied record shows no amended registered date.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Safa One de GRISOGONO's own record.
Buyer Position
Tracking Your Position at Safa One de GRISOGONO
This page is one of four project resources that together cover a Safa One de GRISOGONO purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Safa One de GRISOGONO Construction Updates
This page: every dated Safa One register reading since the 1 June 2022 construction start.

Safa One de GRISOGONO Golden Visa: Jeweller-Branded, Every Tier
DAMAC's Safa One de GRISOGONO, a pair of towers holding 511 units at Safa Park, qualifies at all five tiers.
Read the Safa One de GRISOGONO Golden Visa Guide
Safa One de GRISOGONO Escrow: DAMAC's Safa Park Account
DAMAC's Safa One de GRISOGONO escrows 511 units at Emirates NBD as DLD project 2374, 68.66% certified July 2026.
Verify the Safa One de GRISOGONO Escrow Account
Safa One de GRISOGONO Snagging for the Twin Towers at Safa Park
Safa One de GRISOGONO is DAMAC Properties' freehold twin-tower development on Sheikh Zayed Road, with 511 residential units.
Book Safa One de GRISOGONO SnaggingApproaching Handover
Between 68.66% and Handover: What Safa One de GRISOGONO Buyers Should Do Now
At the 15 July 2026 reading Safa One sat 1.34 points below 70%, with envelope, finishes and MEP works still moving across both towers, so the priority for a buyer at this stage is tracking payments and readings, with handover preparation building on top as the finishing band nears. The calendar is what makes it pressing: Q4 2026, the handover quoted for buyers, closes on 31 December 2026, 169 days after that reading, so the three steps below belong to this stage and not to the week a handover notice arrives.
First, match every instalment still due against register progress on the Safa One escrow account page, so remaining payments follow recorded construction rather than requests.
Second, follow the dated record itself: the Safa One July 2026 construction update holds the latest inspection notes, and each later reading joins the timeline above with its own date.
Third, if your purchase may carry residency, settle the eligibility path through the Safa One Golden Visa guide while completion is still ahead, since title deed timing shapes the application.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore Safa Park Structure
A build record reads best against what surrounds it. These three pages set Safa One's register progress in its market, community and developer context:

Safa Park Properties for Sale
Browse luxury apartments, branded residences and penthouses for sale around Safa Park.
See Safa Park Properties for Sale
Safa Park Community Overview
Read the Safa Park guide: established villas and canal-front residences beside one of Dubai's oldest public parks.
Explore the Safa Park Community
DAMAC Properties: Lagoon Communities, Golf Villas and Branded Collaborations
Founded in 2002, DAMAC has delivered 48,000 homes and is known for large-scale master communities, luxury residential projects and branded collaborations.
View the DAMAC Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
Safa One de GRISOGONO Construction Updates Frequently Asked Questions
Safa One de GRISOGONO by DAMAC is an active project on the Dubai Land Department register, number 2374, and stood at 68.66% on 15 July 2026, the latest dated reading in the supplied record. The RERA inspection on that date placed the substructure, superstructure and internal works at an advanced stage, while envelope, finishes and MEP works were each at a different point of progress. That reading was 76 days old on 29 September 2026, so the inspection timeline above is the record to re-check against Dubai REST.
The Safa One record holds two dated Dubai Land Department register readings: 58.83% on 24 March 2026 and 68.66% on 15 July 2026, a rise of 9.83 points between them. The July entry names 58.83% as its previous inspection, which ties the two dates into one measured interval. Each reading has its own page, the Safa One March 2026 register reading page and the Safa One July 2026 register reading page.
Between 24 March and 15 July 2026, Safa One gained about 2.61 points a month, close to double its whole-build average of about 1.37 points a month counted from the 1 June 2022 construction start to the 68.66% reading. That lifetime average stood at about 1.27 at the March reading, so one 113-day interval lifted it by roughly a tenth of a point. All of these figures are derived arithmetic on a 30-day month, not a forecast; the working sits in the pace analysis.
For buyers, the Safa One handover is Q4 2026; 30 December 2025 is the registered completion date on the Dubai Land Department record for project 2374, and it had lapsed 197 days before the 68.66% reading of 15 July 2026. The supplied record shows no amended registered date and gives no reason for the gap, so neither date is treated as a forecast here. The completion and delay clauses of each SPA govern a buyer's position if completion moves, and this page's record is updated when the next dated reading is logged.
The RERA Independent Progress Monitoring Reports for Safa One, dated 24 March 2026 and 15 July 2026, set out the project description, the inspection notes and a main contract status of progressing, but print no percentage. The figures on this page, 58.83% on 24 March 2026 and 68.66% on 15 July 2026, are the Dubai Land Department project register readings shown in the Dubai REST app for the same dates, which is why each one is labelled a register reading rather than a report figure.
Safa One is registered on the DLD project register as DAMAC CITY, project 2374, with the status Active, a registration date of 18 March 2022 and a construction start of 1 June 2022. The Dubai REST app lists the entry under that register name rather than the Safa One marketing name, so project number 2374 is the dependable search key when checking the 68.66% reading of 15 July 2026.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the Safa One de GRISOGONO construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.