Safa Two by DAMAC in Business Bay project rendering used for the April 2026 construction update showing the planned curved swimming pool and surrounding residential buildings in Dubai - Presented by Tohid Fetrat

DAMAC · Business Bay · Construction Update

Safa Two de GRISOGONO by DAMAC Construction Update - April 2026

April 2026 DLD Register Reading Places Safa Two at 31.35% Construction Progress in Business Bay

Superstructure, internal and MEP works were progressing at different stages when RERA inspected Safa Two on 12 April 2026, with the DLD register recording 31.35%.

Direct advisor access. Every message answered personally, never by a call center.

31.35%DLD Register Reading
12 April 2026Inspection Date
Q4 2027Expected Handover
2200DLD Project Number

DLD Project Register Data

Safa Two Construction Snapshot

A 5.00 point difference from the previous 26.35% reading places Safa Two in the superstructure band, where the DLD register becomes the buyer's main independent check on a building that is paid for on a fixed calendar rather than by milestone.

Project Name

Safa Two de GRISOGONO by DAMAC

Project Number

2200 (registered as Aykon City 3)

Project Status

Active

Construction Progress

31.35%

Inspection Date

12 April 2026

Construction Start

10 December 2019

Total Units

1,293 residential units

Total Built Area

194,369.18 sq m

Expected Completion

Q4 2027

Data source: DLD project register reading and RERA Independent Progress Monitoring Report for the inspection of 12 April 2026, project 2200, registered as Aykon City 3 (registered developer DAMAC CANAL ONE PROPERTY DEVELOPMENT L.L.C, developer number 1119; RERA progress status: Main Contract, Progressing). The 31.35% figure is the DLD register reading, as the RERA report prints no percentage, and the hero image above is a developer rendering, not a site photograph. Construction tracking against RERA inspection data runs across the full tohidfetrat.com project portfolio and is reviewed after every published cycle. Last updated: October 2026.

Want each new reading the day it publishes? Message me on WhatsApp and I will send it to you directly: one message per inspection cycle, nothing else. Message me on WhatsApp

This Inspection Cycle

Safa Two Construction Progress Summary

At the 12 April 2026 inspection the DLD register showed Safa Two at 31.35%, against a previous inspection figure of 26.35%, while RERA's report listed the main contract as progressing. Enabling works, foundations and the substructure were recorded as substantially completed, so the build had moved from below ground into the superstructure, with finishes only at an early stage.

Substantially Completed
  • Enabling works across the Sheikh Zayed Road plot
  • Foundation works for the residential building
  • Substructure works
In Progress at 31.35%
  • Superstructure works on the residential building
  • Internal works, progressing at different stages
  • MEP systems: mechanical, electrical and plumbing works
  • Finishes, recorded at an early stage
  • Site mobilisation, still ongoing at the inspection
Ahead of Handover
  • Remaining superstructure up to the mechanical floors and roof
  • Facade and interior finishes across the 1,293 residences
  • Amenity levels, including the podium beach pool
  • Remaining RERA inspection cycles toward 100% and handover in Q4 2027
Next inspectionPosted in the DLD project register after the next RERA site visit; this record covers 12 April 2026, and a newer reading may already be posted under project 2200.
Completion targetQ4 2027 expected handover; the registered completion date in the DLD record is 30 December 2027, inside that quarter.
Remaining distance68.65 percentage points separated the 12 April 2026 reading from 100%, with 627 days from that inspection to the registered completion date.

Payments and Progress

What 31.35% Progress Means for Safa Two Buyers

DAMAC's plan of record for Safa Two is time-based: the 19 instalments fall due at fixed intervals from each buyer's sale date, not when the building reaches a milestone. That makes a 31.35% reading less a payment trigger than a check on the escrow side of the deal, and at this stage four actions matter most.

Before Each Instalment

Verify the escrow account

Every instalment due before completion should go only to the DLD regulated escrow account registered for project 2200 with Emirates NBD. Safa Two escrow account verification is the step before any transfer; the lookup itself is a two-minute check against the official DLD project record, where the project appears as Aykon City 3.

Before You Sign or Pay

Reread your SPA payment schedule

Check how your sale and purchase agreement counts the 19 instalments from your own sale date, and set the last of them against the Q4 2027 handover expectation and the 10% due on completion. Not sure how your instalments map to this reading? Send me your SPA schedule and I will map it against the recorded milestones.

After Booking

Confirm your Oqood registration

Off plan purchases are registered with the Dubai Land Department through Oqood, so confirm that your unit's interim registration sits under project 2200, the same DLD record that carries the 31.35% reading. A purchase that cannot be found on that record is the one to question before the next instalment.

Every Cycle

Track the remaining cycles

With 68.65 points still to record after April 2026, a number of inspection readings lie between this one and handover. The Safa Two construction updates hub keeps each reading in sequence as it is published.

General framework, not legal advice: instalment dates, registration steps, and fee obligations are set by your individual SPA and the DLD record, and both should be read directly.

Buying at 31.35%?

Entering during the superstructure stage trades more construction exposure for more payment runway: the substructure was recorded as substantially completed in April 2026, the superstructure was still progressing, and DAMAC's time-based plan spreads 70% across instalments before the 10% due on completion. Every instalment goes to the DLD-registered escrow account for project 2200, released against verified construction progress.

Entering at 31.35%
  • Substructure recorded as substantially completed on 12 April 2026
  • Handover expected in Q4 2027, with 68.65 points still to record
  • 90/10 plan: 90% before completion, 10% on completion
Typical Late Stage Entry
  • Structure already standing, so less construction exposure
  • Shorter wait, often months rather than years
  • Little runway left; larger sums fall close to completion
AED 1.40M ≈ USD 381KStarting Price
90/10 Payment Plan10% Due on Completion
Q4 2027Expected Handover
Ask What Is Available at Safa Two

Limited Units Available per the project page as of this update; availability shifts between cycles.

About the Development

Safa Two Project Details

Safa Two by DAMAC in Business Bay project rendering of the illuminated curving tower with a red oval facade feature and skyline at night in Dubai - Presented by Tohid Fetrat
Business Bay · DAMAC

At the April 2026 inspection Safa Two was a superstructure stage build: one residential building rising from a basement and podium levels, planned for 1,293 studio to three bedroom apartments and penthouses under the de GRISOGONO brand. Starting prices: AED 1.40M ≈ USD 381K.

For buyers entering at this stage, the trade off is a longer wait against more of the 90/10 instalment runway still ahead, with handover expected in Q4 2027.

Safa Two de GRISOGONO by DAMAC Project Guide

Site Context This Cycle

Explore Safa Two Location on Dubai Map

Safa Two occupies a plot on Sheikh Zayed Road in Business Bay, the stretch DAMAC's brochure calls the city's Golden Mile, so every stage of the build runs beside the city's main highway. With the substructure recorded as substantially completed in April 2026, the work that cycle centred on the superstructure, which RERA listed as progressing.

Because Business Bay is an established district with completed roads, the canal and working utility networks, Safa Two is being built into a functioning neighbourhood rather than waiting on one, which keeps the open question for buyers at this stage on the building itself and the Q4 2027 handover, not on the area around it. See the project's position on the interactive Dubai real estate map. See the project’s position on the interactive Dubai real estate map.

Interactive Dubai real estate map preview
Click to view Safa Two by DAMAC on Dubai Map

Buyer Resources for This Project

Investing in Safa Two During Superstructure Construction

The superstructure band is where payment protection, residency planning, and steady tracking matter most for an off plan buyer. Each resource below is matched to where Safa Two stood in April 2026.

Safa Two by DAMAC in Business Bay construction updates cover image featuring a project rendering of the curved tower with a prominent red oval facade feature above clouds in Dubai - Presented by Tohid Fetrat
You Are Here

Safa Two Construction Updates

This page: what the 12 April 2026 DLD register reading means for Safa Two buyers.

Safa Two by DAMAC in Business Bay Golden Visa concept graphic featuring a gold card above a view of residential towers and an elevated roadway in Dubai - Presented by Tohid Fetrat

Safa Two de GRISOGONO Golden Visa: Inside a Jewel-Branded Address

DAMAC's Safa Two de GRISOGONO, 1,293 residences, qualifies from the 2 bedroom; studios and 1 bedrooms do not.

Read the Safa Two Golden Visa Guide
Safa Two by DAMAC in Business Bay escrow account concept graphic featuring a shield and padlock over a curved building entrance and landscaped streetscape in Dubai - Presented by Tohid Fetrat

Safa Two de GRISOGONO Escrow: A 1300-Unit Emirates NBD Account

DAMAC's Safa Two de GRISOGONO escrows 1300 units at Emirates NBD, DLD project 2200, certified 31.35% in April 2026.

Verify the Safa Two Escrow Account

Update Timeline

Other Safa Two Construction Updates

This April 2026 page is the first monthly record of Safa Two in the series; later readings join the timeline as each inspection is published.

All Safa Two Construction Updates

FAQs

Safa Two de GRISOGONO by DAMAC Construction Progress in April 2026: Frequently Asked Questions

Safa Two stood at 31.35% in the Dubai Land Department project register after the RERA inspection of 12 April 2026, recorded under project 2200. That figure is the DLD register reading: the RERA Independent Progress Monitoring Report for the same visit prints no percentage and lists the main contract as progressing. How readings are followed from one cycle to the next is set out on the Safa Two construction updates hub.

The DLD register showed a registered completion date of 30 December 2027 at the 12 April 2026 inspection, which falls inside the Q4 2027 handover expected for Safa Two. Registered dates can be revised between inspection cycles, so any change would surface in a later reading under project 2200 rather than on this April 2026 record.

On the DLD app's inspection card dated 12 April 2026, 26.35% sits in the Previous Inspection field beside the 31.35% current reading for project 2200. The app shows no date for that earlier figure, so this page records it as the prior register value only and does not turn the difference into a monthly pace.

According to the RERA report for the 12 April 2026 inspection, site mobilisation was still ongoing, while enabling works, foundations and the substructure were substantially completed. Superstructure, internal and MEP works were progressing at different stages, and finishes were at an early stage. The report describes one residential building with a basement, podium levels and mechanical floors, designed as a concrete structure with blockwork and internal and external finishes.

Search project number 2200: the DLD register lists Safa Two under the registered name Aykon City 3, in Business Bay, with DAMAC CANAL ONE PROPERTY DEVELOPMENT L.L.C as the registered developer (developer number 1119). The register entry carries the name Aykon City 3 rather than Safa Two, so the project number is the reliable search key, and its inspection card dated 12 April 2026 shows the 31.35% reading.

As of April 2026, the DLD record for project 2200 shows construction started on 10 December 2019 and the project registered on 19 December 2019, nine days later. Both dates are given here exactly as recorded; the register offers no explanation for the order. The 31.35% reading of 12 April 2026 is the cumulative figure for the build since that start date.

A Question the FAQ Can Not Answer?

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is helping you read the April 2026 inspection record for Safa Two de GRISOGONO correctly before your next payment decision. Client identities and transactions are never published or referenced. Message me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

Get Progress Alerts