The Register Record of the Ruby-Inspired Building on Sheikh Zayed Road
Safa Two read 31.35% on the DLD register at its 12 April 2026 inspection, a climb that carried the Sheikh Zayed Road build from substructure into superstructure.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
Safa Two de GRISOGONO at a Glance
Safa Two de GRISOGONO by DAMAC is a 1,293-residence building on Sheikh Zayed Road in Business Bay, branded by the Swiss jeweller de GRISOGONO. Its DLD record opens with a 10 December 2019 construction start, nine days before the 19 December 2019 registration, and runs 2,315 days to the 31.35% register reading of 12 April 2026. Those six-plus years are the groundwork years of this record: by April 2026, RERA listed enabling works, foundations and the substructure as substantially completed while the superstructure was still progressing.
2200 (registered as Aykon City 3)
Active
10 December 2019
1,293 residential units
194,369.18 sq m
30 December 2027 (DLD)
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
Safa Two de GRISOGONO Construction Update Timeline
Safa Two's record on this page carries one dated reading: 31.35% in the DLD project register at the RERA inspection of 12 April 2026, a little over six years after the December 2019 groundbreaking. The register card for that date also lists a previous inspection at 26.35% with no date attached, so it sits on the track below as an unlabelled earlier dot rather than a table row, and the single row links the full April 2026 update.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| April 2026 | 31.35% | 12 April 2026 | View the April 2026 update |
Pace Analysis
How Fast Safa Two de GRISOGONO Has Been Built
Safa Two has a single dated reading, so there is no inspection-to-inspection pace to measure yet. What the register does allow is arithmetic, not a forecast, on a 30-day month:
- Dec 2019 to Apr 2026: whole-build average, from the 10 December 2019 start to 31.35% on 12 April 2026About 0.41 points per month
- Apr 2026 to Dec 2027: the remaining 68.65 points to 100% by the 30 December 2027 registered completion dateAbout 3.28 points per month
What this record cannot show yet is a curve. With one dated reading there is no acceleration or taper to read, and the 26.35% listed as the previous inspection carries no date, so it cannot anchor a measured rate. The two figures above frame the build instead: a long opening span from the December 2019 start, in which enabling works, foundations and the substructure were recorded as substantially completed by April 2026, and 68.65 points still to record across the superstructure, MEP works, finishes and amenity levels. For an end user planning around the Q4 2027 handover, and for an investor timing the 10% due on completion under the 90/10 plan, the next dated reading is the one to watch, because it gives Safa Two its first measured pace between two inspections.
Get the Next Inspection Figure First
Tell me you are tracking Safa Two de GRISOGONO and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About Safa Two de GRISOGONO at Business Bay
A 31.35% reading on 12 April 2026 is easier to judge once you know what the finished building is meant to hold. The project guide covers the residences and amenities this record is tracking toward:

Safa Two de GRISOGONO: A Cut-Diamond Tower on Sheikh Zayed Road
Safa Two de GRISOGONO is a DAMAC tower in Business Bay with 1,293 residences, branded by the Swiss jeweller.
View the Safa Two de GRISOGONO Project GuideConsidering a Mid-Construction Entry?
Units at Safa Two are limited, and availability keeps shifting as the build works toward its Q4 2027 handover. If the record on this page is what brought you here, ask me for current availability before choosing a unit type.
Ask About Remaining Availability on WhatsAppStage Record
Safa Two de GRISOGONO Build Stages, Mapped to the Inspections
The stages below are drawn from the three groups in RERA's 12 April 2026 report on Safa Two, works substantially completed, works progressing and works at an early stage, so each window shows where the building stood at its 31.35% register reading rather than a textbook sequence.
Site Activation and Enabling Works
Construction started on 10 December 2019, nine days before the 19 December 2019 DLD registration; by the 12 April 2026 inspection RERA recorded enabling works as substantially completed, with mobilisation still ongoing.
Foundations and Substructure
The foundations and the basement below the podium levels: RERA's 12 April 2026 report lists foundation and substructure works as substantially completed, within the 31.35% register reading.
Superstructure, Internal and MEP Works
The stage the 12 April 2026 inspection found under way: superstructure, internal and MEP works progressing at different stages, with the register at 31.35% against an undated previous 26.35%.
Finishes and Amenity Levels
Recorded only at an early stage in April 2026: external and interior finishes across 1,293 residences, plus the podium beach pool, Ruby Heart and rooftop Fog Forest named in DAMAC's brochure.
Completion and Handover
The final 68.65 points to 100%, set against a registered completion date of 30 December 2027 inside the Q4 2027 handover window, when the plan's 10% completion payment falls due.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Safa Two de GRISOGONO's own record.
Buyer Position
Tracking Your Position at Safa Two de GRISOGONO
This page is one of four project resources that together cover a Safa Two de GRISOGONO purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Safa Two de GRISOGONO Construction Updates
This page: the DLD register record for Safa Two, from the December 2019 start to handover.

Safa Two de GRISOGONO Golden Visa: Inside a Jewel-Branded Address
DAMAC's Safa Two de GRISOGONO, 1,293 residences, qualifies from the 2 bedroom; studios and 1 bedrooms do not.
Read the Safa Two de GRISOGONO Golden Visa Guide
Safa Two de GRISOGONO Escrow: A 1300-Unit Emirates NBD Account
DAMAC's Safa Two de GRISOGONO escrows 1300 units at Emirates NBD, DLD project 2200, certified 31.35% in April 2026.
Verify the Safa Two de GRISOGONO Escrow AccountApproaching Handover
Between 31.35% and Handover: What Safa Two de GRISOGONO Buyers Should Do Now
At the 12 April 2026 reading of 31.35%, Safa Two's superstructure, internal and MEP works were still progressing, yet DAMAC's 90/10 plan of record keeps instalments falling due every three months from each buyer's sale date, whatever the register shows. Because the next instalment arrives on the calendar rather than on a milestone, the three checks below belong before it, not after it.
First, confirm that every instalment goes to the Emirates NBD escrow account registered for project 2200; the Safa Two escrow account page shows how to match the account to the DLD record.
Second, if residency is part of the plan, check your unit type against the threshold now through the Safa Two Golden Visa guide, since only the two bedroom, three bedroom and penthouse tiers meet it on price.
Third, if you are still choosing a unit, compare the five tiers on the Safa Two project guide, from AED 1.40M ≈ USD 381K, against the 10% due on completion and the Q4 2027 handover.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore Business Bay Structure
Safa Two's build record reads best next to what surrounds the Sheikh Zayed Road plot. These three pages put its progress beside the Business Bay market it will compete in, the community itself, and DAMAC's portfolio:

Business Bay Properties for Sale
Browse canal-front apartments, penthouses and branded residences for sale across Business Bay.
See Business Bay Properties for Sale
Business Bay Community Overview
Read the Business Bay guide: canal-front towers, offices and residences minutes from Downtown, with prices and rental demand covered.
Explore the Business Bay Community
DAMAC Properties: Lagoon Communities, Golf Villas and Branded Collaborations
Founded in 2002, DAMAC has delivered 48,000 homes and is known for large-scale master communities, luxury residential projects and branded collaborations.
View the DAMAC Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
Safa Two de GRISOGONO Construction Updates Frequently Asked Questions
Safa Two is an active project on the Dubai Land Department register (project 2200) and stood in its superstructure stage at the latest recorded inspection, on 12 April 2026, when the register showed 31.35%. RERA's report for that visit listed the main contract as progressing, and the full sequence of readings sits in the Safa Two inspection timeline above.
The DLD register card for Safa Two dated 12 April 2026 shows 31.35% current progress against a previous inspection figure of 26.35%, a difference of 5.00 percentage points. The register gives no date for the 26.35% reading, so that difference cannot be converted into a monthly rate. The inspection detail for that visit is set out in the Safa Two April 2026 construction update.
As arithmetic, not a forecast, Safa Two averaged about 0.41 percentage points per month across the whole build: 31.35 points over the 2,315 days from the 10 December 2019 construction start to the 12 April 2026 reading, on a 30-day month. Reaching 100% by the registered completion date of 30 December 2027 works out at about 3.28 points per month over the remaining 627 days. With one dated reading on record, no inspection-to-inspection pace exists yet; the working is in the pace analysis above.
The DLD register lists a registered completion date of 30 December 2027 for Safa Two (project 2200), which falls inside the Q4 2027 handover expected for the project, and that date was still ahead when the register recorded 31.35% on 12 April 2026. The registered date is the administrative anchor in the DLD record; actual handover is confirmed by DAMAC as the build approaches completion, and this page's record is updated as each new inspection is recorded.
Safa Two includes 1,293 residences across studio, one, two and three bedroom apartments and penthouses, with prices from AED 1.40M ≈ USD 381K for a 353 sq ft studio. All of them sit in one residential building that RERA's 12 April 2026 report describes with a basement, podium levels and mechanical floors, recorded at 31.35% on the DLD register that day.
At the 12 April 2026 inspection, 68.65 percentage points separated Safa Two's 31.35% register reading from 100%. RERA recorded the superstructure, internal and MEP works as progressing at different stages and the finishes as early-stage, so the remaining work spans the rest of the superstructure, external and interior finishes across 1,293 residences, and the amenity levels DAMAC's brochure describes, including the podium beach pool, the Ruby Heart and the rooftop Fog Forest, ahead of the Q4 2027 handover.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the Safa Two de GRISOGONO construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.