Selvara 2 Construction Update - May 2026

May 2026 Inspection Records Selvara 2 at 4.04% Construction Progress in Grand Polo Club and Resort

Mobilization, substructure works, and deep infrastructure services define site activity at Selvara 2, verified at 4.04 percent in the May 2026 RERA inspection cycle.

Direct advisor access. Every message answered personally, never by a call center.

4.04%Construction Progress
14 May 2026Inspection Date
Q2 2029Expected Completion
3823DLD Project Number

Verified DLD Inspection Data

Selvara 2 Construction Snapshot

A 3.39 point rise from the 0.65% previously recorded places Selvara 2 in the enabling and foundations band, the earliest stage of the register, where what protects a buyer is the escrow account and the registration paperwork rather than anything visible on site.

Project Name

Selvara 2 at Grand Polo by Emaar

Project Number

3823

Project Status

Active

Construction Progress

4.04%

Inspection Date

14 May 2026

Construction Start

02 November 2025

Total Units

246 villas (G+2)

Total Built Area

Expected Completion

Q2 2029

Data source: RERA inspection conducted on 14 May 2026, tracked against DLD inspection records for project 3823. Construction tracking against RERA inspection data runs across the full tohidfetrat.com project portfolio and is reviewed after every published cycle. Last updated: August 2026.

Want each new reading the day it publishes? Message me on WhatsApp and I will send it to you directly: one message per inspection cycle, nothing else. Message me on WhatsApp

This Inspection Cycle

Selvara 2 Construction Progress Summary

The 14 May 2026 reading moves Selvara 2 from 0.65% to 4.04%, a gain of 3.39 points earned almost entirely below ground level. No date is published against that earlier 0.65% figure in the register, so the elapsed interval cannot be stated, only the distance travelled. What the number describes is a site that has crossed from paperwork into physical work: the contractor is mobilized, foundations are being formed, and buried services are being run ahead of the villas that will sit on them.

Completed
  • Project registration recorded in the DLD register on 13 June 2025
  • Trust account established with National Bank of Ras Al Khaimah
  • Construction start logged against the record on 02 November 2025
In Progress at 4.04%
  • Contractor mobilization across the plot 3456 site footprint
  • Substructure works forming foundations for the villa plots
  • Deep services trenching for site wide infrastructure
  • Main contract carried as progressing on the RERA indicator
Ahead of Handover
  • Superstructure across the 246 villas in the G+2 format
  • The four milestone gates at 50%, 70%, 90%, and 100% completion
  • Building completion certificate procedures
  • Handover from Q2 2029
Next inspectionPublished in the DLD project register after the next RERA site visit; this page updates with each cycle.
Completion targetQ2 2029, roughly three years from this inspection date on the current schedule.
Remaining distance95.96 percentage points separate the May 2026 reading from handover readiness.
First milestone gate50% certified completion, the point at which the fifth installment falls due under the published plan.

Payment Linked Progress

What 4.04% Progress Means for Selvara 2 Buyers

The published Selvara 2 plan is an 80/20 structure in which the early payments are dated, not earned: the booking amount and the first four installments fall on fixed calendar dates, and only from the fifth does money follow certified construction. At 4.04% that distinction is the whole picture, because a buyer here is paying against a schedule while the site is still below ground. Four actions matter most at this stage.

Before Every Installment

Verify the escrow account

Every payment from the booking amount onward belongs in the DLD regulated escrow account registered for project 3823, held with National Bank of Ras Al Khaimah. The Selvara 2 escrow account verification is the step before any transfer; the lookup itself takes about two minutes against the official DLD project record.

Before the Next Dated Installment

Reread your SPA milestone schedule

Confirm which of your payments are calendar dated and which are gated on certified progress at 50%, 70%, 90%, and 100%, because at 4.04% only the dated ones are live. Not sure how your installments map to this reading? Send me your SPA schedule and I will map it against the certified milestones.

Within Weeks of Booking

Confirm your Oqood registration

Off plan purchases are recorded on the interim property register through Oqood, and the 4% Dubai Land Department fee paid at booking is what registers your interest against project 3823. Ask for the registration certificate rather than assuming it followed the receipt; at this distance from handover it is the only formal record that your unit is yours.

Every Cycle

Track the road to the first gate

Several inspection cycles sit between this reading and the 50% mark where milestone payments begin, and the shape of that climb is the best early signal of programme health. The Selvara 2 construction updates hub keeps each reading in one place.

General framework, not legal advice: milestone definitions, notice periods, and fee obligations are set by your individual SPA and the DLD record, and both should be read directly.

Buying at 4.04%?

Entering a project this early trades delivery certainty for the longest possible payment runway: the structure is not yet proven on site, but 80% of the price is spread across a plan reaching to 2029 rather than concentrated near handover. Every payment goes to the DLD-registered escrow account for project 3823, released against certified construction progress.

Entering Now at 4.04%
  • Full payment runway: 80% spread across the plan, 20% at completion
  • Construction risk carried from substructure through to handover
  • Widest choice of plot, style, and orientation while the phase is open
Typical Late-Stage Entry
  • Certified structure to inspect, with far less delivery uncertainty
  • Short runway: the balance falls due within months, not years
  • Only the units left unsold by earlier buyers remain available
AED 6.22M ≈ USD 1.69MStarting Price
80/20 Plan20% Due on Completion
From Q2 2029Expected Handover

Limited units listed available on the project page as of this update; availability shifts between cycles.

About the Development

Selvara 2 Project Details

Selvara 2 by Emaar in Grand Polo Club and Resort contemporary villas with landscaped front gardens and covered parking viewed from the street in Dubai - Presented by Tohid Fetrat
Grand Polo Club and Resort · Emaar

With foundations forming and services going in, Selvara 2 is an early stage release of 246 four bedroom villas in a G+2 format, built to a single typology across three styles and their mirrored layouts. Starting prices: AED 6.22M ≈ USD 1.69M.

For buyers entering at this stage, the trade off is a four year wait against the fullest position in the payment plan, with handover expected from Q2 2029.

Site Context This Cycle

Explore Selvara 2 Location on Dubai Map

Selvara 2 occupies plot 3456 on the outer eastern edge of the Grand Polo masterplan, registered under Dubai Investment Park Second and sitting beyond the first Selvara release and Montura 2, with open desert on its far boundary. That perimeter position explains the shape of this cycle: a phase with no existing services running through it has to be trenched and connected before villa plots can rise, which is why deep infrastructure work dominates the May 2026 inspection notes.

Grand Polo Club and Resort is itself a masterplan under construction rather than a settled district, so the roads, the Green Core with its polo fields and clubhouse, and the earlier villa clusters are maturing on their own timelines alongside this phase. For buyers that matters in a specific way: the amenity picture at handover depends on the community programme as much as on Selvara 2, while the wider road position stays fixed, roughly five minutes from Al Maktoum International Airport and ten from Expo City. See the project's position on the interactive Dubai real estate map. See the project’s position on the interactive Dubai real estate map.

Interactive Dubai real estate map preview

Buyer Resources for This Project

Investing in Selvara 2 During Early Construction Progress

The foundations band is where payment protection and residency planning are decided, long before there is a villa to inspect. Each resource below is matched to where Selvara 2 stands right now.

Selvara 2 by Emaar in Grand Polo Club and Resort construction updates cover image featuring a project rendering of a contemporary villa with covered parking and landscaped frontage in Dubai - Presented by Tohid Fetrat
You Are Here

Selvara 2 Construction Updates

This page: the verified May 2026 inspection record for Selvara 2, from mobilization to handover.

Selvara 2 by Emaar in Grand Polo Club and Resort Golden Visa card graphic above a contemporary villa rendering with landscaped frontage in Dubai - Presented by Tohid Fetrat

Selvara 2 Golden Visa: One Villa Typology, Three Times Over

Selvara 2, Emaar's 246-villa Grand Polo Club and Resort cluster, releases one typology, the 4 bedroom villa, and it qualifies.

Read the Selvara 2 Golden Visa Guide
Selvara 2 by Emaar in Grand Polo Club and Resort escrow account protection concept with shield and padlock icons above a landscaped villa streetscape in Dubai - Presented by Tohid Fetrat

Selvara 2 Escrow: The Grand Polo Club Villa Account

Selvara 2 at Grand Polo is DLD project 3823, escrowed with National Bank of Ras Al Khaimah, 4.04% certified May 2026.

Verify the Selvara 2 Escrow Account

Update Timeline

Other Selvara 2 Construction Updates

This is the first published reading in the Selvara 2 record. Each new inspection cycle is added to the hub, so the full climb from mobilization to handover stays in one place.

All UpdatesSelvara 2 Construction Updates Hub
Next Update · One Message Per CycleGet notified the day it publishes
All Selvara 2 Construction Updates

FAQs

Selvara 2 Construction Progress in May 2026: Frequently Asked Questions

As of the RERA inspection conducted on 14 May 2026, Selvara 2 stands at 4.04% construction progress in the DLD project register, with the progress status recorded as main contract progressing.

The register moves Selvara 2 from 0.65% at the prior reading to 4.04% on 14 May 2026, a gain of 3.39 points. The DLD record carries no published date against that earlier reading, so the interval it covers cannot be stated.

Handover is scheduled for Q2 2029. With construction recorded as starting on 02 November 2025, that is a build programme of roughly three and a half years from site start, which is consistent with a 246 unit villa release delivered in phases.

The 14 May 2026 inspection notes record contractor mobilization ongoing, with substructure works and deep services for infrastructure progressing on site. At this stage the visible activity is groundworks and buried utility runs rather than vertical villa construction.

The published Emaar plan links four payments to certified construction completion: 10% at 50%, 10% at 70%, 10% at 90%, and the closing 20% at 100%. Everything before those, including the booking payment and the first four installments, falls on calendar dates instead.

The May 2026 monitoring record names National Bank of Ras Al Khaimah (P.S.C) as the trust account bank for project 3823, developed by Emaar Development P.J.S.C. under developer number 1211. Account details should be confirmed against the DLD record before any transfer.

Selvara 2 occupies plot 3456 on the eastern edge of the masterplan, registered under Dubai Investment Park Second, immediately beside the first Selvara release and Montura 2. Its perimeter position is why infrastructure and deep services lead this phase of works.

A Question the FAQ Can Not Answer?

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is helping you read the May 2026 inspection record for Selvara 2 correctly before your next payment decision. Client identities and transactions are never published or referenced. Message me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

Get Progress Alerts