The Lana Residences Dorchester Collection by Omniyat in Marasi Bay construction updates cover image showing the waterfront towers beside the marina and yachts in Dubai - Presented by Tohid Fetrat

OMNIYAT · Marasi Bay

The Lana Residences Construction Updates

The Completed Register Record of a Foster + Partners Tower on Marasi Bay

The building shared by The Lana Residences and its hotel read 100% in the DLD register on 11 January 2024, closing a build started 01 March 2018.

Construction tracking against RERA inspection data, updated after every recorded inspection.

Direct advisor access. Every message answered personally, never by a call center.

100%Construction Progress
11 January 2024Latest RERA Inspection
39 ResidencesTotal Units
Project 2052 (Dorchester Collection Dubai)DLD Registration

Construction Snapshot

The Lana Residences at a Glance

The Lana Residences is OMNIYAT's collection of 39 residences on the Marasi Bay waterfront, set inside a Foster + Partners building that it shares with the Dorchester Collection hotel. That building is registered with the DLD as Dorchester Collection Dubai (project 2052), and the one registration covers both the hotel and The Lana Residences. Construction started on 01 March 2018, and the register logged 100% on 11 January 2024; its status now reads Finished, and the collection is listed as Ready. Because hotel rooms, serviced apartments, retail units and the residences all sit under that single project number, every reading below describes the whole 2B+G+31 Floor+Roof building rather than the 39 homes alone.

DLD Project Number

2052 (Dorchester Collection Dubai)

Project Status

Finished

Construction Start

01 March 2018

Total Units

39 Residences

Total Built-Up Area

105,173.91 sq m

Registered Completion Date

01 June 2022

Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.

Inspection Record

The Lana Residences Construction Update Timeline

This record holds one dated inspection: 11 January 2024, when the register logged the Dorchester Collection Dubai building at 100% and the inspection report marked it Completed. The register view also shows a previous reading of 93.15% but gives it no date, so it sits on the track as an unlabelled earlier point and has no row of its own. The January 2024 row links the full monthly update for that visit.

Inspection MonthConstruction ProgressInspection DateFull Update
January 2024100%11 January 2024View the January 2024 update
!

Reading the dates: the DLD register gives 01 June 2022 as the registered completion date for project 2052. The inspection report of 11 January 2024 records the Building Completion Certificate and the DCD completion as received on 16-10-2023, and the register read 100% on that January 2024 visit. All three dates are shown exactly as recorded; the register status now reads Finished and the collection is listed as Ready.

Pace Analysis

How Fast The Lana Residences Has Been Built

A measured pace needs two dated readings, and this record has only one. What it can show is the size of the closing step and the length of the whole build, both as plain arithmetic:

  • Undated previous reading to 11 January 2024: completion step, 93.15% to 100%6.85 points, no monthly pace
  • 01 March 2018 start to the 11 January 2024 reading: whole build2,142 days, arithmetic only

There is no curve to read here, because this page's record begins at the finish. The years when the two towers of the Foster + Partners design rose on the Dubai Water Canal carry no dated readings, so nothing can be said about acceleration or taper. The 6.85 point step cannot be spread over months, because the earlier figure has no date. And the 2,142 days, about five years and ten months, is a span from start to the 100% reading, not a pace or a forecast. The inspection notes from that January visit list accessories, snagging, deep cleaning and BTU metering, which are building-services and finishing items rather than structure. For an end user, the building is recorded complete, so the questions now concern the individual residence. For an investor, the value of the record lies in its completion documents, not in any delivery pace.

Get the Next Inspection Figure First

Tell me you are tracking The Lana Residences and I will send you the next recorded figure and site photos directly, ahead of the page update.

Get the Next Update on WhatsApp

Project Profile

About The Lana Residences at Marasi Bay

A 100% reading matters because of what it completes. The full project guide covers the homes this record describes:

The Lana Residences Dorchester Collection by Omniyat marina waterfront view with yachts and modern glass towers in Dubai - Presented by Tohid Fetrat

The Lana Residences: Dorchester-Managed Homes on Marasi Bay

The Lana Residences are 39 OMNIYAT residences in a Foster + Partners building shared with the Dorchester Collection hotel.

View the The Lana Residences Project Guide

Considering a Ready Residence?

The Lana Residences is listed as Limited Collection Available, with the building recorded complete and the handover status Ready. If the record on this page is what brought you here, ask me which residences remain and on what terms, because availability in a finished collection can change quickly.

Ask About Remaining Availability on WhatsApp

Stage Record

The Lana Residences Build Stages, Mapped to the Inspections

Only one of the five stages below has an inspection reading, so each one is anchored to a dated register or report event instead: the March 2018 start, the April 2018 registration, the June 2022 registered completion date, the October 2023 certificates and the January 2024 reading of 100%.

Mar 2018 to Apr 2018

Start and Registration

The register records construction starting on 01 March 2018 on plot 77 in Business Bay. The DLD registration of project 2052, as Dorchester Collection Dubai, is dated 26 April 2018.

2018 to 2023, no dated reading

Towers, Structure, and Envelope

The 2B+G+31 Floor+Roof building went up as two towers, one for the hotel and one for the residences. No dated reading exists for this stretch: the only earlier figure is an undated 93.15%.

01 Jun 2022, registered date

Registered Completion Date

The DLD register sets 01 June 2022 as the registered completion date for project 2052. It is shown here as recorded, next to the certificate dates that follow.

16 Oct 2023, certificates

Completion Certificates Received

According to the January 2024 report, the Building Completion Certificate through Dubai BPS and the DCD completion were both received on 16-10-2023. DEWA meters were installed by that visit.

Current PhaseJan 2024 onward, 100% at last reading

Completed and Listed as Ready

On 11 January 2024 the building was logged at 100% Completed, with minor accessories, snagging and deep cleaning noted as progressing that day. The register now reads Finished.

What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on The Lana Residences's own record.

Buyer Position

Tracking Your Position at The Lana Residences

This page is one of four project resources that together cover a The Lana Residences purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

The Lana Residences Dorchester Collection by Omniyat in Marasi Bay construction updates cover image showing the waterfront towers beside the marina and yachts in Dubai - Presented by Tohid Fetrat
You Are Here

The Lana Residences Construction Updates

This page: the register record for The Lana Residences, from the 2018 start to 100 percent.

The Lana Residences Dorchester Collection by Omniyat in Marasi Bay Golden Visa card graphic above the waterfront residence with Downtown Dubai skyline and Burj Khalifa in the background in Dubai - Presented by Tohid Fetrat

The Lana Residences Golden Visa on the Marasi Bay Waterfront

The Lana Residences, OMNIYAT's 39 residences in a Foster + Partners building, qualifies individually at all six residence types.

Read the The Lana Residences Golden Visa Guide
The Lana Residences Dorchester Collection by Omniyat in Marasi Bay escrow account protection graphic with shield and padlock icons above the illuminated waterfront residence in Dubai - Presented by Tohid Fetrat

The Lana Residences Escrow: OMNIYAT's Marasi Bay Account at Ajman Bank

OMNIYAT's The Lana Residences at Marasi Bay is DLD project 2052, 57 units escrowed with Ajman Bank, 100% certified January 2024.

Verify the The Lana Residences Escrow Account
The Lana Residences Dorchester Collection by Omniyat in Marasi Bay snagging inspection cover image showing a furnished bedroom interior with floor to ceiling windows and city skyline view in Dubai - Presented by Tohid Fetrat

The Lana Residences Snagging on the Marasi Bay Waterfront

The Lana Residences is OMNIYAT's collection of 39 branded residences managed by Dorchester Collection, in a Foster + Partners building.

Book The Lana Residences Snagging

Approaching Handover

Between 100% and Handover: What The Lana Residences Buyers Should Do Now

At 100%, the building itself leaves nothing more to track. What remains is the transaction and the condition of one residence: the finishes, the glazing, the appliances and the systems inside the home you are about to accept. In a ready building, the handover appointment can follow soon after the sale completes, so take the three steps below before you sign acceptance, not afterwards.

First, have the residence inspected independently, so that any defect in its marble, oak, glazing or home automation is on record before you accept it. The Lana Residences snagging page explains the timing and what the inspection checks.

Second, before any payment leaves your account, check the payment route against The Lana Residences escrow account page, so that the money follows the DLD record for project 2052 rather than an instruction you cannot verify.

Third, if residency is part of your plan, confirm your eligibility through The Lana Residences Golden Visa page before the title deed is issued, because its timing shapes the application.

Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.

The Wider Picture

Explore Marasi Bay Structure

A finished building still sits within a waterfront that is changing around it. These three pages put the record of The Lana Residences in its market, community and developer context:

Marasi Bay waterfront properties for sale with luxury marina skyline views in Dubai Presented by Tohid Fetrat

Marasi Bay Properties for Sale

Browse branded residences, waterfront apartments and penthouses for sale by OMNIYAT at Marasi Bay.

See Marasi Bay Properties for Sale
Marasi Bay in Business Bay Dubai showing waterfront canal view modern residential towers marina and urban lifestyle along Dubai Water Canal Presented by Tohid Fetrat

Marasi Bay Community Overview

Read the Marasi Bay guide: OMNIYAT's ultra-luxury canal-front district of branded residences, offices and hospitality.

Explore the Marasi Bay Community
Lumena Alta sky lounge and infinity pool overlooking Dubai skyline at night – ultra-luxury commercial tower by Omniyat, presented by Tohid Fetrat

Omniyat: Ultra-Luxury Architectural Icons From Palm Jumeirah to Business Bay

Omniyat designs ultra-luxury waterfront residences and commercial landmarks, and held the largest share of the UAE's ultra-luxury segment in 2024.

View the OMNIYAT Developer Profile

Construction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.

FAQs

The Lana Residences Construction Updates Frequently Asked Questions

The Lana Residences sits in a building registered with the DLD as Dorchester Collection Dubai (project 2052). The register lists its status as Finished, and the latest reading, dated 11 January 2024, is 100%. That reading was 992 days old on 29 September 2026, and the owner lists the collection as Ready. The dated record is laid out in the inspection timeline above.

The inspection of 11 January 2024 recorded progress status Completed, and the DLD register reading for the same date is 100%. That is 6.85 points above the previous reading of 93.15%, which carries no date. The visit notes and register detail are in the January 2024 construction update for The Lana Residences.

The Lana Residences' building has three dated completion records for project 2052. The DLD register gives a registered completion date of 01 June 2022. The inspection report records the Building Completion Certificate and the DCD completion as received on 16-10-2023. The register then logged 100% Completed on 11 January 2024. All three are shown as recorded, the register status now reads Finished, and this page's record is updated if a later register entry appears.

The Lana Residences comprises 39 residences, from two bedroom plus study homes up to five bedroom penthouses. They sit in a 2B+G+31 Floor+Roof building that also houses the Dorchester Collection hotel. That building is registered as a single DLD project, so no residences-only built-up area figure is published on this page.

From the 01 March 2018 construction start to the 11 January 2024 reading of 100%, the building behind The Lana Residences took 2,142 days, about five years and ten months. This is plain arithmetic on two register dates, not a measured pace, because the only earlier reading, 93.15%, has no date. The pace analysis above sets out what the record can and cannot show.

Construction on the building that houses The Lana Residences started on 01 March 2018, and the DLD registration of project 2052 is dated 26 April 2018. Both dates are shown as recorded. The first tracked reading in this record is also the latest: 100% on 11 January 2024.

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is keeping the The Lana Residences construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

WhatsApp +971543443597
Get the Latest Status