The Register Record of 424 Venice Villas Opposite DAMAC Hills

Venice at DAMAC Lagoons read 74.43% on the DLD register on 17 July 2026, leaving envelope, MEP, finishes and external works before its 424 villas reach handover.

Construction tracking against RERA inspection data, updated after every recorded inspection.

Direct advisor access. Every message answered personally, never by a call center.

74.43%Construction Progress
17 July 2026Latest RERA Inspection
424 villasTotal Units
Project 2396DLD Registration

Construction Snapshot

Venice at DAMAC Lagoons at a Glance

Venice at DAMAC Lagoons is DAMAC's cluster of 424 villas, offered as 6 Bedroom and 7 Bedroom homes, inside DAMAC Lagoons opposite DAMAC Hills. The Dubai Land Department registered it as project 2396 on 23 May 2022, construction began on 28 December 2022, and roughly three and a half years later the register read 74.43% on 17 July 2026. What sets this record apart is that late-stage reading sitting beside a registered completion date that has already passed, while DAMAC's current estimate for handover is Q3 2027; the cards below keep the register dates and that estimate apart.

DLD Project Number

2396

Project Status

Active

Construction Start

28 December 2022

Total Units

424 villas

Total Built-Up Area

291,988.09 sq m

Registered Completion Date

29 September 2025

Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.

Inspection Record

Venice at DAMAC Lagoons Construction Update Timeline

One dated reading anchors the Venice record so far: 74.43% on the inspection report of 17 July 2026, shown on the register beside a previous reading of 68.05% that carries no date. The track below therefore plots that earlier reading as an unlabelled marker, and the table holds a single row, the July 2026 update with its RERA site notes; each later reading for project 2396 adds a dot and a row.

Inspection MonthConstruction ProgressInspection DateFull Update
July 202674.43%17 July 2026View the July 2026 update
!

Reading the dates: the registered completion date for project 2396 on the DLD register is 29 September 2025. That date has passed, the register still lists the project as Active, and the reading of 17 July 2026 stood at 74.43%. DAMAC's current estimate for handover is Q3 2027; confirm the latest date with DAMAC and check Dubai REST for any extension recorded against the project.

Pace Analysis

How Fast Venice at DAMAC Lagoons Has Been Built

With one dated register reading on file, Venice's pace cannot yet be measured between two inspections. What the record supports is arithmetic, not a forecast:

  • 28 Dec 2022 to 17 Jul 2026: whole build to date, 0% to 74.43% over 1,297 daysAbout 1.72 points per month
  • 17 Jul 2026 to 30 Sep 2027: 74.43% to 100% by the end of the Q3 2027 estimate, 25.57 points over 440 daysAbout 1.74 points per month
  • Undated previous reading to 17 Jul 2026: 68.05% to 74.43%6.38 points, no rate

Read together, those lines describe a villa build whose structural stages the RERA report of 17 July 2026 lists as substantially completed, so the 25.57 points still open on the register belong to the envelope, MEP, internal finishes and the external works around each Venice plot. The first figure averages everything since the 28 December 2022 start; the second is simply the rate that would carry the register to 100% by 30 September 2027. Neither says when DAMAC will hand over, and the move from 68.05% to 74.43% cannot be dated, so it yields no rate. For an investor timing an exit, and for a family planning a move into a 6 or 7 bedroom villa, the figure to watch is the next dated reading for project 2396, because it turns this arithmetic into the first measured pace in the Venice record.

Get the Next Inspection Figure First

Tell me you are tracking Venice at DAMAC Lagoons and I will send you the next recorded figure and site photos directly, ahead of the page update.

Get the Next Update on WhatsApp

Project Profile

About Venice at DAMAC Lagoons

A register percentage means more next to what it is measuring. The project guide covers the villas this record follows toward handover:

Venice at DAMAC Lagoons by DAMAC in DAMAC Lagoons project rendering of a contemporary villa with floor to ceiling glass, a private swimming pool and planted outdoor seating in Dubai - Presented by Tohid Fetrat

Venice at DAMAC Lagoons: Monochromatic Six and Seven Bedroom Villas

Venice at DAMAC Lagoons is a cluster of 424 villas with black and grey marble interiors and green and gold accents.

View the Venice at DAMAC Lagoons Project Guide

Considering a Late-Stage Entry?

Venice is listed with limited units available, and what remains on offer can change as the cluster moves toward its Q3 2027 estimate. If this build record is why you are weighing a Venice villa, ask me which ones are still offered before the choice narrows further.

Ask About Remaining Availability on WhatsApp

Stage Record

Venice at DAMAC Lagoons Build Stages, Mapped to the Inspections

Each stage below is pinned to the dates and readings Venice's own record supports, from the May 2022 registration to the Q3 2027 estimate, rather than to a generic construction sequence.

May 2022 to Dec 2022

Registration to Construction Start

Project 2396 was registered with the Dubai Land Department on 23 May 2022, and construction started on 28 December 2022, 219 days later.

From 28 Dec 2022

Enabling Works and Foundations

Site enabling and foundation works for the Venice villa plots, both listed as substantially completed in the RERA report of 17 July 2026.

Dec 2022 to Jul 2026

Substructure and Villa Superstructure

Concrete structure and block for the 424 villas, which the 17 July 2026 RERA report lists as substantially completed while the register read 74.43%.

Current Phase17 Jul 2026 at 74.43%

Envelope, MEP, Finishes and External Works

Internal works, the external envelope, MEP and infrastructure at advanced stages, with finishes and external works at different stages, per the 17 July 2026 report.

To Q3 2027 (estimated)

Completion and Villa Handover

The remaining 25.57 points after the 17 July 2026 reading, then the completion notice, the 20% completion payment under the 80/20 plan and handover, estimated for Q3 2027.

What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Venice at DAMAC Lagoons's own record.

Buyer Position

Tracking Your Position at Venice at DAMAC Lagoons

This page is one of four project resources that together cover a Venice at DAMAC Lagoons purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Venice at DAMAC Lagoons by DAMAC in DAMAC Lagoons construction updates cover image featuring a project rendering of a contemporary two storey villa with a swimming pool and garden in Dubai - Presented by Tohid Fetrat
You Are Here

Venice at DAMAC Lagoons Construction Updates

This page: the Venice register record, from the 28 December 2022 start through to villa handover.

Venice at DAMAC Lagoons by DAMAC in DAMAC Lagoons Golden Visa concept graphic showing a gold card above the exterior rendering of a two storey villa in Dubai - Presented by Tohid Fetrat

Venice at DAMAC Lagoons Golden Visa: Two Villa Types Clear

Venice at DAMAC Lagoons, DAMAC's 424 villas, clears the threshold at both 6 and 7 bedroom types, under Oqood now.

Read the Venice at DAMAC Lagoons Golden Visa Guide
Venice at DAMAC Lagoons by DAMAC in DAMAC Lagoons escrow account concept graphic featuring a shield and padlock above a rendered modern villa, outdoor pool and planted terrace in Dubai - Presented by Tohid Fetrat

Venice at DAMAC Lagoons Escrow, an Emirates NBD Lagoons Account

DAMAC's Venice at DAMAC Lagoons is DLD project 2396: 424 units, Emirates NBD escrow, 74.43% certified July 2026.

Verify the Venice at DAMAC Lagoons Escrow Account
Venice at DAMAC Lagoons by DAMAC in DAMAC Lagoons snagging inspection page image featuring a rendered furnished living room with green sofas, tall glazing and views toward a private swimming pool in Dubai - Presented by Tohid Fetrat

Venice at DAMAC Lagoons Snagging for 6 and 7 Bedroom Villas

Venice at DAMAC Lagoons offers 424 DAMAC Properties villas of 6 and 7 bedrooms, off Hessa Street opposite DAMAC Hills.

Book Venice at DAMAC Lagoons Snagging

Approaching Handover

Between 74.43% and Handover: What Venice at DAMAC Lagoons Buyers Should Do Now

What is left of the build after the 17 July 2026 reading, 25.57 points, sits in the envelope, MEP, finishes and external works around each villa, the stretch where buyer preparation pays off most against a Q3 2027 handover estimate. Handover notices at comparable projects typically give buyers a short window to complete their appointment, so the three steps below happen now, not when the notice arrives.

First, line up independent snagging so defects across a multi-level villa, its roof, glazing and garden are documented before you accept it; the Venice at DAMAC Lagoons villa snagging guide covers timing and scope.

Second, check what your SPA still treats as due: DAMAC's launch plan attaches its four construction-linked 10% instalments to the 40%, 50%, 60% and 70% completion marks, every one of them under the 74.43% reading of 17 July 2026, so confirm every remaining payment against the Venice at DAMAC Lagoons escrow account page before transferring.

Third, if your villa purchase may support residency, settle eligibility early through the Venice at DAMAC Lagoons Golden Visa eligibility guide, since Oqood registration now and the title deed after handover shape the application path.

Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.

The Wider Picture

Explore DAMAC Lagoons Structure

A villa build record tells half the story; the community taking shape around it tells the rest. These three pages set the Venice build in its market, community and developer context:

DAMAC Lagoons properties for sale in Dubai including villas, townhouses and apartments within landscaped residential surroundings, Presented by Tohid Fetrat

DAMAC Lagoons: Mediterranean-Themed Villas, Townhouses, Apartments and Offices

DAMAC Lagoons sits opposite DAMAC Hills in Dubailand, with 11 themed clusters and 3 projects of villas, townhouses, apartments and offices.

See DAMAC Lagoons Properties for Sale
DAMAC Lagoons master community with crystal lagoon waterfront villas sandy beaches palm trees and leisure amenities in Dubai Presented by Tohid Fetrat

DAMAC Lagoons Community Overview

Read the DAMAC Lagoons guide: Mediterranean-themed clusters and crystal lagoons across a 45 million sq ft waterfront masterplan.

Explore the DAMAC Lagoons Community
DAMAC Properties development overlooking Dubai skyline and waterfront with modern architecture at sunset in Dubai Presented by Tohid Fetrat

DAMAC Properties: Lagoon Communities, Golf Villas and Branded Collaborations

Founded in 2002, DAMAC has delivered 48,000 homes and is known for large-scale master communities, luxury residential projects and branded collaborations.

View the DAMAC Developer Profile

Construction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.

FAQs

Venice at DAMAC Lagoons Construction Updates Frequently Asked Questions

Venice at DAMAC Lagoons is an Active project on the Dubai Land Department register, number 2396, recorded at 74.43% in the inspection report of 17 July 2026 and working through its envelope, MEP, finishes and external works stage. The dated record sits in the Venice inspection timeline above.

Progress at Venice at DAMAC Lagoons is followed through the DLD project register for project 2396, which read 74.43% on 17 July 2026 against a previous reading of 68.05% that the register leaves undated. Each new register reading joins this page as a dated row, and the site notes for the July 2026 figure are in the Venice at DAMAC Lagoons July 2026 construction update.

The registered completion date for Venice at DAMAC Lagoons on the DLD register has already passed, while DAMAC's current handover estimate is Q3 2027 and the register still listed project 2396 as Active at the 74.43% reading of 17 July 2026. A passed registered date is not a handover date: confirm the current timetable with DAMAC in writing and check Dubai REST for any extension recorded against the project. The register date itself is shown in the Venice construction snapshot.

Venice at DAMAC Lagoons comprises 424 villas, offered as 6 Bedroom and 7 Bedroom homes. The RERA report of 17 July 2026 describes them as villas with a concrete structure and block and internal and external finishes, and the DLD register recorded the cluster at 74.43% on that date.

Venice at DAMAC Lagoons has averaged about 1.72 percentage points per month from its 28 December 2022 construction start to the 74.43% register reading of 17 July 2026, arithmetic over 1,297 days rather than a forecast. Reaching 100% by 30 September 2027, the end of the Q3 2027 estimate, would take about 1.74 points per month over the remaining 440 days; the working is in the Venice pace analysis above.

The Dubai Land Department registered Venice at DAMAC Lagoons as project 2396 on 23 May 2022, and construction started 219 days later, on 28 December 2022. The first dated reading in the record followed on 17 July 2026 at 74.43%; the only earlier reading on the register, 68.05%, carries no date.

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is keeping the Venice at DAMAC Lagoons construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

WhatsApp +971543443597
Get the Latest Status