Violet 3 by DAMAC in DAMAC Hills 2 project rendering used for the May 2026 construction update showing planned contemporary villa exteriors and landscaped surroundings in Dubai - Presented by Tohid Fetrat

DAMAC · DAMAC Hills 2 · Construction Update

Violet 3 Construction Update - May 2026

May 2026 Inspection Records Violet 3 at 36.2% Construction Progress in DAMAC Hills 2

Superstructure and internal works now advance across the 616 townhouses at Violet 3, with envelope, MEP, and finishes still at early stages in the May 2026 inspection.

Direct advisor access. Every message answered personally, never by a call center.

36.2%Construction Progress
16 May 2026Inspection Date
Q2 2027Expected Completion
3222DLD Project Number

Verified DLD Inspection Data

Violet 3 Construction Snapshot

A 25.37 point rise from the previous recorded reading places Violet 3 in the superstructure band, the stage where concrete frames rise faster than the trades that follow them. That earlier reading of 10.83% carries no inspection date in the register, so the gain is a distance between two readings rather than a monthly rate.

Project Name

Violet 3 at DAMAC Hills 2

Project Number

3222

Project Status

Active

Construction Progress

36.2%

Inspection Date

16 May 2026

Construction Start

18 December 2024

Total Units

616 townhouses

Total Built Area

Expected Completion

Q2 2027

Data source: RERA Independent Progress Monitoring Report inspected on 16 May 2026, tracked against the DLD project register for project 3222, developer number 1021. The register shows the preceding reading of 10.83% without an inspection date, so no date is attached to it here. Construction tracking against RERA inspection data runs across the full tohidfetrat.com project portfolio and is reviewed after every published cycle. Last updated: August 2026.

Want each new reading the day it publishes? Message me on WhatsApp and I will send it to you directly: one message per inspection cycle, nothing else. Message me on WhatsApp

This Inspection Cycle

Violet 3 Construction Progress Summary

The 16 May 2026 inspection records Violet 3 at 36.2%, up 25.37 points on the register's previous entry of 10.83%, which is logged without a date and therefore cannot be turned into a monthly rate. What the reading does show is a site that has left the ground: substructure packages are at advanced stages while superstructure and internal works run at differing stages across a cluster of 616 low rise homes rather than a single building.

Completed
  • Project 3222 registered with the DLD on 31 October 2024
  • Construction start recorded on site on 18 December 2024
  • Ground works taken far enough to carry vertical structure
In Progress at 36.2%
  • Enabling, foundation, and substructure works at advanced stages
  • Superstructure and internal works at differing stages across the cluster
  • Envelope, MEP, and finishes packages at early stages
  • Community infrastructure works advancing alongside the units
Ahead of Handover
  • Envelope, MEP, and finishing packages carried to completion
  • Remaining RERA inspection cycles between 36.2% and 100%
  • Completion certification and handover from the Q2 2027 window
Next inspectionAdded to the register once RERA next visits the Violet 3 site; this page is rebuilt each time a reading lands.
Handover windowQ2 2027, roughly twelve months beyond the 16 May 2026 reading.
Remaining distance63.8 percentage points separate the May 2026 reading from handover readiness.

Payment Linked Progress

What 36.2% Progress Means for Violet 3 Buyers

Violet 3 sells on a 70/30 construction linked schedule, which means most of what a buyer pays is released while the site is still moving. A verified reading of 36.2% is therefore a position on your own payment schedule, not just a status line. Four actions matter at this stage of the build.

Before Your Next Installment

Verify the escrow account

Construction stage money should reach only the DLD regulated escrow account registered for project 3222, held with Dubai Islamic Bank per the May 2026 monitoring report. The Violet 3 escrow account verification is the step before any transfer; the lookup itself takes about two minutes against the official DLD project record.

Between Inspection Cycles

Reread your SPA milestone schedule

Violet 3 instalments run monthly from your sale date with heavier steps at fixed intervals, so your dates depend on when you booked rather than on this reading. Not sure how your instalments map to 36.2%? Send me your SPA schedule and I will map it against the recorded milestones.

Within Weeks of Booking

Confirm your Oqood interim registration

Off plan purchases are recorded on the DLD interim register through Oqood once the 4 percent registration fee is paid. Check that your unit appears there in your own name; at this distance from handover, the interim register is the document that proves your position.

Every Cycle

Track the remaining cycles

Roughly two thirds of the build still lies between this reading and certification, across several more inspections. The Violet 3 construction updates hub keeps each of those readings in one place.

General framework, not legal advice: milestone definitions, notice periods, and fee obligations are set by your individual SPA and the DLD record, and both should be read directly.

Buying at 36.2%?

Entering mid build trades some payment runway for evidence: a third of the programme is already recorded rather than promised, and the remaining schedule is short enough to plan around. Every payment goes to the DLD-registered escrow account for project 3222, released against certified construction progress.

Entering Now at 36.2%
  • Structure recorded on an independent report, not projected from a plan
  • Around twelve months between booking and the Q2 2027 window
  • Part of the construction schedule already run before you join it
Typical Launch Entry
  • Nothing on site to inspect beyond registration and mobilization
  • Three years or more is a common wait for a townhouse cluster
  • The full instalment ladder still ahead, priced at launch levels
AED 1.911M ≈ USD 520KStarting Price
70/30 Plan30% Due on Completion
Q2 2027Expected Handover

Limited units listed available on the project page as of this update; availability shifts between cycles.

About the Development

Violet 3 Project Details

Violet 3 by DAMAC in DAMAC Hills 2 private balcony overlooking landscaped villa surroundings with palm trees in Dubai - Presented by Tohid Fetrat
DAMAC Hills 2 · DAMAC Properties

With frames rising above completed ground works, Violet 3 is a mid build cluster of 616 four bedroom townhouses in two prototypes of 2,352 and 2,415 sq ft, opposite the community leisure zones. Starting prices: AED 1.911M ≈ USD 520K.

Buying in now means inheriting a schedule already part run and a plot list already thinned by two earlier Violet releases, against a wait measured in months rather than years to the Q2 2027 window.

Site Context This Cycle

Explore Violet 3 Location on Dubai Map

Violet 3 occupies plot 19742 in Madinat Hind 4, on the western side of DAMAC Hills 2 facing the community's water and sports towns, and that horizontal footprint explains the shape of this cycle: progress spreads across hundreds of separate G+2 shells at once, so a percentage moves only when many houses move together rather than when one floor is poured.

Because DAMAC Hills 2 is already occupied, with its amenity towns, retail, and Al Qudra Road approach in use rather than in progress, the infrastructure work recorded this cycle connects Violet 3 into a functioning community instead of building one from nothing, which is what shortens the gap between certification and a liveable street. See the cluster's position on the interactive Dubai real estate map. See the project’s position on the interactive Dubai real estate map.

Interactive Dubai real estate map preview

Buyer Resources for This Project

Investing in Violet 3 During Active Construction Progress

The superstructure band is where payment protection and residency planning matter more than finishing detail. Each resource below is matched to where Violet 3 stands right now.

Violet 3 by DAMAC in DAMAC Hills 2 construction updates cover image featuring a project rendering of a contemporary villa exterior with balconies and palm landscaping in Dubai - Presented by Tohid Fetrat
You Are Here

Violet 3 Construction Updates

This page: the verified May 2026 inspection record for Violet 3, from site start to handover.

Violet 3 by DAMAC in DAMAC Hills 2 Golden Visa card graphic beside a villa exterior with private pool and landscaped garden in Dubai - Presented by Tohid Fetrat

Violet 3 Golden Visa: The Line Inside One Townhouse Typology

Every TH12-4E at Violet 3, DAMAC's 616-townhouse cluster, qualifies alone; the cluster sells a single four bedroom typology.

Read the Violet 3 Golden Visa Guide
Violet 3 by DAMAC in DAMAC Hills 2 escrow account protection concept with shield and padlock icons above a contemporary villa exterior in Dubai - Presented by Tohid Fetrat

Violet 3 Escrow Account: The Third Violet Release at DAMAC Hills 2

DAMAC's Violet 3 is DLD project 3222, 616 units escrowed at Dubai Islamic Bank, 36.2% certified in May 2026.

Verify the Violet 3 Escrow Account

Update Timeline

Other Violet 3 Construction Updates

This is the first published inspection record for Violet 3. Each following cycle is added here, so the cluster's progress can be read reading by reading rather than from a single snapshot.

All UpdatesViolet 3 Construction Updates Hub
Next Update · One Message Per CycleGet notified the day it publishes
All Violet 3 Construction Updates

FAQs

Violet 3 Construction Progress in May 2026: Frequently Asked Questions

As of the RERA Independent Progress Monitoring Report inspected on 16 May 2026, Violet 3 stands at 36.2% construction progress in the DLD project register for project 3222, with the progress status recorded as main contract progressing.

The register moves Violet 3 from a previous reading of 10.83% to 36.2% on 16 May 2026, a gain of 25.37 points. The earlier reading carries no inspection date in the register, so the gain cannot be expressed as a monthly rate and is stated here as a distance between two readings only.

The 16 May 2026 inspection notes record mobilization works ongoing, with enabling, foundation and substructure packages at advanced stages. Superstructure and internal works were progressing at differing stages across the cluster, envelope, MEP and finishes works were at early stages, and community infrastructure work was progressing alongside the units.

The 16 May 2026 record shows no reported slippage against the Q2 2027 handover window, with 63.8 percentage points between that reading and full certification and roughly twelve months of programme left to run. How inspection cycles convert into completion certification is covered on the Violet 3 construction updates hub.

Violet 3 runs a 70/30 construction linked schedule: 20 percent plus the 4 percent DLD fee on booking, 50 percent across construction, and 30 percent on completion. At a 36.2% reading the two percentage triggered steps at 80% and 90% completion, and the 30 percent completion payment, all still sit ahead of the project rather than behind it.

The 16 May 2026 Independent Progress Monitoring Report names Dubai Islamic Bank (Public Joint Stock Company) as the trust account bank for project 3222, registered to Front Line Investment Management L.L.C, developer number 1021. Buyers should confirm the account details against the DLD project record before every transfer rather than against any document supplied by a seller.

A Question the FAQ Can Not Answer?

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is helping you read the May 2026 inspection record for Violet 3 correctly before your next payment decision. Client identities and transactions are never published or referenced. Message me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

Get Progress Alerts