Violet 3 by DAMAC in DAMAC Hills 2 construction updates cover image featuring a project rendering of a contemporary villa exterior with balconies and palm landscaping in Dubai - Presented by Tohid Fetrat

DAMAC Properties · DAMAC Hills 2

Violet 3 Construction Updates

The Dated Build Record for DAMAC's Third Violet Cluster

Violet 3 recorded 36.2% construction at its 16 May 2026 RERA inspection, with superstructure work climbing across 616 townhouse plots toward a Q2 2027 handover.

Construction tracking against RERA inspection data, updated after every recorded inspection.

Direct advisor access. Every message answered personally, never by a call center.

36.2%Construction Progress
16 May 2026Latest RERA Inspection
616 townhousesTotal Units
Project 3222DLD Registration

Construction Snapshot

Violet 3 at a Glance

Violet 3 is DAMAC's 616-townhouse cluster inside DAMAC Hills 2, entered in the Dubai Land Department register as project 3222 and under construction since 18 December 2024. Seventeen months of building had produced a 36.2% reading by the inspection of 16 May 2026, against a registered completion date of 30 June 2027. Because this is a horizontal cluster of G+2 plots rather than a single tower, the percentage moves as whole rows of townhouses advance together, which is why one dated reading tells you less here than the same figure would on a vertical build.

DLD Project Number

3222

Project Status

Active

Construction Start

18 December 2024

Total Units

616 townhouses

Total Built-Up Area

Registered Completion Date

30 June 2027 (DLD)

Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.

Inspection Record

Violet 3 Construction Update Timeline

This record is short by design. Violet 3 broke ground on 18 December 2024, and the register currently publishes one dated reading for project 3222: 36.2% on 16 May 2026. A preceding figure of 10.83% sits in the register without an inspection date attached, so it is noted here for context only. It is not plotted on the track, given a table row, or used in any pace figure below, because an undated reading cannot be placed on a timeline honestly. Every new dated inspection is added as its own row with its own site report.

Inspection MonthConstruction ProgressInspection DateFull Update
May 202636.2%16 May 2026View the May 2026 update

Pace Analysis

How Fast Violet 3 Has Been Built

With one dated inspection on record, the honest reading of pace at Violet 3 is two separate figures rather than a velocity curve: what the build has averaged since groundbreaking, and what it has to average from here.

  • 18 Dec 2024 to 16 May 2026: construction start to first dated reading, 0% to 36.2%About 2.1 points per month (derived)
  • 16 May 2026 to 30 Jun 2027: rate required to close the remaining 63.8 points by the registered dateAbout 4.7 points per month (schedule-implied)

Those two numbers are not the same kind of measurement, and reading them as a slowdown or an acceleration would be wrong. The first is an average smeared across roughly seventeen months, and it carries the slow opening every horizontal cluster has: mobilization, enabling works, and substructure absorb calendar time while the percentage barely moves. The second is arithmetic performed on a registered date, not a forecast of DAMAC's programme. What sits between 2.1 and 4.7 is exactly what the next dated inspection will settle, and there is a structural reason to expect the figure to climb: the May 2026 report placed the cluster in superstructure with envelope, MEP and finishes still opening, and G+2 townhouse rows convert that band into percentage points far faster than foundations ever did. For a buyer on the 70/30 plan, the reading worth waiting for is the one that confirms whether that shift has landed.

Get the Next Inspection Figure First

Tell me you are tracking Violet 3 and I will send you the next recorded figure and site photos directly, ahead of the page update.

Get the Next Update on WhatsApp

Project Profile

About Violet 3 at DAMAC Hills 2

A percentage only means something next to what is being built. The project guide covers the homes behind the 36.2% figure:

Violet 3 by DAMAC in DAMAC Hills 2 private balcony overlooking landscaped villa surroundings with palm trees in Dubai - Presented by Tohid Fetrat

Violet 3, a 616-Unit DAMAC Townhouse Cluster in DAMAC Hills 2

Violet 3 is a 616 unit cluster of townhouses in DAMAC Hills 2, opposite the community's water and sports amenities.

View the Violet 3 Project Guide

Considering an Entry Before the Next Milestone?

Inventory at Violet 3 is limited, and what remains shifts each time the cluster clears another construction milestone. Tell me which prototype you are after, TH12-4E or TH12-4M, and I will send you what is still open before the next dated inspection lands.

Ask About Remaining Availability on WhatsApp

Stage Record

Violet 3 Build Stages, Mapped to the Inspections

Each stage below is pinned to the window it actually occupied between the 18 December 2024 start and the 36.2% reading of 16 May 2026. The labels are Violet 3's own record, not a textbook sequence of what townhouse construction usually involves.

Oct 2024 to Dec 2024

Registration and Site Mobilization

Project 3222 entered the DLD register on 31 October 2024, with construction recorded as starting seven weeks later on 18 December 2024 at plot 19742.

2025 into early 2026

Enabling, Foundation and Substructure

The packages that absorb months without moving the number: excavation, foundations, and substructure across the cluster, all logged at advanced stages by the May 2026 report.

Current Phase16 May 2026 at 36.2%

Superstructure Rising Across the Rows

G+2 concrete frames and internal works advancing at different stages from row to row: the band that carried Violet 3 to its first dated reading of 36.2%.

Recorded at early stages, May 2026

Envelope, MEP and Internal Finishes

Facades, building services, and interior finishing had only opened on 16 May 2026, which makes this the band the next dated inspection should show moving fastest.

Toward 30 June 2027

Infrastructure, Landscaping and Handover

Community infrastructure was already progressing in May 2026; roads, utilities, and landscaping close out alongside final unit finishing ahead of the stated Q2 2027 handover.

What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Violet 3's own record.

Buyer Position

Tracking Your Position at Violet 3

This page is one of four project resources that together cover a Violet 3 purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Violet 3 by DAMAC in DAMAC Hills 2 construction updates cover image featuring a project rendering of a contemporary villa exterior with balconies and palm landscaping in Dubai - Presented by Tohid Fetrat
You Are Here

Violet 3 Construction Updates

This page: the dated inspection record for Violet 3, from the December 2024 start toward handover.

Violet 3 by DAMAC in DAMAC Hills 2 Golden Visa card graphic beside a villa exterior with private pool and landscaped garden in Dubai - Presented by Tohid Fetrat

Violet 3 Golden Visa: The Line Inside One Townhouse Typology

Every TH12-4E at Violet 3, DAMAC's 616-townhouse cluster, qualifies alone; the cluster sells a single four bedroom typology.

Read the Violet 3 Golden Visa Guide
Violet 3 by DAMAC in DAMAC Hills 2 escrow account protection concept with shield and padlock icons above a contemporary villa exterior in Dubai - Presented by Tohid Fetrat

Violet 3 Escrow Account: The Third Violet Release at DAMAC Hills 2

DAMAC's Violet 3 is DLD project 3222, 616 units escrowed at Dubai Islamic Bank, 36.2% certified in May 2026.

Verify the Violet 3 Escrow Account

Approaching Handover

Between 36.2% and Handover: What Violet 3 Buyers Should Do Now

At 36.2% the work deciding your handover date is structural, and the decisions protecting your position are financial rather than physical. On the 70/30 plan the last thirty percent falls due on completion, with three percent released at eighty percent and three percent again at ninety percent, which means the dated inspection figures on this page are the calendar your later installments are measured against, not the sales timeline.

First, tie your payment schedule to the record rather than to the month. The Violet 3 escrow account page covers the DLD-registered trust account holding those installments and how a certified milestone releases funds to the developer.

Second, settle residency eligibility now if it forms part of your reason for buying, since purchase value and title timing are both far easier to plan at 36.2% than in the weeks around handover. The Violet 3 Golden Visa eligibility guide sets out the thresholds.

Third, follow the inspection record rather than launch messaging. Each dated RERA reading published for project 3222 is added to the timeline above with its own report, and the Violet 3 May 2026 inspection report is the current one.

Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.

The Wider Picture

Explore DAMAC Hills 2 Structure

Progress numbers land differently once you know what already stands nearby. These three pages set Violet 3's 36.2% against the community around it and the developer behind it:

Community view of DAMAC Hills 2 showcasing properties for sale including villas, townhouses, and apartments in Dubai. Presented by Tohid Fetrat

DAMAC Hills 2 Properties for Sale

Browse villas, townhouses and selected apartments for sale in DAMAC Hills 2, with prices and payment plans.

See DAMAC Hills 2 Properties for Sale
DAMAC Hills 2 by DAMAC Properties community park with football field tennis courts basketball courts landscaped pathways and residential villas in Dubai - Presented by Tohid Fetrat

DAMAC Hills 2 Community Overview

Read the DAMAC Hills 2 guide: a self-contained villa community with themed clusters, lifestyle zones and family amenities.

Explore the DAMAC Hills 2 Community
DAMAC Properties development overlooking Dubai skyline and waterfront with modern architecture at sunset in Dubai Presented by Tohid Fetrat

DAMAC Properties: Lagoon Communities, Golf Villas and Branded Collaborations

Founded in 2002, DAMAC has delivered 48,000 homes and is known for large-scale master communities, luxury residential projects and branded collaborations.

View the DAMAC Developer Profile

Construction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.

FAQs

Violet 3 Construction Updates Frequently Asked Questions

Violet 3 is an active DLD-registered project, number 3222, recorded at 36.2% construction progress at the RERA inspection of 16 May 2026. At that reading the cluster sat in its superstructure band, with substructure packages at advanced stages and envelope, MEP and finishing scopes only beginning. Every dated reading published for the project is listed in the inspection timeline on this page.

The inspection dated 16 May 2026 recorded 36.2%. The register's preceding entry for project 3222 reads 10.83% but carries no inspection date, so the 25.37 point difference between the two readings is a distance rather than a measured monthly gain, and this page does not plot it on the track. The full site report is in the Violet 3 May 2026 construction update.

The DLD-registered completion date for project 3222 is 30 June 2027, and DAMAC states handover in Q2 2027. The 16 May 2026 inspection recorded 36.2%, leaving 63.8 points to close across the remaining schedule. This page's record is updated each time a new dated inspection is published for the project.

DLD registration records 616 units for project 3222, built as G+2 four-bedroom townhouses in two prototypes, TH12-4E and TH12-4M, with total sellable areas of 2,415.33 sq ft and 2,352.26 sq ft respectively. Layouts and the wider buying case are set out in the Violet 3 project guide.

From the 18 December 2024 construction start to the 16 May 2026 inspection, Violet 3 averaged roughly 2.1 percentage points per month. That is a derived start-to-inspection figure, not a velocity measured between two dated readings, because only one dated reading exists so far. Closing the remaining 63.8 points by the registered date of 30 June 2027 implies about 4.7 points per month from May 2026 onward. Both figures are set out in the pace analysis above.

Project 3222 entered the Dubai Land Department register on 31 October 2024, and construction was recorded as starting on 18 December 2024. The first dated progress reading published for the project is 36.2%, logged on 16 May 2026, roughly seventeen months after that start date.

By 16 May 2026 the cluster had cleared the ground. Enabling, foundation and substructure packages were logged in their advanced stages, with frame and internal work under way at differing points from row to row. The envelope, services and finishing scopes had barely opened, infrastructure was moving, and the overall status for project 3222 read main contract progressing.

The cluster is built on plot 19742, registered under Madinat Hind 4, along the western edge of DAMAC Hills 2 with the water and sports amenity zones facing it. Violet 3 is the third phase to carry the Violet name here. What has already been delivered nearby is covered in the DAMAC Hills 2 community overview.

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is keeping the Violet 3 construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

WhatsApp +971543443597
Get the Latest Status