Violet 4 by DAMAC Properties in DAMAC Hills 2 project rendering used for the May 2026 construction update showing landscaped villas and community greenery from a furnished terrace in Dubai - Presented by Tohid Fetrat

DAMAC Properties · DAMAC Hills 2 · Construction Update

Violet 4 Construction Update - May 2026

May 2026 Inspection Confirms Violet 4 Reaches 14.17% Construction Progress in DAMAC Hills 2

Mobilization, enabling, and foundation works dominate site activity at Violet 4, with substructure and MEP at early stages, verified at 14.17 percent on 13 May 2026.

Direct advisor access. Every message answered personally, never by a call center.

14.17%Construction Progress
13 May 2026Inspection Date
Q3 2027Expected Handover
3288DLD Project Number

Verified DLD Inspection Data

Violet 4 Construction Snapshot

A 13.21 point rise from the previous register reading of 0.96% places Violet 4 in the enabling and foundations band, the stage where payment protection and registration paperwork decide more for a buyer than anything visible on site.

Project Name

Violet 4 by DAMAC Properties

Project Number

3288

Project Status

Active

Construction Progress

14.17%

Inspection Date

13 May 2026

Construction Start

09 December 2024

Total Units

352 townhouses

Total Built Area

Expected Completion

Q3 2027

Data source: RERA Independent Progress Monitoring Report inspection conducted on 13 May 2026, tracked against the DLD project register for project 3288. The register carries an earlier reading of 0.96% with no inspection date published against it, so no dated prior point is plotted on the bar above. Construction tracking against RERA inspection data runs across the full tohidfetrat.com project portfolio and is reviewed after every published cycle. Last updated: August 2026.

Want each new reading the day it publishes? Message me on WhatsApp and I will send it to you directly: one message per inspection cycle, nothing else. Message me on WhatsApp

This Inspection Cycle

Violet 4 Construction Progress Summary

The 13 May 2026 inspection records Violet 4 at 14.17%, up from a register reading of 0.96%, a gain of 13.21 points. Because no inspection date is published against that earlier figure, the interval the gain covers cannot be stated, only the distance itself. What the May 2026 report describes is a site that has crossed from registration and mobilization into ground works across the Madinat Hind 4 plot.

Completed
  • DLD project registration recorded on 04 November 2024
  • Escrow trust account opened with Dubai Islamic Bank
  • Construction start recorded on 09 December 2024
In Progress at 14.17%
  • Mobilization works ongoing across the Madinat Hind 4 site
  • Enabling and foundation works at different stages plot by plot
  • Substructure, superstructure, and MEP works at early stages
  • Community infrastructure advancing alongside the townhouse rows
Ahead of Handover
  • Remaining superstructure across the ground plus two townhouse rows
  • Internal and external finishes on the concrete and block structure
  • Remaining RERA inspection cycles toward 100%
  • Completion certification ahead of the Q3 2027 handover window
Next inspectionDue on the next RERA visit to the Madinat Hind 4 plot; the reading enters the register for project 3288.
Previous reading0.96% on record with no published inspection date, so this cycle is dated from 13 May 2026 only.
Completion targetQ3 2027, the handover window on record for Violet 4 at the time of this update.
Remaining distance85.83 percentage points separate the May 2026 reading from handover readiness.

Payment Linked Progress

What 14.17% Progress Means for Violet 4 Buyers

Dubai off plan schedules attach money to elapsed months, to certified build milestones, or to both, which makes a verified reading of 14.17% a checkpoint rather than a headline: it tells you which protections should already be in place and how much of the schedule is still ahead. At this stage of Violet 4, four actions matter most.

Before Your Next Installment

Verify the escrow account

Every payment on an off plan townhouse should reach only the DLD regulated escrow account registered for project 3288, held with Dubai Islamic Bank per the 13 May 2026 monitoring report. Violet 4 escrow account verification is the step before any transfer; the lookup itself takes about two minutes against the official DLD project record.

Before the Next Milestone Date

Map your SPA payment schedule

The plan quoted on Violet 4 is the regular 70/30 construction linked structure, 20% on booking with the 4% DLD fee on top, 50% through construction, and 30% on completion. Check how your sale and purchase agreement dates those installments against the Q3 2027 handover window. Not sure how your installments map to this reading? Send me your SPA schedule and I will map it against the certified milestones.

Within Weeks of Booking

Confirm your Oqood interim registration

Off plan purchases are recorded on the DLD Oqood interim register before title issues at handover, and that entry is what evidences your position in project 3288 through the construction period. Ask for the Oqood certificate once the booking amount and the DLD fee are settled, rather than waiting until the handover file is opened.

Every Cycle

Track the early inspection cycles

Several inspection readings separate 14.17% from completion, and movement across the early bands is the clearest signal of contractor pace on a row cluster. Violet 4 construction updates hub keeps every cycle in one place.

General framework, not legal advice: milestone definitions, notice periods, and fee obligations are set by your individual SPA and the DLD record, and both should be read directly.

Buying at 14.17%?

Entering a project at the enabling and foundation stage trades certainty for runway: the structure is not yet standing, the handover window is over a year out, and almost the entire installment schedule is still ahead of you rather than behind. Every payment goes to the DLD-registered escrow account for project 3288, released against certified construction progress.

Entering Now at 14.17%
  • Certified early stage record: enabling and foundation works underway
  • Roughly fifteen months to the Q3 2027 handover window
  • The construction portion of the 70/30 plan spread across monthly installments
Entering Near Completion
  • Structure already certified, far less construction risk left to carry
  • Keys within months of signing rather than years
  • Most of the price falling due in a single completion payment
AED 1.96M ≈ USD 534KStarting Price
70/30 Plan20% on Booking
From Q3 2027Expected Handover

Limited units listed available on the project page as of this update; availability shifts between cycles.

About the Development

Violet 4 Project Details

Violet 4 by DAMAC Properties in DAMAC Hills 2 row of modern villas beside landscaped gardens and a reflective water feature in Dubai - Presented by Tohid Fetrat
DAMAC Hills 2 · DAMAC Properties

With enabling and foundation works underway across the plot, Violet 4 is an early stage cluster of 352 four bedroom townhouses over ground, first and roof levels, positioned opposite Water Town in DAMAC Hills 2. Starting prices: AED 1.96M ≈ USD 534K.

Buyers signing at this point accept a longer wait in return for a construction linked schedule that has barely started drawing down, with keys expected in Q3 2027.

Site Context This Cycle

Explore Violet 4 Location on Dubai Map

Violet 4 occupies plot 19739 in Madinat Hind 4, extending the Violet neighbourhood on the eastern side of DAMAC Hills 2 in long townhouse rows set around a landscaped park strip. That horizontal footprint explains the language of this cycle: on a row cluster the ground works advance plot by plot rather than floor by floor, which is why the May 2026 report records enabling and foundation works at different stages instead of one uniform front.

Because DAMAC Hills 2 is already an occupied master community, with the Water Town, Sports Town and Down Town amenity districts operating and access off Al Qudra Road complete, Violet 4 is being built into a working neighbourhood rather than an empty one, which matters for buyers judging what will surround the plot by the Q3 2027 handover window. See the project's position on the interactive Dubai real estate map. See the project’s position on the interactive Dubai real estate map.

Interactive Dubai real estate map preview

Buyer Resources for This Project

Investing in Violet 4 During Early Construction Progress

The enabling and foundations band is where payment protection and residency planning are decided, long before any handover paperwork exists. Each resource below is matched to where Violet 4 stands right now.

Violet 4 by DAMAC Properties in DAMAC Hills 2 construction updates cover image featuring a project rendering of a modern villa with landscaped surroundings in Dubai - Presented by Tohid Fetrat
You Are Here

Violet 4 Construction Updates

This page: the verified May 2026 inspection record for Violet 4, from enabling works toward handover.

Violet 4 by DAMAC Properties in DAMAC Hills 2 Golden Visa concept graphic with a gold card above a modern villa exterior in Dubai - Presented by Tohid Fetrat

Violet 4 at DAMAC Hills 2 Golden Visa: Which Terrace Qualifies

Every TH12-4E end terrace at Violet 4 at DAMAC Hills 2 qualifies; so does the upper mid terrace band.

Read the Violet 4 Golden Visa Guide
Violet 4 by DAMAC Properties in DAMAC Hills 2 escrow account protection concept with shield and padlock icons above a modern villa and private pool in Dubai - Presented by Tohid Fetrat

Violet 4 at DAMAC Hills 2: The Fourth Release's Escrow

Dubai Islamic Bank keeps Violet 4 at DAMAC Hills 2 escrow under DLD project 3288, 352 units, 14.17% certified May 2026.

Verify the Violet 4 Escrow Account

Update Timeline

Violet 4 Construction Update Timeline

This is the first published inspection record for Violet 4. Every new RERA reading is added here, so the full construction history stays in one place, reading by reading.

All UpdatesViolet 4 Construction Updates Hub
Next Update · One Message Per CycleGet notified the day it publishes
All Violet 4 Construction Updates

FAQs

Violet 4 Construction Progress in May 2026: Frequently Asked Questions

As of the RERA inspection conducted on 13 May 2026, Violet 4 stands at 14.17% construction progress in the DLD project register for project 3288.

The register moves Violet 4 from a previous reading of 0.96% to 14.17% on 13 May 2026, a gain of 13.21 points. No inspection date is published against that earlier 0.96% figure, so the length of the interval the gain covers is not on record, only the distance itself.

The May 2026 record shows no change to the handover window: Q3 2027 remains the anticipated completion period as of this update, with 85.83 percentage points between the 13 May 2026 reading and full certification, roughly fifteen months ahead. The mechanics behind inspection cycles and completion certification are set out on the Violet 4 construction updates hub.

Yes. A registered completion window can be moved between cycles, and a project sitting at 14.17% still has many readings left in which that can happen, unlike one already in its finishing stage. The Q3 2027 window shown here reflects the position as of this update; a revised window would be reported in the following Violet 4 cycle.

The 13 May 2026 monitoring report records mobilization works ongoing, enabling and foundation works progressing at different stages across the plot, substructure, superstructure and MEP works at early stages, and community infrastructure advancing alongside. The progress status logged on that report is main contract progressing.

The 13 May 2026 monitoring report names Dubai Islamic Bank (Public Joint Stock Company) as the trust account bank for project 3288. Installments on a DLD registered off plan project are paid into that escrow account and released to the developer against certified construction progress rather than on request.

A Question the FAQ Can Not Answer?

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is helping you read the May 2026 inspection record for Violet 4 at DAMAC Hills 2 correctly before your next payment decision. Client identities and transactions are never published or referenced. Message me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

Get Progress Alerts