Violet 4 by DAMAC Properties in DAMAC Hills 2 construction updates cover image featuring a project rendering of a modern villa with landscaped surroundings in Dubai - Presented by Tohid Fetrat

DAMAC Properties · DAMAC Hills 2

Violet 4 at DAMAC Hills 2 Construction Updates

The Verified Build Record for a Four-Bedroom Townhouse Cluster in DAMAC Hills 2

Violet 4 recorded 14.17% construction at its 13 May 2026 RERA inspection, the first dated reading in this DAMAC Hills 2 townhouse cluster's build record.

Construction tracking against RERA inspection data, updated after every recorded inspection.

Direct advisor access. Every message answered personally, never by a call center.

14.17%Construction Progress
13 May 2026Latest RERA Inspection
352 townhousesTotal Units
Project 3288DLD Registration

Construction Snapshot

Violet 4 at DAMAC Hills 2 at a Glance

Violet 4 is DAMAC's four-bedroom townhouse cluster inside DAMAC Hills 2, carried on the Dubai Land Department register as project 3288 and under construction since 09 December 2024. Seventeen months of that work sit behind the 14.17% logged on 13 May 2026, which makes this one of the shortest records tracked anywhere on this site. Its 352 homes are also built to two floor plans only, so what the percentage measures here is repetition across identical rows rather than the varied trades a mixed-use tower record would carry.

DLD Project Number

3288

Project Status

Active

Construction Start

09 December 2024

Total Units

352 townhouses

Total Built-Up Area

Registered Completion Date

30 August 2027 (DLD)

Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.

Inspection Record

Violet 4 at DAMAC Hills 2 Construction Update Timeline

One dated reading anchors this record so far: 14.17%, verified at the RERA inspection of 13 May 2026. The project register also displays an earlier figure of 0.96% with no inspection date published beside it, so that number is disclosed here rather than plotted on the track or entered in the table, and it takes no part in any pace figure on this page. Each new reading joins the same track as it is recorded, which is how a single point becomes a curve.

Inspection MonthConstruction ProgressInspection DateFull Update
May 202614.17%13 May 2026View the May 2026 update

Pace Analysis

How Fast Violet 4 at DAMAC Hills 2 Has Been Built

With a single dated inspection on file, Violet 4 has no measured velocity between readings yet. Two figures can still be stated honestly, and both are labelled for exactly what they are:

  • Dec 2024 to May 2026: derived average from the construction start to the first dated reading, 0% to 14.17%About 0.8 points per month (derived)
  • May 2026 to Aug 2027: schedule-implied rate needed to reach the registered completion date of 30 August 2027About 5.5 points per month (schedule-implied)

Neither number is an observed pace, and the distance between them is the whole point at this stage. The 0.8 is an average smeared across seventeen months that covered mobilization, enabling packages and foundations, the phase in which a townhouse cluster consumes calendar without moving a percentage very far. The 5.5 is arithmetic rather than evidence: the remaining 85.83 points divided by the fifteen and a half months left to the registered date. A cluster of repeated prototypes can absorb a rate like that once the frame starts multiplying across finished plots, but nothing on the record has demonstrated it yet. The practical read for a buyer is that the second and third dated readings will say far more about Violet 4 than the first one does, and they are worth waiting for before any conclusion about delivery is drawn.

Get the Next Inspection Figure First

Tell me you are tracking Violet 4 at DAMAC Hills 2 and I will send you the next recorded figure and site photos directly, ahead of the page update.

Get the Next Update on WhatsApp

Project Profile

About Violet 4 at DAMAC Hills 2

A percentage only means something beside what it is building. The project guide covers the homes sitting behind the 14.17%:

Violet 4 by DAMAC Properties in DAMAC Hills 2 row of modern villas beside landscaped gardens and a reflective water feature in Dubai - Presented by Tohid Fetrat

Violet 4 at DAMAC Hills 2: Townhouses Opposite Water Town

Violet 4 at DAMAC Hills 2 is DAMAC's fourth townhouse phase: 352 homes over ground, first and roof levels.

View the Violet 4 at DAMAC Hills 2 Project Guide

Considering an Early-Stage Entry?

Limited units are listed as available at Violet 4, and a cluster this early is where the widest choice of rows, plots and frontages is still on the table. If it is the inspection record that brought you to this page, ask what is left before that selection narrows.

Ask About Remaining Availability on WhatsApp

Stage Record

Violet 4 at DAMAC Hills 2 Build Stages, Mapped to the Inspections

Each stage below is pinned to a date this project actually holds on record rather than to a generic construction sequence, so it is clear where the 13 May 2026 reading falls and what still sits ahead of it.

Nov 2024 to Dec 2024

Registration and Site Start

Project 3288 was entered on the Dubai Land Department register on 04 November 2024, with the trust account held at Dubai Islamic Bank, and construction was recorded as starting on 09 December 2024.

Current PhaseDec 2024 to May 2026, 14.17% at last reading

Mobilization, Enabling and Foundations

The 13 May 2026 inspection found mobilization still running, foundation and enabling packages at uneven stages from row to row, and substructure, superstructure and MEP work all logged as early-stage. This is the band the current percentage sits in.

From 14.17% onward

Superstructure Across the Rows

Concrete frame and block work rising to ground plus two levels on each townhouse. On a cluster of repeated prototypes this is the band where the percentage historically moves fastest, once the first rows are set.

Ahead of the finishing readings

Facades, MEP and Internal Finishes

External and internal finishing to the block-and-concrete shells, mechanical and electrical second fix, then the private gardens, patios and roof terraces that complete each of the 352 homes.

Toward 30 August 2027

Infrastructure, Certification and Handover

Cluster infrastructure, the closing RERA inspection cycles, and completion certification against the registered date of 30 August 2027, the point at which this page converts from a progress record into a delivery record.

What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Violet 4 at DAMAC Hills 2's own record.

Buyer Position

Tracking Your Position at Violet 4 at DAMAC Hills 2

This page is one of four project resources that together cover a Violet 4 at DAMAC Hills 2 purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Violet 4 by DAMAC Properties in DAMAC Hills 2 construction updates cover image featuring a project rendering of a modern villa with landscaped surroundings in Dubai - Presented by Tohid Fetrat
You Are Here

Violet 4 at DAMAC Hills 2 Construction Updates

This page: every dated RERA reading for Violet 4, from the December 2024 start toward handover.

Violet 4 by DAMAC Properties in DAMAC Hills 2 Golden Visa concept graphic with a gold card above a modern villa exterior in Dubai - Presented by Tohid Fetrat

Violet 4 at DAMAC Hills 2 Golden Visa: Which Terrace Qualifies

Every TH12-4E end terrace at Violet 4 at DAMAC Hills 2 qualifies; so does the upper mid terrace band.

Read the Violet 4 at DAMAC Hills 2 Golden Visa Guide
Violet 4 by DAMAC Properties in DAMAC Hills 2 escrow account protection concept with shield and padlock icons above a modern villa and private pool in Dubai - Presented by Tohid Fetrat

Violet 4 at DAMAC Hills 2: The Fourth Release's Escrow

Dubai Islamic Bank keeps Violet 4 at DAMAC Hills 2 escrow under DLD project 3288, 352 units, 14.17% certified May 2026.

Verify the Violet 4 at DAMAC Hills 2 Escrow Account

Approaching Handover

Between 14.17% and Handover: What Violet 4 at DAMAC Hills 2 Buyers Should Do Now

At this end of a record, nothing visible on the plot changes what a buyer should be doing; the schedule does that. A construction-linked plan attaches money to elapsed months from the sale date and to certified build milestones, so the calls arrive on their own timetable whether or not anyone has checked where the money lands. The three items below are worth settling now rather than at the first milestone notice.

First, confirm that every installment reaches the DLD-regulated trust account registered against project 3288 and nothing else; the Violet 4 escrow account page sets out how releases are tied to certified progress rather than to a request from the developer.

Second, if residency is part of the plan, test the threshold against your contracted price now instead of at handover, because the Violet 4 Golden Visa guide works from the figure written into your contract and not from the entry price quoted for the cluster.

Third, follow the readings themselves. With one dated point on file, each new inspection changes what can honestly be said about pace, and the current cycle is set out in full in the Violet 4 May 2026 construction update.

Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.

The Wider Picture

Explore DAMAC Hills 2 Structure

A build record reads differently inside a community that is already lived in. These three pages place Violet 4's 14.17% in its market, community and developer context:

Community view of DAMAC Hills 2 showcasing properties for sale including villas, townhouses, and apartments in Dubai. Presented by Tohid Fetrat

DAMAC Hills 2 Properties for Sale

Browse villas, townhouses and selected apartments for sale in DAMAC Hills 2, with prices and payment plans.

See DAMAC Hills 2 Properties for Sale
DAMAC Hills 2 by DAMAC Properties community park with football field tennis courts basketball courts landscaped pathways and residential villas in Dubai - Presented by Tohid Fetrat

DAMAC Hills 2 Community Overview

Read the DAMAC Hills 2 guide: a self-contained villa community with themed clusters, lifestyle zones and family amenities.

Explore the DAMAC Hills 2 Community
DAMAC Properties development overlooking Dubai skyline and waterfront with modern architecture at sunset in Dubai Presented by Tohid Fetrat

DAMAC Properties: Lagoon Communities, Golf Villas and Branded Collaborations

Founded in 2002, DAMAC has delivered 48,000 homes and is known for large-scale master communities, luxury residential projects and branded collaborations.

View the DAMAC Developer Profile

Construction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.

FAQs

Violet 4 at DAMAC Hills 2 Construction Updates Frequently Asked Questions

Violet 4 carries Active status on the Dubai Land Department register as project 3288, with 14.17% construction verified at the RERA inspection of 13 May 2026. That single dated reading places the cluster in its foundation and early substructure band; the record itself is in the inspection timeline above.

The 13 May 2026 inspection recorded 14.17% construction progress against project 3288. The register also carries an earlier figure of 0.96%, but no inspection date is published beside it, so neither a verified interval nor a measured rate of gain can be derived from the pair. The report for the current cycle is covered in the May 2026 construction update.

With one dated reading on file there is no inter-inspection velocity for Violet 4 yet. Two derived figures can be stated: an average of about 0.8 points per month across the seventeen months from the 09 December 2024 start to the 14.17% of 13 May 2026, and a schedule-implied 5.5 points per month required to reach 100% by the registered date of 30 August 2027. Both are labelled and explained in the pace analysis above.

The completion date registered with the Dubai Land Department for project 3288 is 30 August 2027, which falls inside the Q3 2027 handover window quoted for the cluster. That date has not lapsed, and at 14.17% as of 13 May 2026 most of the inspection cycles are still ahead, so it remains the date on record rather than a confirmed handover.

Violet 4 comprises 352 four-bedroom townhouses built to two prototypes: 220 mid-terrace TH12-4M homes at 2,352.26 sq ft saleable area and 132 end-terrace TH12-4E homes at 2,415.33 sq ft. Each home stacks its four bedrooms over three levels, ground, first and roof, which is the ground-plus-two configuration logged on the RERA monitoring report.

Project 3288 was entered on the Dubai Land Department register on 04 November 2024, and construction was recorded as started on 09 December 2024. The first dated inspection on file arrived seventeen months later, on 13 May 2026, at 14.17%.

At the 13 May 2026 inspection the plot was still in ground works: mobilization continuing, foundation and enabling packages at uneven stages from row to row, and the first substructure, superstructure and MEP activity logged as early-stage, with cluster infrastructure advancing in parallel. That combination is what a 14.17% reading describes on a townhouse cluster.

Violet 4 is registered against plot 19739 at Madinat Hind 4, toward the eastern edge of DAMAC Hills 2, with the Water Town amenity district on its near side. Because the wider master community is already occupied, the cluster is going up between finished streets rather than on open land; its position is mapped in the Violet 4 at DAMAC Hills 2 project guide.

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is keeping the Violet 4 at DAMAC Hills 2 construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

WhatsApp +971543443597
Get the Latest Status