Violet at DAMAC Hills 2 by DAMAC Properties construction update overlooking the townhouse community and landscaped surroundings in Dubai Captured by Tohid Fetrat

DAMAC Properties · DAMAC Hills 2

Violet at DAMAC Hills 2 Construction Updates

The Verified Build Record Across 526 Townhouse Plots

Violet at DAMAC Hills 2 recorded 85.44% construction at its 14 April 2026 RERA inspection, with external works still to close before 526 townhouses hand over.

Construction tracking against RERA inspection data, updated after every recorded inspection.

Direct advisor access. Every message answered personally, never by a call center.

85.44%Construction Progress
14 April 2026Latest RERA Inspection
526 TownhousesTotal Units
Project 2734DLD Registration

Construction Snapshot

Violet at DAMAC Hills 2 at a Glance

Violet is DAMAC Properties' 526-townhouse cluster inside DAMAC Hills 2, registered with the Dubai Land Department as project 2734 on plot 11385 in Madinat Hind 4. Roughly thirty months separate the 23 October 2023 construction start from the 85.44% recorded on 14 April 2026, and the figures below are the DLD-registered anchors behind that reading. Because this is a horizontal build of G+1+R homes rather than a tower, progress moves street by street across the cluster instead of floor by floor, which is why infrastructure and external works carry so much weight in the closing percentage.

DLD Project Number

2734

Project Status

Active

Construction Start

23 October 2023

Total Units

526 townhouses

Total Built-Up Area

73,408.11 sq m

Registered Completion Date

Not published in the DLD record

Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.

Inspection Record

Violet at DAMAC Hills 2 Construction Update Timeline

This record is deliberately short, because that is what the source data supports. The DLD dashboard for project 2734 publishes one dated inspection, 14 April 2026 at 85.44%, and carries the preceding reading of 70.23% without a published date. The 15.21 points between those two readings are the clearest movement figure available for Violet, and the track below plots both against the 100% handover line rather than inventing a date that the record does not hold.

Inspection MonthConstruction ProgressInspection DateFull Update
April 202685.44%14 April 2026View the April 2026 update
Preceding inspection70.23%Not published in the DLD recordNo dated update published
!

Reading the dates: the DLD record for project 2734 carries no registered completion date, and the anticipated completion published by DAMAC in the launch documentation was June 2026, while the last recorded inspection on 14 April 2026 stood at 85.44%. Neither figure is a handover notice: delivery at Violet is confirmed by DAMAC as closing inspections complete, plot by plot across the cluster. Ask for the current handover status on WhatsApp.

Pace Analysis

How Fast Violet at DAMAC Hills 2 Has Been Built

With one dated inspection in the published record, pace at Violet has to be read two ways: the average the whole build has held since the site opened, and the size of the last recorded step.

  • Oct 2023 to Apr 2026: construction start to the 14 April 2026 inspection, 0% to 85.44%About 2.9 points per month
  • Preceding reading to Apr 2026: 70.23% to 85.44%, earlier date not published15.21 points gained

A 2.9-point monthly average sustained across roughly thirty months is the rhythm of a large horizontal cluster: 526 homes progressing in parallel rows, where the percentage climbs through repetition rather than through height. The 15.21-point step into 85.44% is the phase where a townhouse cluster stops looking like a construction site and starts looking like a street, with envelopes closed and internal finishes running through the plots. What remains is 14.56 points, and on this build type that residue is weighted toward MEP commissioning, infrastructure, and external works around the units rather than anything structural. For an investor, the useful signal is that the heavy lifting is behind the figure; for an end user, it is that the gap to 100% will be closed by works that finish quietly and quickly once approvals clear.

Get the Next Inspection Figure First

Tell me you are tracking Violet at DAMAC Hills 2 and I will send you the next recorded figure and site photos directly, ahead of the page update.

Get the Next Update on WhatsApp

Project Profile

About Violet at DAMAC Hills 2

The build percentage only matters in the context of what is being delivered. The full project guide covers what buyers are tracking toward on this page:

Violet at DAMAC Hills 2 by DAMAC Properties contemporary townhouse with private swimming pool landscaped garden and outdoor terrace in Dubai Presented by Tohid Fetrat

Violet at DAMAC Hills 2 Project Guide

The two four-bedroom townhouse prototypes at 2,352 and 2,415 sq ft, the DAMAC Hills 2 amenity towns around the cluster, payment structures, and the full investment case behind DAMAC's Dubailand community.

View the Violet Project Guide

Considering a Near-Handover Entry?

Availability across the Violet cluster continues to shift as the project moves through its final works. If the record on this page is what brought you here, ask me for current availability before the remaining inventory narrows further.

Ask About Remaining Availability on WhatsApp

Stage Record

Violet Build Stages, Mapped to the Recorded Readings

Rather than a generic construction sequence, each stage below is anchored to what Violet's own record supports: the 23 October 2023 start, the undated 70.23% reading, and the 85.44% logged on 14 April 2026.

From 23 October 2023

Site Activation and Plot Infrastructure

DLD registration on 15 August 2023 was followed by a construction start on 23 October 2023: enabling works, roads, and foundations across the 73,408.11 sq m plot.

Across the 526 plots

Concrete Structure and Blockwork

Project 2734 is registered as 526 G+1+R homes in concrete and block, so the structural phase repeats the same frame hundreds of times across the cluster rows.

Recorded at 70.23%

Envelope and Internal Works

The preceding reading of 70.23%, logged without a published date, marks the point where enabling, foundation, structural, and internal works were substantially closed out.

70.23% to 85.44%

MEP, Finishes, and Infrastructure

The 15.21-point step into the April 2026 reading covers envelope completion, MEP, finishes, and cluster infrastructure advancing together toward delivery condition.

Current Phase 14 April 2026, 85.44% recorded

External Works and Handover Preparation

At 85.44% the inspection recorded external works running at different stages across the cluster, which is the last band of the record before unit-by-unit handover.

What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Violet's own record.

Buyer Position

Tracking Your Position at Violet at DAMAC Hills 2

This page is one of four project resources that together cover a Violet purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Violet at DAMAC Hills 2 by DAMAC Properties construction update overlooking the townhouse community and landscaped surroundings in Dubai Captured by Tohid Fetrat
You Are Here

Violet Construction Updates

This page: the verified inspection record for Violet at DAMAC Hills 2, from groundbreaking to handover.

Violet at DAMAC Hills 2 by DAMAC Properties Golden Visa eligibility for townhouse buyers in Dubai Presented by Tohid Fetrat

Violet Golden Visa

Check whether a qualifying Violet townhouse purchase supports 10-year UAE Golden Visa residency eligibility.

Read the Violet Golden Visa Guide
Violet at DAMAC Hills 2 by DAMAC Properties escrow account protection for townhouse buyers in Dubai Presented by Tohid Fetrat

Violet Escrow Account

Verify the Emirates NBD trust account holding Violet payments and how installments track certified milestones.

Verify the Violet Escrow Account
Violet at DAMAC Hills 2 by DAMAC Properties snagging inspection for townhouse exterior and architectural finishes in Dubai Presented by Tohid Fetrat

Violet Snagging Inspection

At 85.44% recorded progress, document defects in your Violet townhouse before you accept handover.

Book Violet Snagging

Approaching Handover

Between 85.44% and Handover: What Violet Buyers Should Do Now

The 14.56 points still open at Violet are closed by commissioning, infrastructure, and external works rather than by anything you can watch rise, which makes this the window where buyer preparation matters more than site watching. Handover notices at comparable projects typically give buyers a short window to complete their appointment, so the three steps below happen now, not when the notice arrives.

First, arrange independent snagging so defects in your townhouse, its garden, and its roof terrace are documented before you accept it; the Violet snagging inspection page covers timing and what gets inspected.

Second, confirm your remaining installments against the certified completion milestones on the Violet escrow account page, since the DAMAC payment structures release funds at completion thresholds rather than on request.

Third, if your purchase may qualify for residency, settle eligibility before handover through the Violet Golden Visa guide, since the title deed timing affects the application path.

Send me your unit number on WhatsApp and I will tell you what the April inspection means for your handover and map the sequence for your specific townhouse.

The Wider Picture

Explore DAMAC Hills 2 Structure

A build record is only half the picture; the other half is what is rising around it. These three pages put Violet's progress in its community and developer context:

Community view of DAMAC Hills 2 showcasing properties for sale including villas, townhouses, and apartments in Dubai. Presented by Tohid Fetrat

DAMAC Hills 2 Properties for Sale

Browse villas, townhouses, and apartments completing across DAMAC Hills 2 while Violet closes its final works.

See DAMAC Hills 2 Properties for Sale
DAMAC Hills 2 by DAMAC Properties community park with football field tennis courts basketball courts landscaped pathways and residential villas in Dubai - Presented by Tohid Fetrat

DAMAC Hills 2 Community Overview

See how DAMAC Hills 2 amenities and infrastructure are maturing around the Violet townhouse cluster.

Explore the DAMAC Hills 2 Community
DAMAC developer iconic modern tower with unique architectural design and Dubai skyline at sunset Presented by Tohid Fetrat

DAMAC Properties Developer Profile

Review DAMAC Properties' delivery record across Dubai before Violet reaches its own handover inspections.

View the DAMAC Properties Developer Profile

Construction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.

FAQs

Violet at DAMAC Hills 2 Construction Updates Frequently Asked Questions

Violet at DAMAC Hills 2 is an active DLD-registered project (number 2734) recorded at 85.44% on 14 April 2026, with envelope, MEP, finishes, and infrastructure at advanced stages and external works still running across the cluster. The full record is in the inspection timeline above.

The 14 April 2026 inspection recorded 85.44% construction progress, 15.21 points above the preceding reading of 70.23%. The site report for that period is in the April 2026 construction update.

The DLD record for project 2734 carries no registered completion date, and the anticipated completion published by DAMAC at launch was June 2026, while the 14 April 2026 inspection recorded 85.44%. Delivery is confirmed by DAMAC as closing inspections complete across the cluster, and this page's record is updated when the next inspection is recorded.

DLD registration records show 526 units across a total built-up area of 73,408.11 sq m, described in the RERA record as G+1+R homes. The two four-bedroom prototypes carry sellable areas of 2,352.26 sq ft and 2,415.33 sq ft, and both are covered in the Violet at DAMAC Hills 2 project guide.

From the 23 October 2023 construction start to the 85.44% recorded on 14 April 2026, the build has averaged roughly 2.9 percentage points per month across about thirty months, and the last recorded step added 15.21 points over the preceding 70.23% reading. The breakdown is in the pace analysis above.

The project was registered with the Dubai Land Department on 15 August 2023 and construction started on 23 October 2023, placing the 85.44% reading of 14 April 2026 roughly thirty months into the build.

The RERA inspection record for project 2734 names Emirates NBD Bank (P.J.S.C) as the trust account bank, with the project registered under developer number 1021. How installments release against certified progress is set out on the Violet at DAMAC Hills 2 escrow account page.

With the project at 85.44% as of 14 April 2026, buyers should arrange independent snagging at Violet at DAMAC Hills 2 ahead of their handover appointment, check remaining installments against certified completion milestones, and settle any residency questions through the Violet at DAMAC Hills 2 Golden Visa guide before the title deed is issued.

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments - Presented by Tohid Fetrat

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is keeping the Violet at DAMAC Hills 2 construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

Get the Latest Status