
DAMAC Properties · DAMAC Hills 2
Violet at DAMAC Hills 2 Construction Updates
The Verified Build Record Across 526 Townhouse Plots
Violet at DAMAC Hills 2 recorded 85.44% construction at its 14 April 2026 RERA inspection, with external works still to close before 526 townhouses hand over.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
Violet at DAMAC Hills 2 at a Glance
Violet is DAMAC Properties' 526-townhouse cluster inside DAMAC Hills 2, registered with the Dubai Land Department as project 2734 on plot 11385 in Madinat Hind 4. Roughly thirty months separate the 23 October 2023 construction start from the 85.44% recorded on 14 April 2026, and the figures below are the DLD-registered anchors behind that reading. Because this is a horizontal build of G+1+R homes rather than a tower, progress moves street by street across the cluster instead of floor by floor, which is why infrastructure and external works carry so much weight in the closing percentage.
2734
Active
23 October 2023
526 townhouses
73,408.11 sq m
Not published in the DLD record
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
Violet at DAMAC Hills 2 Construction Update Timeline
This record is deliberately short, because that is what the source data supports. The DLD dashboard for project 2734 publishes one dated inspection, 14 April 2026 at 85.44%, and carries the preceding reading of 70.23% without a published date. The 15.21 points between those two readings are the clearest movement figure available for Violet, and the track below plots both against the 100% handover line rather than inventing a date that the record does not hold.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| April 2026 | 85.44% | 14 April 2026 | View the April 2026 update |
| Preceding inspection | 70.23% | Not published in the DLD record |
Reading the dates: the DLD record for project 2734 carries no registered completion date, and the anticipated completion published by DAMAC in the launch documentation was June 2026, while the last recorded inspection on 14 April 2026 stood at 85.44%. Neither figure is a handover notice: delivery at Violet is confirmed by DAMAC as closing inspections complete, plot by plot across the cluster. Ask for the current handover status on WhatsApp.
Pace Analysis
How Fast Violet at DAMAC Hills 2 Has Been Built
With one dated inspection in the published record, pace at Violet has to be read two ways: the average the whole build has held since the site opened, and the size of the last recorded step.
- Oct 2023 to Apr 2026: construction start to the 14 April 2026 inspection, 0% to 85.44%About 2.9 points per month
- Preceding reading to Apr 2026: 70.23% to 85.44%, earlier date not published15.21 points gained
A 2.9-point monthly average sustained across roughly thirty months is the rhythm of a large horizontal cluster: 526 homes progressing in parallel rows, where the percentage climbs through repetition rather than through height. The 15.21-point step into 85.44% is the phase where a townhouse cluster stops looking like a construction site and starts looking like a street, with envelopes closed and internal finishes running through the plots. What remains is 14.56 points, and on this build type that residue is weighted toward MEP commissioning, infrastructure, and external works around the units rather than anything structural. For an investor, the useful signal is that the heavy lifting is behind the figure; for an end user, it is that the gap to 100% will be closed by works that finish quietly and quickly once approvals clear.
Get the Next Inspection Figure First
Tell me you are tracking Violet at DAMAC Hills 2 and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About Violet at DAMAC Hills 2
The build percentage only matters in the context of what is being delivered. The full project guide covers what buyers are tracking toward on this page:

Violet at DAMAC Hills 2: A Single-Typology Townhouse Cluster
Violet at DAMAC Hills 2 is a single-typology cluster of 526 four bedroom townhouses positioned directly opposite Water Town.
View the Violet at DAMAC Hills 2 Project GuideConsidering a Near-Handover Entry?
Availability across the Violet cluster continues to shift as the project moves through its final works. If the record on this page is what brought you here, ask me for current availability before the remaining inventory narrows further.
Ask About Remaining Availability on WhatsAppStage Record
Violet at DAMAC Hills 2 Build Stages, Mapped to the Inspections
Rather than a generic construction sequence, each stage below is anchored to what Violet's own record supports: the 23 October 2023 start, the undated 70.23% reading, and the 85.44% logged on 14 April 2026.
Site Activation and Plot Infrastructure
DLD registration on 15 August 2023 was followed by a construction start on 23 October 2023: enabling works, roads, and foundations across the 73,408.11 sq m plot.
Concrete Structure and Blockwork
Project 2734 is registered as 526 G+1+R homes in concrete and block, so the structural phase repeats the same frame hundreds of times across the cluster rows.
Envelope and Internal Works
The preceding reading of 70.23%, logged without a published date, marks the point where enabling, foundation, structural, and internal works were substantially closed out.
MEP, Finishes, and Infrastructure
The 15.21-point step into the April 2026 reading covers envelope completion, MEP, finishes, and cluster infrastructure advancing together toward delivery condition.
External Works and Handover Preparation
At 85.44% the inspection recorded external works running at different stages across the cluster, which is the last band of the record before unit-by-unit handover.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Violet at DAMAC Hills 2's own record.
Buyer Position
Tracking Your Position at Violet at DAMAC Hills 2
This page is one of four project resources that together cover a Violet at DAMAC Hills 2 purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Violet at DAMAC Hills 2 Construction Updates
This page: the verified inspection record for Violet at DAMAC Hills 2, from groundbreaking to handover.

Violet at DAMAC Hills 2 Golden Visa: Only the End Townhouses
Every end townhouse at Violet at DAMAC Hills 2, DAMAC's 526-townhouse community, qualifies; middle townhouses qualify only above the line.
Read the Violet at DAMAC Hills 2 Golden Visa Guide
Violet at DAMAC Hills 2: The First Violet Escrow, 85% Certified
Violet at DAMAC Hills 2, DLD project 2734, escrows 526 units at Emirates NBD, certified 85.44% in April 2026.
Verify the Violet at DAMAC Hills 2 Escrow Account
Violet at DAMAC Hills 2 Snagging in Two Townhouse Prototypes
Violet at DAMAC Hills 2 is a 526 townhouse DAMAC cluster, each home four bedrooms across ground, first and roof levels.
Book Violet at DAMAC Hills 2 SnaggingApproaching Handover
Between 85.44% and Handover: What Violet at DAMAC Hills 2 Buyers Should Do Now
The 14.56 points still open at Violet are closed by commissioning, infrastructure, and external works rather than by anything you can watch rise, which makes this the window where buyer preparation matters more than site watching. Handover notices at comparable projects typically give buyers a short window to complete their appointment, so the three steps below happen now, not when the notice arrives.
First, arrange independent snagging so defects in your townhouse, its garden, and its roof terrace are documented before you accept it; the Violet snagging inspection page covers timing and what gets inspected.
Second, confirm your remaining installments against the certified completion milestones on the Violet escrow account page, since the DAMAC payment structures release funds at completion thresholds rather than on request.
Third, if your purchase may qualify for residency, settle eligibility before handover through the Violet Golden Visa guide, since the title deed timing affects the application path.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore DAMAC Hills 2 Structure
A build record is only half the picture; the other half is what is rising around it. These three pages put Violet's progress in its community and developer context:

DAMAC Hills 2 Properties for Sale
Browse villas, townhouses and selected apartments for sale in DAMAC Hills 2, with prices and payment plans.
See DAMAC Hills 2 Properties for Sale
DAMAC Hills 2 Community Overview
Read the DAMAC Hills 2 guide: a self-contained villa community with themed clusters, lifestyle zones and family amenities.
Explore the DAMAC Hills 2 Community
DAMAC Properties: Lagoon Communities, Golf Villas and Branded Collaborations
Founded in 2002, DAMAC has delivered 48,000 homes and is known for large-scale master communities, luxury residential projects and branded collaborations.
View the DAMAC Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
Violet at DAMAC Hills 2 Construction Updates Frequently Asked Questions
Violet at DAMAC Hills 2 is an active DLD-registered project (number 2734) recorded at 85.44% on 14 April 2026, with envelope, MEP, finishes, and infrastructure at advanced stages and external works still running across the cluster. The full record is in the inspection timeline above.
The 14 April 2026 inspection recorded 85.44% construction progress, 15.21 points above the preceding reading of 70.23%. The site report for that period is in the April 2026 construction update.
The DLD record for project 2734 carries no registered completion date, and the anticipated completion published by DAMAC at launch was June 2026, while the 14 April 2026 inspection recorded 85.44%. Delivery is confirmed by DAMAC as closing inspections complete across the cluster, and this page's record is updated when the next inspection is recorded.
DLD registration records show 526 units across a total built-up area of 73,408.11 sq m, described in the RERA record as G+1+R homes. The two four-bedroom prototypes carry sellable areas of 2,352.26 sq ft and 2,415.33 sq ft, and both are covered in the Violet at DAMAC Hills 2 project guide.
From the 23 October 2023 construction start to the 85.44% recorded on 14 April 2026, the build has averaged roughly 2.9 percentage points per month across about thirty months, and the last recorded step added 15.21 points over the preceding 70.23% reading. The breakdown is in the pace analysis above.
The project was registered with the Dubai Land Department on 15 August 2023 and construction started on 23 October 2023, placing the 85.44% reading of 14 April 2026 roughly thirty months into the build.
The RERA inspection record for project 2734 names Emirates NBD Bank (P.J.S.C) as the trust account bank, with the project registered under developer number 1021. How installments release against certified progress is set out on the Violet at DAMAC Hills 2 escrow account page.
With the project at 85.44% as of 14 April 2026, buyers should arrange independent snagging at Violet at DAMAC Hills 2 ahead of their handover appointment, check remaining installments against certified completion milestones, and settle any residency questions through the Violet at DAMAC Hills 2 Golden Visa guide before the title deed is issued.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the Violet at DAMAC Hills 2 construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.