Project Name
Beachgate by Address

The June 2026 inspection confirms Beachgate by Address has reached 95.03% construction progress, with internal finishes, MEP systems, façade, and external works progressing toward completion at Emaar Beachfront.
Beachgate by Address
2430
Active
95.03%
25 June 2026
23 November 2022
252 residences
37,249.05 sq m
31 December 2026
The latest inspection conducted on 25 June 2026 confirms Beachgate by Address has advanced from 80.19% to 95.03% construction progress, reflecting substantial advancement toward project completion. Internal works have been completed, while external envelope, MEP systems, external works, and finishing activities continue across the development.
Inspection findings confirm that the superstructure, internal works, foundations, and substructure are complete. Current construction efforts are focused on final building systems, façade completion, external landscaping, and remaining finishing works as the project progresses toward its planned December 2026 completion.
The 25 June 2026 inspection confirms Beachgate by Address has entered the final construction stage, with internal works completed while MEP installations, external envelope, external works, and finishing activities continue progressing across the development.
The project comprises a B+G+7 Podium+37 Floor residential tower with retail space, built using a reinforced concrete structure with high-quality internal and external finishes. Construction is advancing toward the scheduled December 2026 completion as final systems and exterior works continue.
Beachgate by Address is positioned within Emaar Beachfront in Dubai Harbour, offering a private island waterfront setting between Dubai Marina and Palm Jumeirah with direct beach access and marina-front living.
The location provides seamless connectivity to Sheikh Zayed Road, Downtown Dubai, Business Bay, and Dubai International Airport while combining beachfront residences with one of Dubai’s most prestigious coastal communities.

The increase from 80.19% to 95.03% construction progress reflects Beachgate by Address entering its final construction stage with completion drawing closer.
Verified progress supports buyer confidence as Beachgate by Address advances toward its scheduled December 2026 handover.
Eligible Beachgate by Address investments may qualify buyers for long-term UAE residency.
Buyer payments remain protected through a DLD-regulated escrow account linked to construction milestones.
Inspect your residence before handover with an independent snagging inspection that identifies defects requiring developer rectification.
Beachgate by Address is a branded beachfront residential development at Emaar Beachfront, offering luxury apartments and penthouses with private beach access, marina views, and premium waterfront living.
Positioned between Dubai Marina and Palm Jumeirah, the project combines direct beach access, branded residences, and strong connectivity within Dubai Harbour.

Beachgate by Address construction updates connect to the wider Emaar Beachfront master community, showcasing branded waterfront residences, private beaches, and marina-front living within Dubai Harbour.
Browse beachfront apartments, penthouses, and branded residences across Emaar Beachfront with private beach access and marina views.
Explore Emaar Beachfront's private beaches, waterfront promenade, marina lifestyle, and premium coastal residential environment.
Learn more about Emaar Properties, its luxury waterfront developments, and landmark residential communities across Dubai.
As of the latest inspection on 25 June 2026, Beachgate by Address has reached 95.03% construction progress.
MEP installations, external envelope, external works, and final finishing activities are progressing toward project completion.
Construction progress increased from 80.19% to 95.03%, reflecting significant advancement toward handover.
The project is scheduled for completion in December 2026, according to the latest project timeline.
Beachgate by Address comprises 252 branded waterfront residences at Emaar Beachfront.
Construction updates provide verified RERA inspection information, helping buyers monitor project milestones and construction progress before handover.

This website uses cookies to ensure you get the best experience on our website.
Copyrights © 2025 Tohid Fetrat
Loading...