Natura at DAMAC Hills 2 by DAMAC Properties contemporary townhouses with landscaped private gardens spacious balconies and modern facade design in Dubai Presented by Tohid Fetrat

DAMAC Properties · DAMAC Hills 2 · Construction Update

Natura Construction Update - May 2026

May 2026 Inspection Confirms Natura at DAMAC Hills 2 Reaches 85.57% Construction Progress

Internal fit out, MEP, envelope, finishes, infrastructure and external works are recorded at advanced stage across Natura's 439 townhouses, verified at 85.57 percent on 13 May 2026.

Direct advisor access. Every message answered personally, never by a call center.

85.57%Construction Progress
13 May 2026Inspection Date
June 2026Anticipated Completion
2735DLD Project Number

Verified DLD Inspection Data

Natura Construction Snapshot

A 17.57 point rise since the previous inspection puts Natura deep inside the finishing band, past the 80% construction milestone written into its launch payment plan and 4.43 points short of the next one.

Project Name

Natura at DAMAC Hills 2

Project Number

2735

Project Status

Active

Construction Progress

85.57%

Inspection Date

13 May 2026

Construction Start

23 October 2023

Total Units

439 townhouses

Total Built Area

60,071.74 sq m

Anticipated Completion

June 2026 (date passed)

Data source: RERA inspection conducted on 13 May 2026 for project 2735, tracked against DLD inspection records. Construction tracking against RERA inspection data runs across the full tohidfetrat.com project portfolio and is reviewed after every published cycle. Last updated: July 2026.

Want each new reading the day it publishes? Message me on WhatsApp and I will send it to you directly: one message per inspection cycle, nothing else.

This Inspection Cycle

Natura Construction Progress Summary

Natura moved from a previously recorded 68% to 85.57% at the 13 May 2026 inspection, a gain of 17.57 points. The inspector's notes carry the more useful detail: enabling, foundation and structure works are logged as completed, while internal, MEP, envelope, finishes, infrastructure and external works are all logged at advanced stage. Nothing structural is left to build at Natura; what remains is the work that turns 439 shells into 439 houses.

Completed
  • Enabling and foundation works across the Natura plot
  • Structure works on all 439 G+1+R townhouses
  • Concrete frame and block work forming the townhouse shells
In Progress at 85.57%
  • Envelope works across the townhouse rows
  • MEP: mechanical, electrical, and plumbing installation
  • Internal and external finishes on the TH12 4 bedroom layouts
  • Infrastructure and external works: cluster roads, services, landscaping
Ahead of Handover
  • Remaining RERA inspection cycles toward 100%
  • Building completion certificate procedures
  • Handover, with no confirmed completion date currently in the DLD register
Next inspectionPublished in the DLD project register after the next RERA site visit; this page updates with each cycle.
Completion targetDAMAC's launch documents carried an anticipated completion date of June 2026. That date has now passed, and the DLD project register carries no confirmed completion date for project 2735 as of this update.
Remaining distance14.43 percentage points separate the 13 May 2026 reading from a 100% certified position.

Payment Linked Progress

What 85.57% Progress Means for Natura Buyers

Natura launched on a 60/40 plan whose back end is tied directly to certified construction: 5% falls due at 80% completion, another 5% at 90% completion, and 40% on completion itself. At a verified 85.57%, the first of those triggers is already behind the project and the second sits 4.43 points ahead. Four actions matter most at this reading.

Before Any Remaining Payment

Verify the escrow account

The 13 May 2026 inspection report records the project trust account bank as Emirates NBD Bank (P.J.S.C). Any payment still ahead of handover should go only to the DLD regulated escrow account registered for project 2735. The Natura escrow account verification is the step before any transfer; the lookup itself takes about two minutes against the official DLD project record.

Before the 90% Trigger

Reread your SPA milestone schedule

The launch plan is the template, but your sale and purchase agreement is the contract: check how it defines the completion linked installments and the handover notice period. Not sure how your installments map to this reading? Send me your SPA schedule and I will map it against the certified milestones.

Window Open Now

Book the snagging window

At 85.57% recorded progress, with the anticipated completion window already behind the project, Natura is squarely inside the booking period for a pre handover inspection. The Natura snagging inspection guide covers what independent defect documentation should cover on a G+1+R townhouse before acceptance.

Every Cycle

Track the remaining cycles

With no confirmed completion date in the register, the inspection readings are the only reliable schedule Natura buyers have. The Natura construction updates hub collects each verified cycle as it publishes.

General framework, not legal advice: milestone definitions, notice periods, and fee obligations are set by your individual SPA and the DLD record, and both should be read directly.

Buying at 85.57%?

Entering a project this deep into finishing trades payment plan runway for evidence: the structure is certified, the remaining works are visible ones, and the developer's June 2026 anticipated completion date has already passed without a certified handover, which is precisely why the inspection record above carries more weight here than any launch brochure. Every payment goes to the DLD-registered escrow account for project 2735, released against certified construction progress.

Entering Now at 85.57%
  • Certified structure: the 13 May 2026 record is the risk picture
  • 14.43 points remain to a 100% certified position
  • The 80% completion installment is already behind the project
Typical Launch Entry
  • Construction risk carried from enabling works to handover
  • Two to four years of waiting is the usual delivery horizon
  • Longer installment runway, priced at launch levels
AED 1.83M ≈ USD 498KStarting Price
60/40 Plan40% Due on Completion
439 Townhouses4 Bedroom G+1+R
Ask What Is Available at Natura

Natura launched with 439 four bedroom townhouses; remaining availability shifts between cycles and is checked against the live developer price list at the time of enquiry.

About the Development

Natura Project Details

Natura at DAMAC Hills 2 by DAMAC Properties contemporary townhouse front elevation with covered parking balconies landscaped surroundings and modern architecture in Dubai Presented by Tohid Fetrat
DAMAC Hills 2 · DAMAC Properties

With structure works closed out across the plot, Natura is a finishing stage cluster of 439 four bedroom G+1+R townhouses in two layouts, TH12-4E and TH12-4M, each carrying a ground floor garden, first floor balconies, and a roof terrace built for later expansion. Starting prices: AED 1.83M ≈ USD 498K.

The trade off for buyers entering now is a back loaded plan against a short remaining build: 40% of the price falls due on completion, and with the June 2026 anticipated date already passed, the inspection readings rather than the brochure define the schedule.

Natura at DAMAC Hills 2 Project Guide

Site Context This Cycle

Explore Natura Location on Dubai Map

Natura sits on plot 13116 in Madinat Hind 4, on the outer edge of DAMAC Hills 2 directly opposite Water Town, and the cluster is laid out as long townhouse rows threaded along internal loop roads rather than as towers on a single footprint. That geometry explains why the May 2026 inspection logs infrastructure and external works advancing alongside the finishes: the roads, services, and landscaping between the rows have to be completed at the same pace as the houses standing on them.

Because DAMAC Hills 2 is an established and largely delivered community, with Water Town, Sports Town, and Down Town already operating, Natura is finishing into a working neighborhood rather than an empty one, which changes the calculation for buyers weighing occupancy or rental plans now that the anticipated completion window has come and gone. See the cluster's position on the interactive Dubai real estate map.

Interactive Dubai real estate map preview
Click to view Natura at DAMAC Hills 2 on Dubai Map

Buyer Resources for This Project

Investing in Natura During Final Construction Progress

Past the 80% mark, three questions turn practical at once: whether the money is protected, whether the purchase clears the residency threshold, and who inspects the townhouse before you sign for it. Each resource below is matched to where Natura stands right now.

Natura at DAMAC Hills 2 by DAMAC Properties contemporary townhouses with landscaped private gardens spacious balconies and modern facade design during construction update in Dubai Presented by Tohid Fetrat
You Are Here

Natura Construction Updates

This page: the verified 13 May 2026 inspection record for Natura, from enabling works through finishing.

Natura at DAMAC Hills 2 by DAMAC Properties contemporary townhouses highlighting Golden Visa eligibility opportunity in Dubai Presented by Tohid Fetrat

Natura Golden Visa

Check whether a qualifying Natura townhouse supports 10 year UAE Golden Visa residency eligibility.

Read the Natura Golden Visa Guide
Natura at DAMAC Hills 2 by DAMAC Properties aerial community view highlighting escrow account protection and secure property investment in Dubai Presented by Tohid Fetrat

Natura Escrow Account

Confirm the DLD registered escrow account for project 2735, held with Emirates NBD, before releasing installments.

Verify the Natura Escrow Account
Natura at DAMAC Hills 2 by DAMAC Properties townhouse balcony overlooking landscaped streets and contemporary residences highlighting independent snagging inspection in Dubai Presented by Tohid Fetrat

Natura Snagging Inspection

At 85.57% recorded progress, arrange independent defect documentation before you accept your Natura townhouse.

Book the Natura Snagging Inspection

Update Timeline

Other Natura Construction Updates

This is the first inspection reading published in the Natura record. Each new RERA cycle is added here as it is verified, so the finishing stretch can be read reading by reading rather than guessed at.

All Natura Construction Updates

FAQs

Natura Construction Progress in May 2026: Frequently Asked Questions

As of the RERA inspection conducted on 13 May 2026, Natura stands at 85.57% construction progress in the DLD project register, under project number 2735.

Natura moved from a previously recorded 68% to 85.57% on 13 May 2026, a gain of 17.57 points. The register screen carries no date against the earlier reading, so this page states the previous figure without asserting a month for it.

No. DAMAC's launch documents carried an anticipated completion date of June 2026, and the most recent verified reading places Natura at 85.57% on 13 May 2026, short of certification. The DLD project register carries no confirmed completion date for project 2735 as of this update, so the inspection cycles are currently the only dated schedule available. Each new cycle is recorded on the Natura construction updates hub.

The 13 May 2026 inspection notes record enabling, foundation and structure works as completed, with internal works, MEP, envelope, finishes, infrastructure and external works all progressing at advanced stage across the 439 G+1+R townhouses. The contract status is logged as Main Contract - Progressing.

On the 60/40 launch plan, Natura carries three construction linked triggers at the back end: 5% at 80% completion, 5% at 90% completion, and 40% on completion. The 85.57% reading of 13 May 2026 sits past the first and 4.43 points short of the second. Individual obligations are defined by each buyer's SPA, which can differ from the launch schedule.

Yes, the window is open. The practical booking period opens once a project passes roughly 70% or comes within months of expected handover, and at 85.57% with its anticipated completion date already passed, Natura meets both conditions. Booking ahead of the handover notice avoids a compressed inspection and rectification timeline on a three level townhouse.

A Question the FAQ Can Not Answer?

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is helping you read the May 2026 inspection record for Natura correctly before your next payment decision. Client identities and transactions are never published or referenced. Message me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

Get Progress Alerts