OMNIYAT · Palm Jumeirah
Orla Infinity Dorchester Collection Construction Updates
Twenty Duplex Residences Rising on the Palm Jumeirah Crescent
Orla Infinity reached 40.02% construction at its 16 March 2026 RERA inspection, with the concrete structure climbing above Palm Jumeirah's crescent toward a Q2 2027 handover.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
Orla Infinity Dorchester Collection at a Glance
Orla Infinity is OMNIYAT's 20-residence Dorchester Collection building on the Palm Jumeirah crescent, carried on the DLD register as project 2664. Just under two and a half years separate its 31 October 2023 construction start from the 40.02% recorded at the March 2026 inspection, and the figures below are the registered anchors behind that reading. ORLA Infinity contains only 20 four-bedroom duplex residences, with individual homes ranging from 7,679 to 8,582 sq ft (713 to 797 sq m). Its low unit count and large-format residences make it materially different from a conventional tower containing hundreds of smaller apartments.
2664
Active
31 October 2023
20 duplex residences
15,199.52 sq m
Q2 2027
Figures from Dubai Land Department registration records and RERA inspection reports, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
Orla Infinity Dorchester Collection Construction Update Timeline
This record is deliberately short: registration was completed on 31 July 2023, work started on plot 3402 that October, and the DLD dashboard currently carries two readings for project 2664. The dated one is 40.02% on 16 March 2026. The reading before it, 24.94%, is published without a date, so it appears on the track below at its exact percentage but without a month label rather than being given one it does not have.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| March 2026 | 40.02% | 16 March 2026 | View the March 2026 update |
| Preceding reading | 24.94% | Date not published by DLD | Not published |
Pace Analysis
How Fast Orla Infinity Has Been Built
With one dated reading on the dashboard, the honest pace measure for project 2664 is the average across the whole build so far rather than a phase-by-phase velocity:
- Oct 2023 start to the 16 Mar 2026 inspection: 0% to 40.02% across roughly 28.5 monthsAbout 1.4 points per month
- Preceding recorded reading to 16 Mar 2026: 24.94% to 40.02%, interval undated15.08 points gained
The 15.08-point step between the two published readings is real, but no points-per-month figure is stated for it here, because the earlier reading carries no date and a velocity invented from a guessed interval would be worse than no number at all. What can be said with confidence is the long-run average: 40.02% in about 28.5 months of site work, which is the signature of a concrete-frame building working through piling, foundations, structure, envelope, internal finishes, and MEP in parallel rather than in tidy sequence, exactly as the March 2026 inspection notes describe.
The arithmetic ahead is what an investor should be reading. Closing the remaining 59.98 points by the Q2 2027 handover guidance implies a run rate near 3.9 points per month, roughly two and a half times the average recorded so far. That is not an alarm: percentage progress on a B+GF+MZ+10 residential building accelerates once the frame is topped out and fit-out, glazing, and terrace pools start landing across all 20 duplexes at once. It does mean the next recorded reading is the number that matters most, and it is the one to watch rather than any brochure timeline.
Get the Next Inspection Figure First
Tell me you are tracking Orla Infinity and I will send you the next recorded RERA figure the moment it lands, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About Orla Infinity Dorchester Collection at Palm Jumeirah
A percentage only means something once you know what those points are buying. The project guide covers what the 40.02% on this page is building toward:
Orla Infinity Dorchester Collection Project Guide
Twenty duplex residences on a B+GF+MZ+10 frame on Palm Jumeirah plot 3402, with Foster + Partners architecture, YODEZEEN interiors, ZED Collective landscaping, and Dorchester Collection management. The guide covers layouts, the terrace pools running up to 18 metres, the shared Orla amenity deck, and the investment case behind the OMNIYAT beachfront position.
View the Orla Infinity Project GuideConsidering an Entry Before the Frame Tops Out?
With 20 residences in the entire building, availability at Orla Infinity moves in single units rather than in releases, and it shifts as the project advances toward completion. If the record on this page is what brought you here, ask me what is actually available right now.
Ask About Remaining Availability on WhatsAppStage Record
Orla Infinity Build Stages, Mapped to the Record
Each stage below is tied to the dates and percentages actually on file for project 2664, so you can see where the 40.02% recorded in March 2026 sits in the sequence and what is still ahead of it.
Registration and Site Mobilization
Project 2664 was registered with the DLD on 31 July 2023 and the escrow structure opened with Mashreq Bank PSC. Construction was recorded as started on 31 October 2023.
Piling and Basement
Piling and foundations for a beachfront basement on plot 3402, the slowest points on any Palm build and the reason the average sits at 1.4 points per month.
Concrete Frame and External Envelope
The March 2026 inspection recorded structure, external envelope, internal works, finishes, and MEP all progressing at different stages across the B+GF+MZ+10 frame, at 40.02%.
Duplex Fit-Out and Terrace Pools
The phase where the percentage historically climbs fastest: interiors across the 20 duplexes, glazing, and the private terrace pools of up to 18 metres built into each residence.
Landscaping, Commissioning, and Handover
Beach and garden landscaping, systems commissioning, and closing approvals ahead of the Q2 2027 handover guidance. This page records each reading until the final one.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays on Orla Infinity's own record.
Buyer Position
Tracking Your Position at Orla Infinity Dorchester Collection
Four resources cover an Orla Infinity purchase end to end: the construction record you are reading now, plus residency, payment protection, and handover inspection. The siblings sit one click away:

Orla Infinity Construction Updates
This page: the verified RERA inspection record for Orla Infinity, from the 2023 groundbreaking to handover.
Orla Infinity Golden Visa
Confirm how a duplex purchase at project 2664 sits against the 10-year Golden Visa property threshold.
Read the Orla Infinity Golden Visa Guide
Orla Infinity Escrow Account
See how Orla Infinity installments release into the Mashreq Bank escrow account against certified construction milestones.
Verify the Orla Infinity Escrow Account
Orla Infinity Snagging Inspection
At 40.02% recorded progress, plan independent defect documentation well before your duplex handover appointment.
Plan Orla Infinity SnaggingMid-Build Position
Between 40.02% and Topping Out: What Orla Infinity Buyers Should Do Now
At this point in the record the building still has more to go than it has done, and the buyer's job is verification rather than handover preparation. Payment requests during the structure phase arrive tied to construction milestones, and the window to check one against the certified record closes quickly once an invoice lands, so the three steps below belong in the diary now.
First, match every remaining installment to the milestones certified into escrow; the Orla Infinity escrow account page shows how the Mashreq trust account releases funds against inspected progress rather than against a request.
Second, settle residency eligibility early instead of at title deed stage; the Orla Infinity Golden Visa guide sets out how an off-plan purchase at project 2664 is assessed while the building is still rising.
Third, follow the record itself. Readings on this project are published irregularly, so the Orla Infinity March 2026 inspection report is the current baseline, and this page is amended the moment RERA files the next one.
Send me your residence number on WhatsApp and I will tell you what the March inspection means for your payment schedule and map the sequence for your specific duplex.
The Wider Picture
Explore the Palm Jumeirah Picture
At 40.02%, what is happening around plot 3402 matters as much as what is rising inside it. These three pages set the record in its island, community, and developer context:
Palm Jumeirah Properties for Sale
Browse beachfront apartments and villas delivering around Orla Infinity on the Palm Jumeirah crescent.
See Palm Jumeirah Properties for Sale
Palm Jumeirah Community Overview
See how the crescent's beachfront plots and infrastructure are filling in around project 2664.
Explore the Palm Jumeirah Community
OMNIYAT Developer Profile
Review the OMNIYAT portfolio and delivery record behind project 2664 before Orla Infinity reaches handover.
View the OMNIYAT Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
Orla Infinity Dorchester Collection Construction Updates Frequently Asked Questions
Orla Infinity is an active DLD-registered project (number 2664) working through its concrete frame and external envelope, recorded at 40.02% at the inspection of 16 March 2026. The full record is in the inspection timeline above.
The 16 March 2026 inspection recorded 40.02% construction progress, up 15.08 points from the preceding recorded reading of 24.94%. The inspection notes list piling, foundation, structure, internal works, external envelope, internal finishes, and MEP as progressing at different stages on site. The site report is in the March 2026 construction update.
From the 31 October 2023 construction start to the 16 March 2026 inspection, Orla Infinity recorded 40.02% across roughly 28.5 months of site work, an average of about 1.4 percentage points per month. A phase velocity between the 24.94% and 40.02% readings cannot be calculated because the earlier reading is published without a date. The full working is in the pace analysis above.
The working handover window for Orla Infinity is Q2 2027. The DLD record for project 2664 does not currently publish a usable registered completion date, so the timeline on this page is anchored to that handover guidance and to the recorded inspection readings, most recently 40.02% on 16 March 2026. The record here is amended each time a new inspection is filed.
DLD registration records show 20 residential units at ORLA Infinity. The project specifications identify them as four-bedroom duplex residences ranging from 7,679 to 8,582 sq ft (713 to 797 sq m). The registered project built-up area should not be interpreted as the internal or saleable area of an individual residence.
Project 2664 was registered on 31 July 2023 and construction was recorded as started on 31 October 2023. The earliest reading currently carried on the DLD dashboard is 24.94%, published without a date; the first dated reading in the record is 40.02% on 16 March 2026.
The RERA project description records a B+GF+MZ+10 residential building of duplex apartments, a concrete structure with block, internal, and external finishes, on plot 3402 on the Palm Jumeirah crescent. All 20 residences are duplexes with private terrace pools running up to 18 metres, under Dorchester Collection management. Layouts and specifications are in the Orla Infinity Dorchester Collection project guide.
Orla Infinity is the 20-residence building of the two that OMNIYAT is delivering on the same beachfront position, sharing the amenity deck and beach club with its neighbour Orla. It carries its own DLD registration as project 2664 and its own inspection record, which is why 40.02% at 16 March 2026 describes this building specifically and not the site as a whole. The wider position is covered on the Palm Jumeirah community page.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the Orla Infinity Dorchester Collection construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.