DAMAC Properties · DAMAC Hills
Golf Gate 2 Construction Updates
The Verified Build Record on the DAMAC Hills Golf Edge
Golf Gate 2 reached 60.02% construction at its 25 March 2026 RERA inspection, with the concrete frame substantially complete and finishing works carrying the climb toward handover.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
Golf Gate 2 at a Glance
Golf Gate 2 is DAMAC Properties' 464-apartment tower on plot 2128 in Al Hebiah Third, standing on the golf-facing edge of DAMAC Hills rather than inside the villa clusters. Thirty-two months separate its 03 August 2023 construction start from the 60.02% recorded in March 2026, and the anchors below come from the DLD register for project 2698. One of them is a blank: the register carries no completion date for this project, which is why every date on this page is an inspection date rather than a promise.
2698
Active
03 August 2023
464 apartments
78,793.05 sq m
Q4 2026
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
Golf Gate 2 Construction Update Timeline
Three readings sit in this record: an undated 30.12% entry carried in the register, 43.25% certified on 27 November 2025, and 60.02% on 25 March 2026. The register publishes no date against the 30.12% figure, so it is shown here exactly as it stands, without a month attached to it. Each dated reading below links the full monthly update.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| March 2026 | 60.02% | 25 March 2026 | View the March 2026 update |
| November 2025 | 43.25% | 27 November 2025 | View the November 2025 update |
| Earlier reading | 30.12% | Not published in the register | No monthly update published for this reading |
Reading the dates: the DLD register carries no completion date for project 2698; the field returns a system null rather than a date. DAMAC states a Q4 2026 handover target, which is a developer figure and not a registered one, and the two should never be quoted as the same thing. Ask for the current handover position on WhatsApp.
Pace Analysis
How Fast Golf Gate 2 Has Been Built
Only two readings in this register carry dates, so the pace math is built around them and around the whole-build average since the August 2023 start:
- Aug 2023 to Nov 2025: construction start to 43.25%About 1.6 points per month
- Undated 30.12% reading to 43.25% on 27 Nov 202513.13 points, no cycle length published
- Nov 2025 to Mar 2026: structure closeout into finishing, 43.25% to 60.02%About 4.3 points per month
The one dated interval in this record is the interesting one. Between 27 November 2025 and 25 March 2026, Golf Gate 2 added 16.77 points in under four months, roughly two and a half times the 1.6 points per month the project averaged from groundbreaking to that November reading. That jump is what the closeout of a concrete frame looks like on a register: the last floors of a G+2P+27 tower are poured, structure is signed off as substantially complete, and internal, external, and MEP packages that had been opened floor by floor all start certifying at once. What the register does not let anyone do is slice it finer, because the 30.12% entry carries no date. For a buyer, the useful read is that 39.98 points remain and the last certified cycle was the fastest on this record, while the 70% milestone that the payment plan cares about sits 9.98 points above the current reading.
Get the Next Inspection Figure First
Tell me you are tracking Golf Gate 2 and I will send you the next recorded figure directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About Golf Gate 2 at DAMAC Hills
The build percentage only matters in the context of what is being delivered. The full project guide covers what buyers are tracking toward on this page:
Golf Gate 2 Project Guide
One and two bedroom layouts across 464 apartments, the podium amenity deck, the golf-course orientation of the tower, and the full investment case behind DAMAC's second Golf Gate release.
View the Golf Gate 2 Project GuideConsidering an Entry at 60.02%?
Availability at Golf Gate 2 shifts between inspection cycles, and the structural phase is now behind the project rather than ahead of it. If the record on this page is what brought you here, ask me what is currently released before the next reading publishes.
Ask About Remaining Availability on WhatsAppStage Record
Golf Gate 2 Build Stages, Mapped to the Inspections
Rather than a generic construction sequence, each stage below is anchored to the inspection window it actually occupied in this project's record, so you can see when Golf Gate 2 passed through it.
Site Activation and Substructure
From the 03 August 2023 construction start: enabling works, foundations, and the ground and podium levels of the tower on plot 2128 in Al Hebiah Third.
Frame Rising, No Date Attached
The register carries a 30.12% reading with no inspection date published against it, so this milestone sits in the record as a percentage only, without a month.
Superstructure at Advanced Stages
The 27 November 2025 inspection recorded 43.25%: structure works advanced across the G+2P+27 frame, with block work and MEP first fix opened on the completed floors below.
Structure Closeout, Facade, and Fit-Out
The fastest certified cycle in this record: 16.77 points to 60.02% on 25 March 2026, the report noting structure substantially complete with internal, external, and MEP works at advanced stages.
Finishing, Commissioning, and Handover
Apartment finishes across the 464 units, external works around the tower, completion certification, and handover against the developer's stated Q4 2026 target.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Golf Gate 2's own record.
Buyer Position
Tracking Your Position at Golf Gate 2
This page is one of four project resources that together cover a Golf Gate 2 purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Golf Gate 2 Construction Updates
This page: the verified inspection record for Golf Gate 2, from construction start to handover.
Golf Gate 2 Golden Visa
Golf Gate 2 pricing sits below the AED 2 million property route; the guide maps eligibility.
Read the Golf Gate 2 Golden Visa Guide
Golf Gate 2 Escrow Account
Verify the DLD-registered escrow account for project 2698 before you release your next milestone installment.
Verify the Golf Gate 2 Escrow Account
Golf Gate 2 Snagging Inspection
At 60.02% recorded progress, the defect documentation window opens as Golf Gate 2 passes 70%.
Plan Golf Gate 2 Snagging TimingApproaching the Milestone Band
Between 60.02% and the 70% Milestone: What Golf Gate 2 Buyers Should Do Now
The published Golf Gate 2 plan calls installments at the 70%, 80%, and 90% completion marks, and the current reading sits 9.98 points below the first of them. At the 4.3 points per month recorded in the last certified cycle, that gap is measured in inspection cycles rather than years, which makes this the window where the paperwork gets checked, not the one where it gets rushed.
First, confirm where your money goes: the Golf Gate 2 escrow account page shows the DLD-registered trust account for project 2698, so a milestone installment is released against certified progress rather than against a request.
Second, read the timing on the Golf Gate 2 snagging inspection guide; the booking window opens as the project clears roughly 70% recorded progress, which is the next milestone on this record rather than a distant one.
Third, if residency is part of your plan, the Golf Gate 2 Golden Visa guide sets out how a purchase at this price level measures against the property thresholds, since the answer depends on total value rather than on the build percentage.
Send me your unit number on WhatsApp and I will tell you what the March inspection means for your remaining installments and map the sequence for your specific unit.
The Wider Picture
Explore DAMAC Hills Structure
A build record is only half the picture; the other half is what already stands around it. These three pages put Golf Gate 2's progress in its community and developer context:
DAMAC Hills Villas and Townhouses for Sale
Delivered DAMAC Hills homes trade today while Golf Gate 2 works through its remaining 39.98 points.
See DAMAC Hills Villas and Townhouses for Sale
DAMAC Hills Community Overview
The golf course, schools, and retail around plot 2128 were finished long before this tower started.
Explore the DAMAC Hills CommunityDAMAC Properties Developer Profile
Read DAMAC's delivery record across DAMAC Hills against the inspection cycles certified on this page.
View the DAMAC Properties Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
Golf Gate 2 Construction Updates Frequently Asked Questions
Golf Gate 2 is an active DLD-registered project (number 2698) in its finishing and fit-out phase, recorded at 60.02% at the inspection of 25 March 2026, with structure works reported as substantially complete. The full record is in the inspection timeline above.
The 25 March 2026 inspection recorded 60.02% construction progress, up 16.77 points from the 43.25% certified on 27 November 2025. The cycle detail is in the Golf Gate 2 March 2026 construction update.
The DLD register carries no completion date for project 2698: the field returns a system null rather than a date, so no registered completion date can be quoted. DAMAC states a Q4 2026 handover target, which is a developer figure rather than a registered one. With 39.98 points remaining as of 25 March 2026, this page's record is updated as each further inspection is certified.
DLD registration records show 464 apartments across a total built-up area of 78,793.05 sq m, laid out as one and two bedroom homes in a single G+2P+27 tower on the golf-facing edge of DAMAC Hills.
Across the only dated interval in the register, 27 November 2025 to 25 March 2026, the project certified 16.77 points in under four months, about 4.3 percentage points per month. That is roughly two and a half times the 1.6 points per month averaged from the 03 August 2023 construction start to the November 2025 reading. The full breakdown is in the pace analysis above.
Construction officially started on 03 August 2023 on plot 2128 in Al Hebiah Third. The first dated inspection carried in this record is 27 November 2025 at 43.25%, documented in the Golf Gate 2 November 2025 construction update.
The register carries a 30.12% figure for project 2698 without publishing a date against it, which happens when the date field is not populated in the DLD record. It is shown on this page as a percentage without a month, and no velocity is calculated across it, because a pace figure needs two dated points.
The published payment plan attaches installments to the 70%, 80%, and 90% completion milestones, with 20% falling due on completion. The 25 March 2026 reading of 60.02% sits 9.98 points below the first of them, so no completion-linked installment has been triggered by this reading. Individual obligations are governed by the sale and purchase agreement, and the funds themselves are released through the project's Golf Gate 2 escrow account verification guide.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the Golf Gate 2 construction record accurate, inspection by inspection, until handover. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.