Anya 2 at Arabian Ranches 3 by Emaar Properties contemporary townhouse exterior at dusk featured for construction updates in Dubai - Presented by Tohid Fetrat

Emaar Properties · Arabian Ranches 3

Anya 2 at Arabian Ranches 3 Construction Updates

A Dated Inspection Record for 362 G+1 Townhouses in Wadi Al Safa 5

Anya 2 at Arabian Ranches 3 reached 97.01% at its 15 July 2026 RERA inspection, leaving the last finishes across 362 townhouses before a Q4 2026 handover.

Construction tracking against RERA inspection data, updated after every recorded inspection.

Direct advisor access. Every message answered personally, never by a call center.

97.01%Construction Progress
15 July 2026Latest RERA Inspection
362 townhouses (G+1)Total Units
Project 2609DLD Registration

Construction Snapshot

Anya 2 at Arabian Ranches 3 at a Glance

Anya 2 is Emaar Properties' cluster of 362 ground plus first floor townhouses on plot 7970 in Wadi Al Safa 5, inside the Arabian Ranches 3 master community. It was registered with the DLD on 17 March 2023, broke ground on 26 June 2023 and stood at 97.01% on 15 July 2026, and the registered anchors behind that record are listed below. Because every home here is a two-storey house rather than a floor in a tower, the last points on this record are spread across 362 separate facades, gardens and driveways plus the streets that join them, which is why the final stretch moves slowly on paper.

DLD Project Number

2609

Project Status

Active

Construction Start

26 June 2023

Total Units

362 townhouses (G+1)

Total Built-Up Area

72,269.27 sq m

Registered Completion Date

30 December 2026 (DLD)

Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.

Inspection Record

Anya 2 at Arabian Ranches 3 Construction Update Timeline

The DLD record for Anya 2 carries two dated readings, 94.93% on 17 March 2026 and 97.01% on 15 July 2026, a spread of 2.08 points in 120 days. A third figure, 86.65%, appears in the March 2026 entry as the previous reading with no date attached, so it sits on the track below as an undated marker and stays out of the table. Each table row links the full monthly update for its inspection.

Inspection MonthConstruction ProgressInspection DateFull Update
July 202697.01%15 July 2026View the July 2026 update
March 202694.93%17 March 2026View the March 2026 update

Pace Analysis

How Fast Anya 2 at Arabian Ranches 3 Has Been Built

With two dated inspections on record, Anya 2 has one measurable pace interval, and it sits entirely inside the finishing stretch of the build:

  • Mar 2026 to Jul 2026: finishing and external works, 94.93% to 97.01%About 0.52 points per month

That rate describes a townhouse cluster whose structure was already standing before its first dated reading: the 17 March 2026 report lists enabling, foundation, structural and internal works as complete, so the 2.08 points added by 15 July 2026 came from the envelope, MEP, finishes, external works and infrastructure alone. With no earlier dated interval to compare against, this record cannot yet show an acceleration or a taper, and the undated 86.65% reading marks where the project once stood without giving a time base for a rate. What the interval does show is arithmetic. On 15 July 2026, 2.99 points remained and 168 days separated the inspection from the registered 30 December 2026 completion date, which needs roughly 0.53 points per 30-day month against the 0.52 recorded. For an end user, the Q4 2026 handover rests on that finishing pace holding steady; for an investor, the next reading is the one that shows whether it has.

Get the Next Inspection Figure First

Tell me you are tracking Anya 2 at Arabian Ranches 3 and I will send you the next recorded figure and site photos directly, ahead of the page update.

Get the Next Update on WhatsApp

Project Profile

About Anya 2 at Arabian Ranches 3 at Arabian Ranches 3

A 97.01% reading only means something next to what is being finished. The project guide covers the homes this record is tracking toward:

Anya 2 at Arabian Ranches 3 by Emaar Properties contemporary townhouse exterior with modern architecture, landscaped frontage, covered parking, and palm lined streetscape in Dubai - Presented by Tohid Fetrat

Anya 2 at Arabian Ranches 3 in Luna, Aria and Iris Styles

Anya 2 at Arabian Ranches 3 is a gated Emaar cluster of 362 townhouses with a private clubhouse, gym and pool.

View the Anya 2 at Arabian Ranches 3 Project Guide

Considering a Near-Handover Entry?

Units at Anya 2 are limited as of this update, and what remains keeps changing as the cluster moves toward its Q4 2026 handover. If this record is what brought you here, ask me which townhouses are still open before the choice narrows further.

Ask About Remaining Availability on WhatsApp

Stage Record

Anya 2 at Arabian Ranches 3 Build Stages, Mapped to the Inspections

Each stage below is pinned to the dates in Anya 2's own record, from DLD registration on 17 March 2023 to the 97.01% reading of 15 July 2026, rather than to a textbook sequence.

Mar 2023 to Jun 2023

Registration and Site Start

Project 2609 was registered with the DLD on 17 March 2023, and construction on plot 7970 in Wadi Al Safa 5 started on 26 June 2023.

From Jun 2023

Enabling Works and Foundations

Enabling and foundation works for the 362 townhouses followed the 26 June 2023 start; both 2026 inspection reports list them as complete.

Complete by 17 Mar 2026

Concrete and Block Structure

The concrete structure and block walls of every G+1 home were reported complete at the 17 March 2026 inspection, which recorded 94.93%.

Undated 86.65% reading to 17 Mar 2026

Internal Works, MEP and Envelope

Internal works were listed complete by 17 March 2026, with MEP, the external envelope and internal finishes described as progressing at advanced stages at 94.93%.

Current PhaseMar 2026 onward, 97.01% on 15 Jul 2026

Finishes, External Works and Handover

Envelope, MEP, internal finishes, external works and infrastructure were still progressing at 97.01% on 15 July 2026, ahead of the registered 30 December 2026 completion and a Q4 2026 handover.

What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Anya 2 at Arabian Ranches 3 's own record.

Buyer Position

Tracking Your Position at Anya 2 at Arabian Ranches 3

This page is one of four project resources that together cover a Anya 2 at Arabian Ranches 3 purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Anya 2 at Arabian Ranches 3 by Emaar Properties contemporary townhouse exterior at dusk featured for construction updates in Dubai - Presented by Tohid Fetrat
You Are Here

Anya 2 at Arabian Ranches 3 Construction Updates

This page: every dated Anya 2 RERA reading, from groundbreaking in June 2023 to handover.

Anya 2 at Arabian Ranches 3 by Emaar Properties contemporary townhouse community with Golden Visa eligibility concept in Dubai - Presented by Tohid Fetrat

Anya 2 at Arabian Ranches 3 Golden Visa: 362 Townhouses

Both townhouse tiers at Anya 2 at Arabian Ranches 3 qualify, so Emaar's 362-townhouse cluster needs no second property.

Read the Anya 2 at Arabian Ranches 3 Golden Visa Guide
Anya 2 at Arabian Ranches 3 by Emaar Properties contemporary townhouse community with escrow account security concept in Dubai - Presented by Tohid Fetrat

Anya 2 at Arabian Ranches 3 Escrow, Certified Past 97%

Anya 2 at Arabian Ranches 3 escrows 362 units with Mashreq as DLD project 2609, 97.01% certified in July 2026.

Verify the Anya 2 at Arabian Ranches 3 Escrow Account
Anya 2 at Arabian Ranches 3 by Emaar Properties Why an Independent Inspection Protects Anya 2 Buyers featuring a contemporary living and dining interior in Dubai - Presented by Tohid Fetrat

Anya 2 at Arabian Ranches 3 Snagging: Luna, Aria and Iris Townhouses

Anya 2 at Arabian Ranches 3 is a gated cluster of 362 attached Emaar townhouses, each with covered parking.

Book Anya 2 at Arabian Ranches 3 Snagging

Approaching Handover

Between 97.01% and Handover: What Anya 2 at Arabian Ranches 3 Buyers Should Do Now

The 2.99 points still open at Anya 2 on 15 July 2026 are finishes, services and the ground works between townhouses, work a buyer will not see from the street but will live with from the first day. Handover notices usually leave only a short window to act, and 168 days separated the July inspection from the registered 30 December 2026 completion date, so the three steps below belong in the weeks ahead, not in the week the notice lands.

First, arrange an independent inspection so defects in your townhouse, from the staircase to the boundary walls, are logged before you accept it; the Anya 2 snagging page sets out timing and the checklist for a G+1 home.

Second, if you bought on the 2023 launch schedule, check that your completion instalment is going to the project 2609 escrow account shown on the Anya 2 escrow account page, so the last payment follows the recorded build rather than a request.

Third, if residency is part of the plan, work through the Anya 2 Golden Visa guide before handover, so the eligibility question is settled before the title deed stage rather than after it.

Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.

The Wider Picture

Explore Arabian Ranches 3 Structure

A cluster's build record reads differently once you see the master community around it. These three pages set Anya 2's progress against Arabian Ranches 3, its sales market, and the developer behind it:

Arabian Ranches 3 townhouses and villas for sale overlooking landscaped parks, modern homes, recreational spaces, and tree lined streets in Dubai. Presented by Tohid Fetrat

Arabian Ranches 3 Properties for Sale

Browse townhouses and villas for sale in Arabian Ranches 3 - compare projects, prices and payment plans.

See Arabian Ranches 3 Properties for Sale
Aerial master plan view of Arabian Ranches 3 showcasing residential neighborhoods, landscaped parks, road network, and community amenities in Dubai. Presented by Tohid Fetrat

Arabian Ranches 3: Thirteen Villa and Townhouse Clusters Around a Central Park

Arabian Ranches 3 is a gated Emaar masterplan in Dubailand with 4,000 homes, sports facilities and direct access to Emirates Road.

Explore the Arabian Ranches 3 Community
Emaar Properties developer showcasing Downtown Dubai skyline with Burj Khalifa and surrounding residential and commercial towers at dusk Presented by Tohid Fetrat

Emaar Properties: Burj Khalifa, Downtown Dubai and Twenty Master Communities

Emaar, founded in 1997, built Burj Khalifa and Downtown Dubai and has delivered over 85,000 homes across twenty master communities.

View the Emaar Properties Developer Profile

Construction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.

FAQs

Anya 2 at Arabian Ranches 3 Construction Updates Frequently Asked Questions

Anya 2 at Arabian Ranches 3 is an active DLD-registered project, number 2609, recorded at 97.01% construction progress at the RERA inspection of 15 July 2026, when the inspection report gave its progress status as Main Contract - Progressing. Enabling, foundation, structure and internal works were listed as complete on that date. The full record is in the Anya 2 inspection timeline above.

The most recent RERA inspection of Anya 2, dated 15 July 2026, recorded 97.01% construction progress, up 2.08 points from the 94.93% reading of 17 March 2026. It listed the external envelope, MEP, internal finishes, external works and infrastructure as still progressing; the reading is covered in detail in the Anya 2 July 2026 construction update.

Between its two dated inspections, Anya 2 advanced from 94.93% on 17 March 2026 to 97.01% on 15 July 2026, about 0.52 points per 30-day month across 120 days. Reaching 100% by the registered 30 December 2026 date needs about 0.53 points per month from the July reading, within a hundredth of the recorded pace. The workings are in the Anya 2 pace analysis above.

The DLD-registered completion date for Anya 2, project 2609, is 30 December 2026, a date still ahead when this page was built, and handover is scheduled for Q4 2026, the same quarter. At the 15 July 2026 inspection the project stood at 97.01%, 168 days before that date; the handover itself is confirmed by Emaar as final works complete, and this page's record is updated when the closing inspection is recorded.

Anya 2 at Arabian Ranches 3 includes 362 townhouses, each a ground plus first floor (G+1) home with 3 or 4 bedrooms, and the DLD record for project 2609 carries a total built area of 72,269.27 sq m. The 362 figure matches across the DLD register and both 2026 inspection reports, dated 17 March and 15 July 2026.

The DLD inspection entry for Anya 2 dated 17 March 2026 shows 86.65% as the previous inspection reading but gives no date for it. A pace figure needs a date at both ends, so 86.65% appears on the track only as a labelled undated marker: it has no table row and is left out of every points-per-month figure, which start from the dated 94.93% reading of 17 March 2026.

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is keeping the Anya 2 at Arabian Ranches 3 construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.