Binghatti · Jumeirah Village Circle · Construction Update
Binghatti Ruby Construction Update - July 2026
July 2026 DLD Register Reading Places Binghatti Ruby at 46.43% Construction Progress in Jumeirah Village Circle
Superstructure, internal works, MEP, and internal finishes were progressing at Binghatti Ruby when RERA inspected on 23 July 2026, with the DLD register reading 46.43 percent.
Direct advisor access. Every message answered personally, never by a call center.
Verified DLD Inspection Data
Binghatti Ruby Construction Snapshot
A 26.39 point difference separates the previous register reading from the July 2026 one, moving Binghatti Ruby into the mid-construction band, the stage where the structure is still rising while building services and interiors begin inside it.
Binghatti Ruby by Binghatti
3533
Active
46.43%
23 July 2026
01 January 2025
572 residential units
38,308.25 sq m
Q4 2026
Data source: the Dubai Land Department project register reading for project 3533 dated 23 July 2026 and the RERA Independent Progress Monitoring Report of the same date (registered developer Binghatti Developers FZE; trust account bank The National Bank of Fujairah PSC). The hero image is a developer rendering of the finished design, not a site photograph. Construction tracking against RERA inspection data runs across the full tohidfetrat.com project portfolio and is reviewed after every published cycle. Last updated: October 2026.
Want each new reading the day it publishes? Message me on WhatsApp and I will send it to you directly: one message per inspection cycle, nothing else. Message me on WhatsApp
This Inspection Cycle
Binghatti Ruby Construction Progress Summary
At the 23 July 2026 inspection the register moved Binghatti Ruby from a previous reading of 20.04% to 46.43%; the earlier figure carries no date, so no monthly pace can be read from the pair. The RERA report of the same day places the work front above ground: everything from enabling works to the substructure is finished, and the tower itself is now the job.
- Enabling works across the site
- Piling and foundation works
- Substructure works below the ground floor
- Superstructure of the single mixed-use tower
- Internal works inside the building
- MEP systems: mechanical, electrical, and plumbing installation
- Internal finishes, recorded as progressing on 23 July 2026
- Completion of the superstructure carrying 18 residential floors above the podium and office levels
- Finishing and services across the 572 residences
- Remaining RERA inspection cycles toward 100% and the Q4 2026 handover target
Payment Linked Progress
What 46.43% Progress Means for Binghatti Ruby Buyers
The Binghatti Ruby plan takes 20% at booking, 50% across construction per the developer's schedule, and 30% on handover, so a 46.43% reading sits squarely inside the construction share of the plan: the stretch where each installment should be checked against the record. At this stage, four actions matter most.
Verify the escrow account
Every installment in the 50% construction share should go only to the DLD regulated escrow account registered for project 3533 with National Bank of Fujairah. Binghatti Ruby escrow account verification is the step before any transfer; the lookup itself takes about two minutes against the official DLD project record.
Reread your SPA milestone schedule
Check whether your sale and purchase agreement ties the construction share to dates or to milestones, and how it treats the passed registered completion date of 28 February 2026 against the Q4 2026 target. Not sure how your installments map to this reading? Send me your SPA schedule and I will map it against the recorded milestones.
Confirm your Oqood registration
Off plan units at Binghatti Ruby are registered with the Dubai Land Department through Oqood under project 3533. Confirm your apartment appears in your name before further construction installments leave your account.
Track the remaining cycles
With 53.57 points still to be recorded, several readings lie between July 2026 and handover. The Binghatti Ruby construction updates hub collects each one as it is posted.
General framework, not legal advice: milestone definitions, notice periods, and fee obligations are set by your individual SPA and the DLD record, and both should be read directly.
Buying at 46.43%?
Entering mid-construction trades part of the installment runway for a structure that is already out of the ground: the foundations and substructure are recorded as complete, and the open question is the pace of the tower above them. Every payment goes to the DLD-registered escrow account for project 3533, released against construction progress recorded in the DLD project register.
- Enabling, piling, foundation and substructure works recorded as completed on 23 July 2026
- A Q4 2026 handover target set by the developer
- 30% of the 20/50/30 plan due on handover, with the construction share scheduled by the developer
- Construction risk carried from an empty site onward
- The longest wait between booking and keys
- The full installment runway, priced at launch levels
Limited units available as of this update; availability shifts between cycles.
About the Development
Binghatti Ruby Project Details

With its substructure finished and the superstructure progressing at the July 2026 inspection, Binghatti Ruby is a mid-construction tower of 572 studio, 1, 2 and 3 bedroom apartments in Jumeirah Village Circle. Starting prices: AED 695K ≈ USD 189K.
For buyers entering at this stage, the trade off is less installment runway than at launch against construction risk already retired below ground, with the developer targeting handover in Q4 2026.
Binghatti Ruby by Binghatti Project GuideSite Context This Cycle
Explore Binghatti Ruby Location on Dubai Map
Binghatti Ruby stands on a plot of 4,687.10 sq m in Jumeirah Village Circle, per the developer fact sheet, and stacks ground-floor retail, four podium parking levels and two office floors beneath 18 residential floors. On a footprint this compact the tower grows upward over its podium, which is why the July 2026 report pairs a rising superstructure with MEP and finishing works already under way inside it.
Jumeirah Village Circle is an established district reached from Al Khail Road (E44), Sheikh Mohammed Bin Zayed Road (E311), and Hessa Street, so Binghatti Ruby is being built into a neighborhood that already functions; for buyers weighing the Q4 2026 target against rental or occupancy plans, the variable is the tower, not the district around it. See the project's position on the interactive Dubai real estate map. See the project’s position on the interactive Dubai real estate map.

Buyer Resources for This Project
Investing in Binghatti Ruby During Mid-Construction Progress
Mid-construction is where escrow discipline, residency thresholds, and the construction installment schedule meet. Each resource below is matched to where Binghatti Ruby stands at the July 2026 reading.

Binghatti Ruby Construction Updates
This page: the 23 July 2026 DLD register reading for Binghatti Ruby, with RERA inspection notes.

Binghatti Ruby Golden Visa: Only the 3 Bedroom Clears Alone
Binghatti Ruby, a mixed-use Jumeirah Village Circle tower of 572 units, qualifies only through its 3 bedroom apartment.
Read Binghatti Ruby Golden Visa Guide
Binghatti Ruby Escrow, Held by The National Bank of Fujairah
The National Bank of Fujairah holds Binghatti Ruby escrow, DLD project 3533, 628 units, 46.43% certified July 2026.
Verify Binghatti Ruby Escrow AccountUpdate Timeline
Other Binghatti Ruby Construction Updates
This July 2026 page opens the Binghatti Ruby inspection record on this site; later readings join the timeline as the Dubai Land Department posts them.
Where This Update Fits
Explore Binghatti Ruby Structure
This monthly report is one node in a wider record: the community around the plot, the developer building the tower, and the listings competing with it.

Jumeirah Village Circle: Five Imtiaz and Binghatti Towers in New Dubai
Jumeirah Village Circle, Nakheel's freehold ring of ten districts in New Dubai, lists apartments in five Imtiaz and Binghatti towers.
See JVC Properties for Sale
JVC Community Overview
Read the Jumeirah Village Circle guide: Nakheel's freehold community of apartments, townhouses and villas with strong rental yields.
Explore the JVC Community
Binghatti: Record Construction Speed and Branded Towers With Bugatti and Mercedes-Benz
Binghatti has delivered more than 60 projects since 2008, with 27 under development and two master communities across Dubai.
View the Binghatti Developer ProfileFAQs
Binghatti Ruby Construction Progress in July 2026: Frequently Asked Questions
Binghatti Ruby stood at 46.43% in the Dubai Land Department project register at the inspection dated 23 July 2026, up from a previous register reading of 20.04%. The RERA progress report of the same day prints no percentage of its own, so 46.43% is the register figure, and it is the latest reading on record for project 3533 as of this page.
Yes. The DLD record still carries a registered completion date of 28 February 2026, which had already passed when the 23 July 2026 reading was posted, while the developer's stated handover target is Q4 2026. Completion dates can be revised between inspection cycles, so the current date is confirmed with Binghatti and on Dubai REST under project 3533 rather than read from either figure alone.
The inspection report card for 23 July 2026 lists 20.04% as Previous Inspection and 46.43% as Current Progress, but the register shows no date beside the earlier figure. Without that date the gap between the two readings cannot be turned into a monthly pace, which is why this page states the two readings side by side and nothing more.
The RERA Independent Progress Monitoring Report of 23 July 2026 records the enabling, piling, foundation and substructure works as completed, with the superstructure, internal works, MEP and internal finishes progressing. Its progress status reads Main Contract, Progressing, and the report carries inspection photographs, which remain part of the official record.
The DLD record lists construction start as 01 January 2025 and project registration as 07 April 2025, so the start precedes the registration; both dates are printed here exactly as recorded, and the record gives no reason for the order. The 46.43% reading of 23 July 2026 was taken 568 days after the recorded start.
No. The hero image is a developer rendering of the finished design, used to illustrate this dated update, and no construction status should be read from it. The state of the tower at 23 July 2026 is described by the register reading and the RERA inspection notes on this page.
A Question the FAQ Can Not Answer?

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is helping you read the July 2026 inspection record for Binghatti Ruby correctly before your next payment decision. Client identities and transactions are never published or referenced. Message me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.