HQ by Rove by IRTH Group in Marasi Bay / Business Bay project rendering used for the July 2026 construction update showing the planned tower beside the waterfront with the Dubai skyline in Dubai - Presented by Tohid Fetrat

IRTH Group · Marasi Bay · Construction Update

HQ by Rove Construction Update - July 2026

July 2026 Inspection Finds HQ by Rove in Enabling Works, With 0.7% Recorded in the DLD Project Register

Excavation and piling dominate the Marasi Bay plot, with the 6 July 2026 RERA inspection recording enabling works in progress and the DLD register showing 0.7 percent.

Direct advisor access. Every message answered personally, never by a call center.

0.7%DLD Recorded Progress
6 July 2026Inspection Date
Q1 2029Anticipated Handover
4143DLD Project Number

Verified DLD Inspection Data

HQ by Rove Construction Snapshot

A move from 0.06% to 0.7% in the DLD project register keeps HQ by Rove in the earliest construction band, the stage where registration, escrow, and the shape of a payment plan with years left to run are what a buyer actually decides.

Project Name

HQ by Rove

Project Number

4143

Project Status

Active

Construction Progress

0.7%

Inspection Date

6 July 2026

Construction Start

15 December 2025

Total Units

414 offices

Total Built Area

47,131.26 sq m

Expected Completion

31 March 2029

Data source: the RERA independent progress monitoring report for inspection date 6 July 2026, read together with the DLD project register entry for project 4143. The monitoring report states a progress status, Enabling Works - Progressing, and prints no percentage; the 0.7% figure is the register reading for that same inspection. Construction tracking against RERA inspection data runs across the full tohidfetrat.com project portfolio and is reviewed after every published cycle. Last updated: September 2026.

Want each new reading the day it publishes? Message me on WhatsApp and I will send it to you directly: one message per inspection cycle, nothing else. Message me on WhatsApp

This Inspection Cycle

HQ by Rove Construction Progress Summary

The register moved from 0.06% at the previous reading to 0.7% on 6 July 2026, a gain of 0.64 of a point, and the inspector's own note explains the size of it: enabling works were still progressing on plot 107. That is the stage that opens the ground for five basement levels rather than the stage that adds visible height, so the July number measures preparation, not structure.

Completed
  • Project registration recorded 22 October 2025 in the DLD register
  • Escrow trust account opened with Commercial Bank of Dubai (PSC)
  • Construction start recorded 15 December 2025
In Progress at 0.7%
  • Enabling works progressing across plot 107 per the 6 July 2026 inspection note
  • Excavation and piling equipment working the site in the inspection photographs
  • Ground preparation for the five basement levels in the registered description
Ahead of Handover
  • Basement, podium and 26 floor superstructure of the 5B+G+3P+26+MEP+R scheme
  • Successive RERA inspection cycles toward 100% in the register
  • Completion recorded as 31 March 2029, inside the anticipated Q1 2029 handover
Next inspectionPublished in the DLD project register after the next RERA site visit; this page updates with each cycle.
Completion target31 March 2029 in the register as of 6 July 2026, inside the Q1 2029 handover the developer anticipates.
Remaining distance99.3 percentage points separate the July 2026 reading from a completed building.

Payment Linked Progress

What 0.7% Progress Means for HQ by Rove Buyers

Dubai off plan plans tie instalments either to dated calendar points or to verified construction milestones, so a register reading of 0.7% places a buyer at the very start of that schedule, with the early stage protections still fully in play. Four actions carry the most weight at this point in the build.

Before Any Instalment

Verify the escrow account

Every payment ahead of handover belongs in the DLD regulated escrow account registered for project 4143, held with Commercial Bank of Dubai (PSC) per the July 2026 monitoring report. HQ by Rove escrow account verification is the step before any transfer; the lookup itself takes about two minutes against the official DLD project record.

Before the Next Due Date

Map your SPA instalment schedule

At 0.7% recorded, your sale and purchase agreement rather than the site decides what falls due next, since some instalments sit on fixed dates and others release against verified construction milestones.

After Reservation

Confirm the Oqood registration

An off plan purchase is recorded on the interim property register, and that entry is what ties your office to project 4143 years before a title deed exists. Ask for the registration confirmation and check that the unit number, floor and area on it match your agreement exactly.

Every Cycle

Track the early readings

A project at 0.7% has years of inspection cycles ahead of it, and the earliest ones move in fractions of a point while the work is below ground. HQ by Rove construction updates hub keeps the whole sequence in one place.

General framework, not legal advice: milestone definitions, notice periods, and fee obligations are set by your individual SPA and the DLD record, and both should be read directly.

Buying at 0.7%?

Entering during enabling works buys the longest payment runway the developer plan offers and the launch price structure that comes with it, in exchange for carrying the build from excavation through to handover. Every payment goes to the escrow account registered to project 4143, and each release is tied to the construction progress the DLD inspection record tracks.

Entering Now at 0.7%
  • Register recorded stage: enabling works, inspected 6 July 2026
  • 50% of the price falls due only at completion, anticipated Q1 2029
  • Launch structure intact, studio offices from AED 3.03M ≈ USD 826K
Entering Near Completion
  • Most of the purchase price due within months of handover
  • Construction risk largely resolved and already priced in
  • Choice narrowed to whatever inventory is still unsold late
AED 3.03M ≈ USD 826KStarting Price
15 / 35 / 50 Plan50% Due on Completion
From Q1 2029Anticipated Handover
Ask What Is Available at HQ by Rove

20 units listed available on the project page as of this update; availability shifts between cycles.

About the Development

HQ by Rove Project Details

HQ by Rove in Business Bay Dubai branded commercial tower with panoramic views of Burj Khalifa and Downtown skyline premium offices by IRTH Developer presented by Tohid Fetrat
Marasi Bay, Business Bay · IRTH Group

At 0.7% recorded progress, HQ by Rove is still a groundworks site: the 414 modular offices, 23 office floors and Rove Hotels branded amenity levels exist as a registered scheme rather than a structure. Studio offices start at AED 3.03M ≈ USD 826K.

For a buyer the trade off at this stage is the longest wait against the fullest payment runway, with handover anticipated in Q1 2029 and completion recorded as 31 March 2029 in the DLD register.

HQ by Rove by IRTH Group Project Guide

Site Context This Cycle

Explore HQ by Rove Location on Dubai Map

HQ by Rove occupies plot 107 in Marasi Bay, the canal front pocket of Business Bay held between the Dubai Water Canal and the Al Khail Road corridor, and that position governs the current cycle directly: a 5B+G+3P+26+MEP+R scheme needs five levels of basement, so excavation and piling on a constrained urban plot are exactly the works the 6 July 2026 inspection found in progress.

Because the district around it is already built and in service, with the promenade, the road network and utilities all working, HQ by Rove is digging into a functioning neighbourhood rather than an empty one, which is the practical difference for a buyer weighing a Q1 2029 handover against office space that could be leased in Business Bay today. See the project’s position on the interactive Dubai real estate map.

Interactive Dubai real estate map preview
Click to view HQ by Rove on Dubai Map

Buyer Resources for This Project

Investing in HQ by Rove During Early Construction

The enabling works band is where registration, payment protection, and residency planning are settled, long before anything is visible above ground. Each resource below is matched to where HQ by Rove stands right now.

HQ by Rove by IRTH Group in Marasi Bay / Business Bay construction updates cover image featuring a project rendering of the tower with HQ signage and the Burj Khalifa skyline in Dubai - Presented by Tohid Fetrat
You Are Here

HQ by Rove Construction Updates

This page: the verified July 2026 inspection record for HQ by Rove, from enabling works onward.

HQ by Rove by IRTH Group in Marasi Bay / Business Bay Golden Visa concept with a gold visa card above a curved waterfront balcony and Dubai skyline view in Dubai - Presented by Tohid Fetrat

HQ by Rove Golden Visa: Backed by an Office You Own

HQ by Rove, IRTH's 414-office building in Marasi Bay, opens every released tier, studio office to penthouse loft, above AED 2M.

Read HQ by Rove Golden Visa Guide
HQ by Rove by IRTH Group in Marasi Bay / Business Bay escrow account protection concept with shield and padlock icons above the branded building exterior in Dubai - Presented by Tohid Fetrat

HQ by Rove Escrow: IRTH's Marasi Bay Account

IRTH's HQ by Rove is DLD project 4143, 414 units escrowed at Commercial Bank of Dubai, 0.7% certified July 2026.

Verify HQ by Rove Escrow Account

Update Timeline

Other HQ by Rove Construction Updates

July 2026 is the first inspection reading published for HQ by Rove on this site, so the timeline below starts here and every later cycle joins it on the hub.

All HQ by Rove Construction Updates

FAQs

HQ by Rove Construction Progress in July 2026: Frequently Asked Questions

The DLD project register records 0.7% progress for project 4143 at the inspection dated 6 July 2026. The RERA independent progress monitoring report for that same inspection publishes a progress status, Enabling Works - Progressing, and carries no percentage of its own, so the 0.7% reading is a register figure rather than a certified completion percentage.

The register shows 0.06% at the previous inspection and 0.7% at the 6 July 2026 inspection, a gain of 0.64 of a percentage point. The register view does not publish the date of that earlier reading. The sequence of readings as they are released is collected on the HQ by Rove construction updates hub.

The DLD project register lists completion on 31 March 2029, which falls inside the Q1 2029 handover the developer anticipates. Expected completion dates in the register can be revised between inspection cycles, so the date here reflects the record as it stood at the 6 July 2026 inspection, and any revision would appear in a later update on this cluster.

The inspection note for 6 July 2026 records that enabling works were progressing at the site, and the photographs in the monitoring report show excavation and piling equipment working across plot 107. The registered project description, 5B+G+3P+26+MEP+R, places five basement levels below ground, which is the work this stage prepares for.

The July 2026 monitoring report identifies project number 4143, developer number 2267 for IRTH Urban Development L.L.C, plot 107 in Business Bay, and the escrow trust account held with Commercial Bank of Dubai (PSC). Those four identifiers are what a sale and purchase agreement and any escrow transfer instruction should agree with.

No. The 6 July 2026 record shows enabling works in progress, the groundwork stage that precedes basement and superstructure construction. The 26 floors, three podium levels and five basements named in the registered description are the permitted scheme rather than built floors, and the register carried 0.7% at that inspection.

A Question the FAQ Can Not Answer?

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is helping you read the July 2026 inspection record for HQ by Rove correctly before your next payment decision. Client identities and transactions are never published or referenced. Message me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

Get Progress Alerts