HQ by Rove by IRTH Group in Marasi Bay / Business Bay construction updates cover image featuring a project rendering of the tower with HQ signage and the Burj Khalifa skyline in Dubai - Presented by Tohid Fetrat

IRTH Group · Marasi Bay, Business Bay

HQ by Rove Construction Updates

Tracking Plot 107 in Marasi Bay From Enabling Works to Handover

HQ by Rove stands at 0.7% in the DLD register at its 6 July 2026 inspection, the first reading that puts Marasi Bay enabling works on record.

Construction tracking against RERA inspection data, updated after every recorded inspection.

Direct advisor access. Every message answered personally, never by a call center.

0.7%Construction Progress
6 July 2026Latest RERA Inspection
414 office unitsTotal Units
Project 4143DLD Registration

Construction Snapshot

HQ by Rove at a Glance

HQ by Rove is IRTH Urban Development's 414-office tower on plot 107 in Marasi Bay, the canal-front pocket of Business Bay. The register pairs 47,131.26 sq m of built-up area with a 76,038 sq ft plot, and that ratio explains the shape of the record so far: a building with five basement levels and 26 floors above them spends its first months going downward, which is why the opening reading is measured in fractions of a point rather than points. The cards below are the DLD-registered anchors behind that record.

DLD Project Number

4143

Project Status

Active

Construction Start

15 December 2025

Total Units

414 office units

Total Built-Up Area

47,131.26 sq m

Registered Completion Date

31 March 2029 (DLD)

Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.

Inspection Record

HQ by Rove Construction Update Timeline

One dated reading carries this record so far: 0.7% for project 4143 at the inspection of 6 July 2026, against 0.06% at the inspection before it, a gain of 0.64 of a point that the register publishes without a date for the earlier visit. The track below therefore shows a single dot, and the registered completion date of 31 March 2029 falls inside the Q1 2029 handover IRTH Urban Development anticipates, so the two records agree rather than compete. Each table row links the full monthly update for its cycle.

Inspection MonthConstruction ProgressInspection DateFull Update
July 20260.7%6 July 2026View the July 2026 update

Pace Analysis

How Fast HQ by Rove Has Been Built

With one dated reading on the register, pace at HQ by Rove is read against the project's own registered dates rather than between inspections. Two calculations carry the weight:

  • 15 December 2025 start to the 6 July 2026 inspection: enabling works, 0.7% recordedAbout 0.1 points per month
  • 6 July 2026 to the registered completion of 31 March 2029: 99.3 points still to recordAbout 3.0 points per month required

The distance between those two numbers is the whole story of an early-stage record. Six and a half months of excavation and piling moved the register by less than a single point, which is arithmetic rather than a warning: groundworks for five basement levels consume calendar time without earning percentage, and the 0.06% standing before this reading shows how little the register credits that stage. The 3.0 points per month implied by the 31 March 2029 date is the figure worth watching, because it only becomes reachable once the substructure is closed out and floor plates start repeating. For a buyer or an investor that sets a simple test for the next two or three cycles: readings still under five points a year from now mean the schedule is absorbing the difference, while a climb into double figures means the 26 floor superstructure has begun.

Get the Next Inspection Figure First

Tell me you are tracking HQ by Rove and I will send you the next recorded figure and site photos directly, ahead of the page update.

Get the Next Update on WhatsApp

Project Profile

About HQ by Rove at Marasi Bay

A register reading only means something against what is being delivered. The project guide covers the building behind the 0.7%:

HQ by Rove in Business Bay Dubai branded commercial tower with panoramic views of Burj Khalifa and Downtown skyline premium offices by IRTH Developer presented by Tohid Fetrat

HQ by Rove: Hospitality-Branded Offices on Marasi Bay

HQ by Rove stacks 414 modular and loft offices over 23 floors on Marasi Bay, developed by IRTH with Rove Hotels.

View the HQ by Rove Project Guide

Considering an Early-Stage Entry?

Availability at HQ by Rove shifts between inspection cycles, and the payment structure a buyer gets is tied to the stage the register is recording now. If the 0.7% record is what brought you here, ask me what is still open before the next cycle changes it.

Ask About Remaining Availability on WhatsApp

Stage Record

HQ by Rove Build Stages, Mapped to the Inspections

Five stages carry plot 107 from a register entry to a finished building, and the windows below are this project's own: registration on 22 October 2025, the start recorded on 15 December 2025, and a completion date on file for 31 March 2029. Two of the five are already on the record.

Oct 2025 to Dec 2025

Registration and Escrow Setup

Project 4143 was entered on the DLD register on 22 October 2025, with the trust account held at Commercial Bank of Dubai (PSC): the records that had to exist before work started on plot 107.

Current PhaseDec 2025 onward, 0.7% at last reading

Enabling Works on Plot 107

Construction was recorded as started on 15 December 2025, and the 6 July 2026 inspection found enabling works progressing: the excavation and piling that carried the register from 0.06% to 0.7%.

Next in the record

Basement and Substructure

The five basement levels of the 5B+G+3P+26+MEP+R scheme are what the current excavation prepares, and they are the works the next inspection cycles should begin to credit.

Toward the 26 floor scheme

Podium and Tower Structure

Three podium levels and 26 floors, 23 of them office floors carrying up to 22 modular units each, are the stage where a register reading moves in points rather than fractions.

Toward 31 March 2029

MEP, Fit-Out, and Handover

Mechanical levels and roof close the registered description, followed by fit-out of the Rove Hotels branded floors and the handover IRTH Urban Development anticipates in Q1 2029, recorded as 31 March 2029.

What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on HQ by Rove's own record.

Buyer Position

Tracking Your Position at HQ by Rove

This page is one of four project resources that together cover a HQ by Rove purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

HQ by Rove by IRTH Group in Marasi Bay / Business Bay construction updates cover image featuring a project rendering of the tower with HQ signage and the Burj Khalifa skyline in Dubai - Presented by Tohid Fetrat
You Are Here

HQ by Rove Construction Updates

This page: every DLD inspection reading for HQ by Rove, from 0.7% to handover.

HQ by Rove by IRTH Group in Marasi Bay / Business Bay Golden Visa concept with a gold visa card above a curved waterfront balcony and Dubai skyline view in Dubai - Presented by Tohid Fetrat

HQ by Rove Golden Visa: Backed by an Office You Own

HQ by Rove, IRTH's 414-office building in Marasi Bay, opens every released tier, studio office to penthouse loft, above AED 2M.

Read the HQ by Rove Golden Visa Guide
HQ by Rove by IRTH Group in Marasi Bay / Business Bay escrow account protection concept with shield and padlock icons above the branded building exterior in Dubai - Presented by Tohid Fetrat

HQ by Rove Escrow: IRTH's Marasi Bay Account

IRTH's HQ by Rove is DLD project 4143, 414 units escrowed at Commercial Bank of Dubai, 0.7% certified July 2026.

Verify the HQ by Rove Escrow Account

Approaching Handover

Between 0.7% and Handover: What HQ by Rove Buyers Should Do Now

The distance between a register reading of 0.7% and a structure anyone can see is measured in inspection cycles, so everything a buyer controls at this stage is administrative rather than physical. The early cycles are also the window where paperwork is cheapest to correct: an escrow instruction or an interim-register entry fixed now costs a message, and the same correction after two years of instalments costs a great deal more.

First, match your instalment schedule to the escrow arrangement before the next due date; the HQ by Rove escrow account page sets out how releases follow recorded progress rather than requests.

Second, if the purchase is meant to carry residency, settle eligibility early through the HQ by Rove Golden Visa guide, because the route depends on a title deed that only exists after completion in 2029.

Third, read each cycle as it publishes: the July 2026 inspection record is the opening entry, and the readings that follow are what tell you whether the 31 March 2029 date is holding.

Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.

The Wider Picture

Explore Marasi Bay Structure

An early reading is easier to judge next to the district it is being dug into, the stock already leasing there, and the company holding the plot. These three pages carry that context:

Marasi Bay waterfront properties for sale with luxury marina skyline views in Dubai Presented by Tohid Fetrat

Marasi Bay Properties for Sale

Browse branded residences, waterfront apartments and penthouses for sale by OMNIYAT at Marasi Bay.

See Marasi Bay Properties for Sale
Marasi Bay in Business Bay Dubai showing waterfront canal view modern residential towers marina and urban lifestyle along Dubai Water Canal Presented by Tohid Fetrat

Marasi Bay Community Overview

Read the Marasi Bay guide: OMNIYAT's ultra-luxury canal-front district of branded residences, offices and hospitality.

Explore the Marasi Bay Community
Irth Group developer Dubai showcasing modern mixed use architecture, illuminated buildings, urban skyline, and premium real estate environment in Dubai Presented by Tohid Fetrat

IRTH: Emirati Heritage and Architectural Artistry, From Al Wasl to Dubai Islands

IRTH blends Emirati roots with modern design across 5 prime districts of Dubai, including Jumeirah, Al Wasl and Dubai Islands.

View the IRTH Developer Profile

Construction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.

FAQs

HQ by Rove Construction Updates Frequently Asked Questions

HQ by Rove is an active DLD-registered project, number 4143, in its enabling works stage, recorded at 0.7% in the DLD project register at the inspection of 6 July 2026. The independent progress monitoring report for the same inspection carries no percentage at all; its only progress field reads Enabling Works - Progressing. The full record is in the inspection timeline above.

The register moved to 0.7% at the 6 July 2026 inspection from 0.06% at the reading before it, a gain of 0.64 of a percentage point, though that earlier figure is shown without a date of its own and so cannot be placed on the timeline. The full detail for the cycle, including the inspection note and the identifiers on the monitoring report, is in the July 2026 construction update.

From the 15 December 2025 construction start to the 6 July 2026 inspection, roughly six and a half months, the register moved 0.7 of a point, about 0.1 points per month, which is the ordinary arithmetic of enabling works. Reaching 100% by the registered completion date of 31 March 2029 means covering the remaining 99.3 points in about 32.8 months, close to 3.0 points per month. Both calculations are set out in the pace analysis above.

The DLD register records completion on 31 March 2029 for project 4143, a date that falls inside the Q1 2029 handover IRTH Urban Development anticipates, so the register and the developer guidance agree rather than conflict. Registered dates can be revised between inspection cycles, and this page's record is updated when each new reading is published.

DLD registration records show 414 units and a total built-up area of 47,131.26 sq m for project 4143. The developer factsheet places those units across 23 office floors, up to 22 modular units per floor, inside the 5B+G+3P+26+MEP+R scheme the register describes.

The project was entered on the DLD register on 22 October 2025 and construction was recorded as started on 15 December 2025. The first dated reading in the register is 0.7% at the 6 July 2026 inspection, which makes that inspection the opening entry in this record.

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is keeping the HQ by Rove construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

WhatsApp +971543443597
Get the Latest Status