Palmiera at The Oasis Construction Update - October 2024

First Reading Above Zero Puts Palmiera at The Oasis at 6.45% Construction Progress in October 2024

Enabling, foundation and substructure works led activity at Palmiera at The Oasis as the 15 October 2024 RERA inspection logged its first measurable progress: 6.45 percent.

Direct advisor access. Every message answered personally, never by a call center.

6.45%Construction Progress
15 October 2024Inspection Date
Q4 2027Expected Completion
2732DLD Project Number

Verified DLD Inspection Data

Palmiera at The Oasis Construction Snapshot

6.45% at the first reading above zero places Palmiera at The Oasis in the enabling and foundations band, the stage where escrow checks and the shape of the payment plan matter more than anything visible on the plots.

Project Name

Palmiera at The Oasis by Emaar

Project Number

2732

Project Status

Active

Construction Progress

6.45%

Inspection Date

15 October 2024

Construction Start

14 August 2023

Total Units

265 villas

Total Built Area

218,534.38 sq m

Expected Completion

Q4 2027

Data source: RERA inspection conducted on 15 October 2024, tracked against DLD inspection records for project 2732; total built area and unit count as shown in the DLD register, expected completion as stated at this update. Construction tracking against RERA inspection data runs across the full tohidfetrat.com project portfolio and is reviewed after every published cycle. Last updated: September 2026.

Want each new reading the day it publishes? Message me on WhatsApp and I will send it to you directly: one message per inspection cycle, nothing else. Message me on WhatsApp

This Inspection Cycle

Palmiera at The Oasis Construction Progress Summary

The 15 October 2024 inspection moved Palmiera at The Oasis off zero for the first time, recording 6.45% across a cluster of 265 villas where enabling, foundation, substructure and early superstructure works were running side by side. At this point the record describes groundwork and infrastructure rather than finished villa shells.

Completed
  • DLD project registration on 28 July 2023
  • Construction start recorded on 14 August 2023
  • Main contract stage reached, status Main Contract, Progressing
In Progress at 6.45%
  • Enabling works across the villa plots
  • Foundation and substructure works at different stages
  • Early superstructure works on the first villas
  • Infrastructure works across the cluster
Ahead of Handover
  • Concrete structure and blockwork for all 216 four bedroom and 49 five bedroom villas
  • Internal and external finishes per the register description
  • Handover expected in Q4 2027
Next reading on this clusterThe 1 October 2025 inspection, covered in the October 2025 update; register readings between the two were not captured with dates.
Completion targetQ4 2027 as stated at this update, roughly three years after the 15 October 2024 inspection.
Remaining distance93.55 percentage points separated the October 2024 reading from full completion.

Payment Linked Progress

What 6.45% Progress Means for Palmiera Buyers

The 2023 launch schedule of record front-loads payment: 35% of the price fell due by October 2024, before any instalment was paired with a construction milestone. At 6.45%, the questions are where that money sits and when the milestone-linked instalments begin. Four actions mattered most at this stage of Palmiera.

Before Each Early Instalment

Verify the escrow account

With 65% of the launch price still scheduled between 2025 and 2027, every instalment should go only to the DLD regulated escrow account registered for project 2732. Palmiera at The Oasis escrow account verification comes before any transfer; the lookup takes about two minutes against the official DLD project record.

Before the July 2025 Milestone

Confirm Oqood and your SPA schedule

Confirm your Oqood registration is issued, then check whether your sale and purchase agreement ties later instalments to dates, to construction milestones, or both; the launch schedule pairs July 2025 with 10% completion. Not sure how your instalments map to this reading? Send me your SPA schedule and I will map it against the certified milestones.

Later: Near the Q4 2027 Handover

Note the villa snagging scope

At 6.45%, the pre handover inspection is roughly three years out, but a villa of this size carries a wide scope: roof terrace, private lift, facade, glazing and garden. Palmiera at The Oasis snagging inspection guide sets out when to book it.

Every Cycle

Follow the readings to handover

93.55 points of progress remained after this reading, spread across superstructure, envelope, MEP and finishing works. Palmiera at The Oasis construction updates hub records every reading that followed.

General framework, not legal advice: milestone definitions, notice periods, and fee obligations are set by your individual SPA and the DLD record, and both should be read directly.

Buying at 6.45%?

An October 2024 entry sat at the very start of the build: groundwork was under way, no villa was near completion, and most of the payment plan still lay ahead of certified progress. Every payment goes to the DLD-registered escrow account for project 2732, released against certified construction progress.

Entering at 6.45% in October 2024
  • 6.45% certified on 15 October 2024, the first reading above zero
  • Roughly three years to the Q4 2027 handover
  • 35% paid by the October 2024 instalment on the launch schedule, 15% held for completion
Entering Later in the Build
  • More of the structure already certified before you commit
  • A shorter wait between contract and keys
  • A shorter instalment runway, usually at later pricing
AED 11.49M ≈ USD 3.13MStarting Price, 4 Bedroom Villa
85/15 Launch Plan15% on Construction Completion
Q4 2027Expected Handover
Ask What Is Available at Palmiera

2 Units Available, per the project page as of September 2026, with prices as of the same date; availability shifts between cycles, and Emaar confirms the payment schedule for a remaining or resale villa at booking.

About the Development

Palmiera at The Oasis Project Details

Palmiera at The Oasis by Emaar modern villa with pool terrace and landscaped garden in Dubai. Presented by Tohid Fetrat.
The Oasis · Emaar Properties

At the October 2024 reading, Palmiera was a groundwork-stage build of 265 stand-alone villas in Classical, Contemporary and Chamfered styles, 216 with four bedrooms and 49 with five. Starting price as of September 2026: AED 11.49M ≈ USD 3.13M.

Buyers who entered at this stage traded the longest wait to the Q4 2027 handover for the fullest instalment runway, with every construction risk still ahead of them rather than behind.

Palmiera at The Oasis by Emaar Project Guide

Site Context This Cycle

Explore Palmiera at The Oasis Location on Dubai Map

Palmiera at The Oasis is laid out as a low-rise villa cluster, with a swimmable lagoon and an urban canal set among the homes in the cluster plan and villa exteriors designed to face the water and public spaces. That spread is why the October 2024 works ran across many plots at once, with enabling, foundation and infrastructure packages advancing at different stages rather than one structure rising in a single spot.

The Oasis, listed in the register under Me'Aisem Second and reached via the D54 and E44 corridors, sits about 18 minutes from Al Maktoum International Airport and 35 minutes from Downtown Dubai, but its lagoons, schools, retail and community center were master plan elements rather than an established district, so October 2024 buyers were weighing a Q4 2027 handover into a community still taking shape. See where the cluster sits on the interactive Dubai real estate map. See the project’s position on the interactive Dubai real estate map.

Interactive Dubai real estate map preview
Click to view Palmiera at The Oasis by Emaar on Dubai Map

Buyer Resources for This Project

Investing in Palmiera at The Oasis During Early Construction Progress

At the foundations stage, the priorities are payment protection, residency planning and a clear view of a handover still three years out. Each resource below matches where Palmiera stood in October 2024.

Palmiera at The Oasis Construction Updates aerial view overlooking waterfront villas, crystal lagoon, landscaped pathways and luxury residential community in Dubai. Presented by Tohid Fetrat
You Are Here

Palmiera at The Oasis Construction Updates

This page: the 15 October 2024 inspection record for Palmiera at The Oasis at 6.45 percent.

Palmiera at The Oasis Golden Visa illustration featuring a luxury villa and residency card symbol representing property investment eligibility in Dubai. Presented by Tohid Fetrat

Palmiera at The Oasis Golden Visa: Two Villa Types Far Above

Palmiera at The Oasis, Emaar Properties' 265-villa cluster, qualifies at both its 4 and 5 bedroom villa types with no combining.

Read Palmiera at The Oasis Golden Visa Guide
Palmiera at The Oasis escrow account illustration featuring a luxury villa with security shield and lock symbols representing protected property investment in Dubai. Presented by Tohid Fetrat

Palmiera at The Oasis Escrow: The First Palmiera Account at Emirates NBD

Palmiera at The Oasis puts 265 units' payments into Emirates NBD escrow, DLD project 2732, 81.72% certified in July 2026.

Verify Palmiera at The Oasis Escrow Account
Palmiera at The Oasis Snagging Inspection featuring a contemporary luxury villa with modern architecture and landscaped surroundings. Presented by Tohid Fetrat

Palmiera at The Oasis Snagging for Stand-Alone Villas

Palmiera at The Oasis is a cluster of 265 stand-alone Emaar villas, 216 with four bedrooms and 49 with five.

Read Palmiera at The Oasis Snagging Guide

Update Timeline

Other Palmiera at The Oasis Construction Updates

October 2024 is the earliest reading on this cluster; the updates that follow trace Palmiera from groundwork through structure toward finishing, one dated reading at a time.

All Palmiera at The Oasis Construction Updates

FAQs

Palmiera at The Oasis Construction Progress in October 2024: Frequently Asked Questions

The RERA inspection of 15 October 2024 recorded Palmiera at The Oasis at 6.45% construction progress in the DLD register for project 2732, up from a previous inspection logged at 0%. That made it the first reading above zero for the 265 villa project.

Yes. Handover was expected in Q4 2027 at the time of this reading, and the 2023 launch schedule of record places its final instalment in December 2027, on construction completion. With 93.55 percentage points still ahead on 15 October 2024, that timing could still move, and the readings that followed are collected on the Palmiera at The Oasis construction updates hub.

The Independent Progress Monitoring Report for 15 October 2024 found enabling, foundation, substructure and superstructure works progressing at different stages, with infrastructure works also progressing at different stages, under the status Main Contract, Progressing. The register describes the villas as a concrete structure with block walls and internal and external finishes, so the finishing packages still lay ahead.

Palmiera is built as 265 separate villas, 216 with four bedrooms and 49 with five, laid out across a cluster plan rather than stacked in one tower, so works can advance plot by plot. In October 2024 that meant some plots were still in enabling and foundation works while others had moved into substructure and early superstructure.

The 2023 launch schedule of record set a 5% third instalment for October 2024, which took the cumulative share to 35% of the price including the 10% down payment. The next instalment on that schedule, 5% in July 2025, is the first one paired with a construction milestone (10% completion). Individual SPAs and resale contracts can differ, so the dates in your own agreement govern.

Construction started on 14 August 2023, a little over two weeks after DLD registration on 28 July 2023, and the 6.45% reading came on 15 October 2024: 428 days, or about 14 months, later. That works out to under half a point a month, a derived average from the two dates rather than a register figure, and consistent with a build still in its groundwork phase.

A Question the FAQ Can Not Answer?

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is helping you read the October 2024 inspection record for Palmiera at The Oasis correctly before your next payment decision. Client identities and transactions are never published or referenced. Message me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.