Passo by Beyond by Beyond Developments in Palm Jumeirah project rendering used for the March 2026 construction update showing the planned waterfront residential buildings at sunset in Dubai - Presented by Tohid Fetrat

Beyond Developments · Palm Jumeirah · Construction Update

Passo by Beyond Construction Update - March 2026

March 2026 RERA Inspection Records Passo by Beyond at 0% Construction Progress on the Palm Jumeirah Crescent

The 24 March 2026 inspection found no construction activities started on the Palm Crescent plot, and the certified record for Passo by Beyond opens at 0 percent.

Direct advisor access. Every message answered personally, never by a call center.

0%Construction Progress
24 March 2026Inspection Date
Q3 2029Expected Handover
3886DLD Project Number

Verified DLD Inspection Data

Passo by Beyond Construction Snapshot

A first certified reading of 0% on 24 March 2026 places Passo by Beyond at the pre-construction end of the DLD record, the stage where registration, escrow, and the payment schedule carry the weight that site data will carry later.

Project Name

Passo by Beyond

Project Number

3886

Project Status

Active

Construction Progress

0%

Inspection Date

24 March 2026

Construction Start

31 December 2025

Total Units

≈ 625 residences

Total Built Area

94,976.37 sq m

Expected Completion

Q3 2029

Data source: RERA Independent Progress Monitoring Report conducted on 24 March 2026, tracked against DLD inspection records. Construction tracking against RERA inspection data runs across the full tohidfetrat.com project portfolio and is reviewed after every published cycle. Last updated: September 2026.

Want the next certified reading the day it publishes? Message me on WhatsApp and I will send it to you directly: one message when a new inspection report is filed, nothing else. Message me on WhatsApp

This Inspection Cycle

Passo by Beyond Construction Progress Summary

This is the first Independent Progress Monitoring Report on the register for project 3886, so the March 2026 record sets a baseline rather than a trend: the Progress Status field is returned as N/A, the previous and current readings both stand at 0%, and the inspector recorded that no construction activities had been started on plot 2026.

Completed
  • Project registered with the DLD on 28 July 2025 as project 3886
  • DLD regulated escrow account opened for the project at Mashreq Bank PSC
  • Build scope filed with RERA: two G+14 residential buildings, six G+2 beach mansions, two shared basement parking levels
In Progress at 0%
  • Certified construction progress recorded at 0% on 24 March 2026
  • No construction activities recorded on the Palm Crescent plot at that inspection
  • Payment schedule running on fixed dates rather than on milestones
Ahead of Handover
  • The first certified reading above 0% in a future RERA report
  • The full build programme filed for the two buildings and six mansions
  • Completion certification and handover expected in Q3 2029
Next inspectionRERA files the next Independent Progress Monitoring Report when it inspects again; no date for it is published in advance, and this page records each reading as it reaches the register.
Registered completionThe DLD project register carries a registered completion date of 31 December 2029 for project 3886; the handover stated for the project is Q3 2029.
Remaining distanceThe full 100 percentage points separate the 24 March 2026 reading from handover readiness.

Payment Linked Progress

What 0% Progress Means for Passo by Beyond Buyers

Dubai off plan payment plans tie installments either to construction milestones or to fixed dates, and the Passo by Beyond schedule runs on dates, so a certified reading of 0% does not pause anything. At this point in the schedule, four actions matter most.

Before Every Installment

Verify the escrow account

Each installment ahead of handover should go only to the DLD regulated escrow account registered for project 3886, held at Mashreq Bank PSC. The escrow account verification is the step before any transfer; the lookup itself takes about two minutes against the official DLD project record.

Before the Next Dated Payment

Map your SPA schedule against the record

The published plan runs 10% on booking, 10% one month later, eight installments of 5% on fixed dates, and 40% on completion, so your obligations are calendar driven while the certified reading is still 0%.

After the SPA Is Signed

Confirm the Oqood registration

An off plan purchase is registered in the buyer's name on the Dubai Land Department Oqood system, and that registration is what evidences your interest in the unit while no construction data exists yet. Keep the registration reference for project 3886 with your purchase documents.

Every Reading

Track each certified reading

The next report is what turns a single 0% baseline into a trend worth reading. The construction updates hub collects each certified reading as it reaches the register.

General framework, not legal advice: milestone definitions, notice periods, and fee obligations are set by your individual SPA and the DLD record, and both should be read directly.

Buying at 0% Certified Progress?

Entering before the first certified movement trades delivery certainty for the longest payment runway and the widest choice in the release. Every payment goes to the DLD-registered escrow account for project 3886, released against certified construction progress.

Entering Now at 0%
  • The whole 60/40 schedule still ahead, ending with 40% on completion
  • Every certified reading from the 0% baseline onward is visible from your entry point
  • Choice across 1 to 4 bedroom residences, five penthouses, and six beach mansions
Entering Near Completion
  • Most of the payment plan falling due inside a short window
  • Construction record already written by the time you enter
  • Choice narrowed to whatever is still unsold late in the build
AED 5.50M ≈ USD 1.50MStarting Price
60/40 Plan40% Due on Completion
Q3 2029Expected Handover
Ask What Is Available at Passo by Beyond

20+ units listed available on the project page as of this update; availability shifts between cycles.

About the Development

Passo by Beyond Project Details

Aerial daytime view of Passo by Beyond on Palm Jumeirah with twin beachfront buildings, landscaped gardens and resort pools Presented by Tohid Fetrat
Palm Jumeirah · Beyond Developments

Filed with RERA as two G+14 residential buildings, six G+2 beach mansions, and two shared basement parking levels, Passo by Beyond is a release of approximately 625 residences on plot 2026 of the Palm Crescent. Starting prices: AED 5.50M ≈ USD 1.50M.

For buyers entering while the certified record still reads 0%, the trade off is a longer wait against the full payment runway and the widest choice of layouts, with handover expected in Q3 2029.

Passo by Beyond Project Guide

Site Context This Cycle

Explore Passo by Beyond Location on Dubai Map

Passo by Beyond sits on plot 2026 on the Crescent of Palm Jumeirah, water on both sides and a 250 metre beach frontage, and the inspection photograph filed with the March 2026 report shows that frontage as a cleared, vacant plot with the Crescent road running behind it.

Because the Crescent is a finished part of Palm Jumeirah, with its road, utilities, and neighbouring resorts already in service, this project will be built inside an established address rather than an emerging one, which matters for buyers weighing a Q3 2029 handover against what already surrounds the site. See the project’s position on the interactive Dubai real estate map.

Interactive Dubai real estate map preview
Click to view Passo by Beyond on Dubai Map

Buyer Resources for This Project

Investing in Passo by Beyond Before Construction Begins

Before a site record exists, residency planning and payment protection carry the decision. Each resource below is matched to where Passo by Beyond stands right now.

Passo by Beyond by Beyond Developments in Palm Jumeirah construction updates cover image featuring an aerial project rendering of curved waterfront residential buildings, landscaped grounds and swimming pools in Dubai - Presented by Tohid Fetrat
You Are Here

Passo by Beyond Construction Updates

This page: the certified 24 March 2026 inspection record for Passo by Beyond, baseline to handover.

Passo by Beyond by Beyond Developments in Palm Jumeirah Golden Visa card graphic above curved waterfront residences and a distant Dubai skyline in Dubai - Presented by Tohid Fetrat

Passo by Beyond Golden Visa

Check whether a qualifying Passo by Beyond purchase supports 10-year UAE Golden Visa residency eligibility.

Read Passo by Beyond Golden Visa Guide
Passo by Beyond by Beyond Developments in Palm Jumeirah escrow account protection graphic with shield and padlock icons above landscaped beachfront residences in Dubai - Presented by Tohid Fetrat

Passo by Beyond Escrow Account

Confirm the DLD-registered escrow account for project 3886 at Mashreq Bank PSC before any installment.

Verify Passo by Beyond Escrow Account

Update Timeline

Other Passo by Beyond Construction Updates

March 2026 is the first certified reading on the register for this project, so the inspection history starts here and grows with every report RERA files.

All Passo by Beyond Construction Updates

FAQs

Passo by Beyond Construction Progress in March 2026: Frequently Asked Questions

As of the RERA Independent Progress Monitoring Report conducted on 24 March 2026, Passo by Beyond is recorded at 0% construction progress on DLD project 3886, with the Progress Status field returned as N/A rather than a percentage band.

That sentence is the inspector's own note on the state of plot 2026 on 24 March 2026, and the inspection photograph filed with the report shows a cleared, vacant beachfront plot with the Crescent road behind it. The previous and current readings on the register both stand at 0%.

The DLD register lists 28 July 2025 as the registration date and 31 December 2025 as the construction start date, and the first Independent Progress Monitoring Report, dated 24 March 2026, records 0% with no activities started. Both entries stand on the register as filed, and the next report is what will show the first certified movement.

Q3 2029 is the handover stated for the project, and the DLD register carries its own registered completion date of 31 December 2029. The 24 March 2026 reading of 0% is the first certified data point against that timeline, and each later report is recorded on the Passo by Beyond construction updates hub.

Yes. Handover expectations and the registered completion date held in the DLD project register can both be revised between inspection cycles. The dates shown here reflect the position as of March 2026; any revision would appear in a later update on this cluster.

Before construction data exists, the items that carry weight are documentary: the Oqood registration of the unit with the Dubai Land Department, the escrow account the installments are paid into, which for project 3886 is held at Mashreq Bank PSC, and the dated installment schedule written into the sale and purchase agreement.

A Question the FAQ Can Not Answer?

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is helping you read the March 2026 inspection record for Passo by Beyond correctly before your next payment decision. Client identities and transactions are never published or referenced. Message me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

Get Progress Alerts