Peninsula Four The Plaza Construction Update - April 2026
April 2026 Inspection Confirms Peninsula Four The Plaza Reaches 95.59% Construction Progress in Business Bay
Final finishes, systems commissioning, and handover preparation now define site activity at Peninsula Four The Plaza, verified at 95.59 percent in the April 2026 RERA inspection cycle.
Direct advisor access. Every message answered personally, never by a call center.
Verified DLD Inspection Data
Peninsula Four The Plaza Construction Snapshot
A 7.14 point rise since December 2025 places Peninsula Four The Plaza in the handover-preparation band, the stage where inspection data speaks directly to final payment and key-collection timing.
Peninsula Four The Plaza
2461
Active
95.59%
15 April 2026
01 October 2022
1,025 residential units
114,514.32 sq m
01 February 2026 (date passed)
Data source: RERA inspection conducted on 15 April 2026, tracked against DLD inspection records. Construction tracking against RERA inspection data runs across the full tohidfetrat.com project portfolio and is reviewed after every published cycle. Last updated: July 2026.
Want each new reading the day it publishes? Message me on WhatsApp and I will send it to you directly: one message per inspection cycle, nothing else.
This Inspection Cycle
Peninsula Four The Plaza Construction Progress Summary
Between the December 2025 and April 2026 inspections, Peninsula Four The Plaza moved from 88.45% to 95.59%, a 7.14 point gain concentrated in interior finishing, MEP commissioning, and waterfront landscaping across both Business Bay towers. At this reading, site activity has shifted decisively from building the towers to preparing them for handover.
- Enabling, foundation, and podium works across the full plot
- Structural works on both 52-storey residential towers
- Facade and external envelope across tower and podium levels
- Final interior finishes across the 1,025 residential units
- MEP testing and commissioning ahead of completion certification
- Common-area and amenity fit out across lobbies, pool, and fitness
- Waterfront landscaping and promenade works on the canal frontage
- Final RERA inspection cycle toward 100%
- Building completion certificate procedures
- Handover notices and key collection (developer anticipates Q3 2026)
Payment Linked Progress
What 95.59% Progress Means for Peninsula Four Buyers
Most Dubai off plan payment plans tie installments to construction milestones or to handover itself, so a verified reading of 95.59% signals that the final completion installment and the handover process are now the live obligations. At this stage of Peninsula Four The Plaza, four actions matter most.
Verify the escrow account
Any payment still ahead of handover, including the 40% completion installment, should go only to the DLD regulated escrow account registered for project 2461. The Peninsula Four escrow account verification is the step before any transfer; the lookup itself takes about two minutes against the official DLD project record.
Reread your SPA completion clauses
Check how your sale and purchase agreement defines the completion installment and the handover notice period, and read those clauses against a completion date the DLD register already shows as passed. Not sure how your final payment maps to this reading? Send me your SPA schedule and I will map it against the certified milestones.
Book the snagging window
At 95.59% and inside the handover run-in, Peninsula Four The Plaza is firmly in the window for a pre handover inspection. The Peninsula Four snagging inspection guide covers the booking window before acceptance.
Track the final inspection
One inspection reading typically remains before completion certification. The Peninsula Four construction updates hub keeps the final stretch free of surprises.
General framework, not legal advice: milestone definitions, notice periods, and fee obligations are set by your individual SPA and the DLD record, and both should be read directly.
Buying at 95.59%?
Entering a project this close to handover trades payment-plan runway for near-term certainty: the structure is verified, the delivery window is short, and the remaining choice is between the last units available. Every payment goes to the DLD-registered escrow account for project 2461, released against certified construction progress.
- Certified near-complete structure: the inspection record above is the risk picture
- Final finishing and commissioning stage, handover approaching
- 40% of the 20/40/40 plan due at completion, minimal runway remaining
- Construction risk carried from excavation to handover
- Two to four years of waiting is the usual delivery horizon
- Longer installment runway, priced at launch levels
2 units listed available on the project page as of this update; availability shifts between cycles.
About the Development
Peninsula Four The Plaza Project Details

With structure and envelope complete across both 52-storey towers, Peninsula Four The Plaza was a finishing-stage development of 1,025 waterfront residences, from studios and apartments to duplex lofts and penthouses on the Dubai Canal frontage. Starting prices: AED 1.30M ≈ USD 353K.
For buyers entering at this stage, the trade off is a short waiting time against a later position in the payment plan, with the DLD-registered completion date of 01 February 2026 already passed and developer-anticipated handover in Q3 2026.
Peninsula Four The Plaza Project GuideSite Context This Cycle
Explore Peninsula Four The Plaza Location on Dubai Map
Peninsula Four The Plaza rises on a canal facing plot in Business Bay, its twin towers oriented toward the Dubai Water Canal and the Downtown skyline, which shapes how the final cycle is sequenced: waterfront landscaping, promenade works, and facade completion on the exposed canal frontage are among the most visible items as the project closes on handover.
Because Business Bay is an established district with completed roads, canal promenade, and utility infrastructure, Peninsula Four The Plaza is finishing into a functioning waterfront neighborhood rather than an emerging one, which matters for buyers weighing immediate occupancy or rental plans now that the structure is verified near completion. See the project's position on the interactive Dubai real estate map.

Buyer Resources for This Project
Investing in Peninsula Four The Plaza During Final Construction Progress
The handover-preparation band is where residency planning, payment protection, and handover readiness converge. Each resource below is matched to where Peninsula Four The Plaza stands right now.

Peninsula Four Construction Updates
This page: the verified April 2026 inspection record for Peninsula Four The Plaza through to handover.
Peninsula Four Golden Visa
Check whether a qualifying Peninsula Four purchase still supports 10-year UAE Golden Visa residency eligibility.
Read Peninsula Four Golden Visa Guide
Peninsula Four Escrow Account
Confirm the DLD-registered escrow account for project 2461 before releasing your final completion installment.
Verify Peninsula Four Escrow Account
Peninsula Four Snagging Inspection
At 95.59% recorded progress, arrange independent defect documentation before you accept your Peninsula Four residence.
Book Peninsula Four SnaggingUpdate Timeline
Other Peninsula Four The Plaza Construction Updates
Follow the full inspection history to see how Peninsula Four The Plaza has moved through each construction phase, reading by reading.
Where This Update Fits
Explore Peninsula Four The Plaza Structure
This monthly report is one node in the wider record: the community that surrounds the site, the developer delivering it, and the listings competing with it.

Peninsula Properties for Sale
Compare available Peninsula waterfront listings while Peninsula Four The Plaza completes its final construction phase.
Peninsula Properties for Sale
About Business Bay Master Community
See how Business Bay infrastructure, Dubai Canal frontage, and retail maturity frame Peninsula Four's waterfront setting.
Business Bay Community Guide
Select Group Developer Profile
Review Select Group's delivery record across Dubai waterfront towers before your remaining payment decisions.
Select Group Developer ProfileFAQs
Peninsula Four The Plaza Construction Progress in April 2026: Frequently Asked Questions
As of the RERA inspection conducted on 15 April 2026, Peninsula Four The Plaza stands at 95.59% construction progress in the DLD project register.
Peninsula Four The Plaza moved from 88.45% recorded in December 2025 to 95.59% on 15 April 2026, a gain of 7.14 points concentrated in interior finishing, MEP commissioning, and waterfront landscaping across both Business Bay towers.
Yes. The DLD project register listed 01 February 2026 as the expected completion date, and that date had already passed by the 15 April 2026 inspection, with the project recorded at 95.59% rather than complete. The developer's anticipated handover is Q3 2026 per the project page. How completion certification works is covered on the Peninsula Four construction updates hub.
The DLD-registered completion date of 01 February 2026 has passed, and the project page lists an anticipated handover of Q3 2026 as of this update. Expected dates can be revised between inspection cycles, and any revision would appear in a later update on this cluster.
With structural works and the external envelope complete on both towers as of the 15 April 2026 inspection, site activity centered on final interior finishes across the 1,025 residential units, MEP testing and commissioning, common-area and amenity fit-out, and waterfront landscaping on the canal-facing plot.
Yes, the window is open. Once a project passes roughly 70% or comes within months of handover the practical booking window is open, and at 95.59% recorded in April 2026 Peninsula Four is firmly inside it, so arranging the inspection ahead of the handover notice avoids compressed timelines later.
A Question the FAQ Can Not Answer?

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is helping you read the April 2026 inspection record for Peninsula Four The Plaza correctly before your next payment decision. Client identities and transactions are never published or referenced. Message me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.