Skyvue Stellar by Sobha Realty in Sobha Hartland 2 project rendering used for the July 2026 construction update showing the planned Stellar entrance facade with curved podium levels and landscaped terraces in Dubai - Presented by Tohid Fetrat

Sobha Realty · Sobha Hartland 2 · Construction Update

Skyvue Stellar Construction Update - July 2026

July 2026 Inspection Records 10.54% Progress on the Skyvue Register in Sobha Hartland 2

Mobilisation, enabling and foundation works, and ongoing structure works define the July 2026 inspection record for the Skyvue registration that includes Skyvue Stellar, read at 10.54 percent.

Direct advisor access. Every message answered personally, never by a call center.

10.54%DLD Register Reading
30 July 2026Inspection Date
Q1 2029Expected Handover
3435DLD Project Number

Verified DLD Inspection Data

Skyvue Stellar Construction Snapshot

A 5.43 point rise since the previous DLD reading (5.11%, undated in the register) puts the Skyvue registration at 10.54% on 30 July 2026, inside the enabling and foundations band, where the record matters most for checking registration and escrow details against each construction payment.

Project Name

Skyvue (four buildings)

Project Number

3435

Project Status

Active

Construction Progress

10.54% (whole registration)

Inspection Date

30 July 2026

Construction Start

01 April 2025

Total Units

449 residences

Total Built Area

235,150.80 sq m (joint DLD register)

Expected Completion

Q1 2029

Data source: the Dubai Land Department project register (inspection report dated 30 July 2026) and the RERA Independent Progress Monitoring Report of the same date. Skyvue Stellar is one of the towers of Sobha Realty's Skyvue development in Sobha Hartland 2: the DLD does not register these towers one by one but lists them together as project 3435, "Skyvue", which the monitoring report describes as four buildings. A register search therefore uses "Skyvue", not "Skyvue Stellar", and every register figure on this page covers the whole registration rather than this tower by itself. The hero image is a developer rendering, not a site photograph. Construction tracking against RERA inspection data runs across the full tohidfetrat.com project portfolio and is reviewed after every published cycle. Last updated: July 2026.

Want each new reading the day it publishes? Message me on WhatsApp and I will send it to you directly: one message per inspection cycle, nothing else. Message me on WhatsApp

This Inspection Cycle

Skyvue Stellar Construction Progress Summary

The RERA monitoring report for the 30 July 2026 visit lists the main contract as progressing, with mobilisation still under way, enabling and foundation works advancing on site and structure works running alongside them. The report covers the four-building Skyvue registration as one site and does not split its notes by building, so none of these activities is assigned to Skyvue Stellar on its own.

Completed
  • DLD registration of project 3435 on 25 February 2025
  • Registered construction start on 01 April 2025
  • An earlier register reading of 5.11%, shown without a date
In Progress at 10.54%
  • Site mobilisation, still under way at the July visit
  • Enabling and foundation works across the registration
  • Structure works running in parallel with the foundations
  • Main contract recorded as progressing
Ahead of Handover
  • Further RERA readings on the shared Skyvue register
  • Superstructure, facade and fit out works for the 449 residences
  • Handover of Skyvue Stellar in Q1 2029 per Sobha Realty
Next inspectionAppears in the DLD project register under "Skyvue" after the next RERA site visit; no date is published in advance, and each new reading is added to this cluster as it is published.
Handover and registered datesSobha Realty's handover quarter for Skyvue Stellar is Q1 2029. The registered completion date of 31 March 2030 applies to the whole multi-tower Skyvue registration and falls after that quarter; registered dates can be revised between cycles.
Remaining distance89.46 percentage points separate the 30 July 2026 reading from 100% for the whole Skyvue registration. Arithmetic, not a forecast: 10.54 points over the 485 days since the registered start on 01 April 2025 average about 0.65 points per month.

Payment Linked Progress

What the 10.54% Skyvue Reading Means for Skyvue Stellar Buyers

Skyvue Stellar is sold on a 60/40 plan: 20% on booking, 40% during construction spread over four payments, and 40% on handover in Q1 2029. A register reading of 10.54% does not by itself show which of those four construction payments has fallen due, because each SPA sets that schedule. At this early stage, four actions matter most.

Before Any Construction Payment

Verify the escrow account

Every construction payment should go only to the DLD regulated escrow account held with Dubai Islamic Bank for the Skyvue registration, project 3435. Skyvue Stellar escrow account verification comes before any transfer; the lookup itself takes about two minutes against the official DLD project record, where the project appears as Skyvue.

Before the Next Installment

Reread your SPA payment schedule

Check how your sale and purchase agreement schedules the four construction payments and the 40% due on handover in Q1 2029, and keep that schedule beside each new register reading. Not sure how your installments map to this reading? Send me your SPA schedule and I will map it against the recorded milestones.

After Booking

Confirm your Oqood registration

Off plan purchases in Dubai are recorded in the Dubai Land Department's Oqood register. Confirm that your Skyvue Stellar purchase has been registered there and keep that record with your SPA, since it is the official evidence of your interest in a unit that is still under construction.

Every Cycle

Track each new reading

Early readings on a four-building register tend to move in uneven steps while enabling and foundation work runs. The Skyvue Stellar construction updates hub dates every reading as it is published.

General framework, not legal advice: payment schedules, notice periods, and fee obligations are set by your individual SPA and the DLD record, and both should be read directly.

Buying at 10.54% on the Skyvue Register?

Entering at an early register reading trades a longer wait for a longer runway: most of the price on the 60/40 plan is paid during the build and on handover, while enabling, foundation and structure works are still under way. Every payment goes to the DLD-registered escrow account for project 3435, released against construction progress recorded for the whole Skyvue registration.

Entering at the 10.54% Reading
  • The register record above is the current risk picture, registration-wide
  • Handover quarter Q1 2029 per Sobha Realty
  • 40% of the 60/40 plan falls due on handover, not up front
Typical Late Stage Entry
  • Most construction risk already retired before purchase
  • A short wait between the main payments and the keys
  • A larger share of the price due within a narrow window
AED 1.85M ≈ USD 504KStarting Price
60/40 Plan40% Due on Handover
Q1 2029Expected Handover
Ask What Is Available at Skyvue Stellar

20+ units listed available on the project page as of this update; availability shifts between cycles.

About the Development

Skyvue Stellar Project Details

Skyvue Stellar by Sobha Realty in Sobha Hartland 2 aerial project rendering of multiple residential towers with a green arrow highlighting one building in Dubai - Presented by Tohid Fetrat
Sobha Hartland 2 · Sobha Realty

Skyvue Stellar is an early stage tower of 449 apartments in six layouts, planned per the developer's factbook as a ground floor, 77 upper floors and a roof, while foundation works progress across its shared registration. Starting prices: AED 1.85M ≈ USD 504K.

For buyers entering at this point, the trade off is the longest wait for the keys against the longest runway on the 60/40 plan, with handover expected in Q1 2029 per Sobha Realty.

Skyvue Stellar by Sobha Realty Project Guide

Site Context This Cycle

Explore Skyvue Stellar Location on Dubai Map

Skyvue Stellar stands within the Skyvue cluster of towers in Sobha Hartland 2, the lagoon-set Sobha Realty master community beside the Ras Al Khor Wildlife Sanctuary. The enabling, foundation and structure works noted in July 2026 are recorded for that shared Skyvue site as a whole rather than for a separate Stellar plot, so this cycle's reading describes ground works across the cluster, not progress on Stellar by itself.

Sobha Realty plans an international school, office space, a mall, a clubhouse and retail within Sobha Hartland 2, while Business Bay lies about 12 minutes' drive and Downtown Dubai about 15 minutes from the community. For a buyer at this stage, the useful question is how much of that planned district will be in place by the Q1 2029 handover, worth checking against the developer's community updates rather than assuming. See the project's position on the interactive Dubai real estate map. See the project’s position on the interactive Dubai real estate map.

Interactive Dubai real estate map preview
Click to view Skyvue Stellar by Sobha Realty on Dubai Map

Buyer Resources for This Project

Investing in Skyvue Stellar During Early Construction Progress

The early band is where registration, payment protection and residency planning get settled, long before any handover preparation begins. Each resource below matches where Skyvue Stellar stands at the July 2026 reading.

Skyvue Stellar by Sobha Realty in Sobha Hartland 2 construction updates cover image featuring split project renderings of glass residential towers and landscaped podium surroundings in Dubai - Presented by Tohid Fetrat
You Are Here

Skyvue Stellar Construction Updates

This page: the 30 July 2026 Skyvue register reading, explained for Skyvue Stellar buyers before payments.

Skyvue Stellar by Sobha Realty in Sobha Hartland 2 Golden Visa concept graphic with a golden card above a rendering of a curved pool and landscaped residential garden in Dubai - Presented by Tohid Fetrat

Skyvue Stellar Golden Visa: Qualifying From the 2 Bedroom Apartment

Skyvue Stellar by Sobha Realty lists 1.5, 2, 3, 3.5 and 4 bedroom types above the AED 2M threshold.

Read Skyvue Stellar Golden Visa Guide
Skyvue Stellar by Sobha Realty in Sobha Hartland 2 escrow account concept graphic showing a shield and padlock above a rendered water fountain and residential towers in Dubai - Presented by Tohid Fetrat

Skyvue Stellar Escrow: Plot 451 in Bukadra, DLD Project 3435

Skyvue Stellar's 449 units use the Skyvue escrow at Dubai Islamic Bank, DLD project 3435, read 10.54% in July 2026.

Verify Skyvue Stellar Escrow Account

Update Timeline

Other Skyvue Stellar Construction Updates

July 2026 is the first monthly report for Skyvue Stellar; the hub collects every later reading on the Skyvue register as it is published.

All Skyvue Stellar Construction Updates

FAQs

Skyvue Stellar Construction Progress in July 2026: Frequently Asked Questions

The Dubai Land Department register recorded 10.54% on 30 July 2026 for project 3435, listed as Skyvue: the single registration that covers Skyvue Stellar together with the other towers of the development. The previous reading shown in the register is 5.11% and carries no date, so the 5.43 point difference between the two cannot be converted into a monthly pace.

No. The RERA monitoring report dated 30 July 2026 describes registration 3435 as a residential and commercial development of four buildings and gives no building-by-building breakdown, so 10.54% describes the whole Skyvue registration. No separate register percentage for Skyvue Stellar appears in the July 2026 record.

The monitoring report for the 30 July 2026 visit lists the main contract as progressing, with mobilisation still under way, enabling and foundation works progressing on site and structure works ongoing as well. These notes apply to the registration as a whole and do not say which building each activity belongs to.

Nothing in the July 2026 record changes it: Sobha Realty's handover quarter for Skyvue Stellar remains Q1 2029 as of this update, and a register percentage records progress rather than resetting a date. Dates in the register and in an SPA can still be revised in later cycles; how the handover quarter sits against the dates of the wider registration is set out on the Skyvue Stellar construction updates hub.

The reading alone does not settle that. The 60/40 plan places 40% of the price in four payments during construction, and the timing of each payment is fixed in the buyer's SPA rather than in the DLD register, so the SPA schedule is the document to compare with the 30 July 2026 record.

No. It is a Sobha Realty rendering of the planned Skyvue Stellar entrance, used to illustrate this update, and it does not document on-site progress. The register record for 30 July 2026 carries its own inspection photographs, which are not reproduced on this page.

A Question the FAQ Can Not Answer?

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is helping you read the July 2026 inspection record for Skyvue Stellar correctly before your next payment decision. Client identities and transactions are never published or referenced. Message me directly: you will always reach me personally, never a call center or sales team.