Sobha Realty · Sobha Hartland 2
Skyvue Stellar Construction Updates
From Enabling Works Toward a Q1 2029 Handover, Read on the Shared Skyvue Register
The Skyvue registration that includes Skyvue Stellar read 10.54% at its 30 July 2026 inspection, an early baseline for tracking this 449-residence Sobha Hartland 2 tower.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
Skyvue Stellar at a Glance
Skyvue Stellar is a 449-residence apartment tower by Sobha Realty in Sobha Hartland 2, one of the towers of the Skyvue development and the one Sobha Realty presents as the tallest tower of the Skyvue collection. The Dubai Land Department does not register those towers one by one: it lists them together as project 3435, "Skyvue", which the RERA monitoring report describes as four buildings, so a register search uses "Skyvue" rather than "Skyvue Stellar". Every register figure on this page, from the 01 April 2025 construction start to the 10.54% read on 30 July 2026, therefore covers the whole registration and not this tower by itself. That split defines how to read this record: the unit count and the Q1 2029 handover quarter are Sobha Realty figures for Skyvue Stellar, while the progress readings describe a four-building site.
3435 (registered as Skyvue)
Active
01 April 2025 (DLD)
449 residences in Skyvue Stellar
235,150.80 sq m (joint DLD register)
31 March 2030 (DLD, whole Skyvue registration)
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
Skyvue Stellar Construction Update Timeline
So far this record holds one dated reading and one undated one: the register shows 10.54% at the 30 July 2026 inspection and an earlier 5.11% that it lists without a date. Three registration milestones frame them, each covering the whole Skyvue registration: DLD registration on 25 February 2025, the registered construction start on 01 April 2025 and a registered completion date of 31 March 2030. The undated reading sits on the track below as an unlabelled dot, and only the dated July 2026 reading carries a table row with its full monthly update.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| July 2026 | 10.54% | 30 July 2026 | View the July 2026 update |
Pace Analysis
How Fast Skyvue Stellar Has Been Built
With a single dated reading there is no inspection-to-inspection pace to measure yet. What the record does support is two pieces of arithmetic, both for the whole Skyvue registration and neither of them a forecast:
- Apr 2025 to Jul 2026: mobilisation, enabling and foundations, 10.54 points in the 485 days from the 01 April 2025 registered start to the 30 July 2026 reading (arithmetic, not a forecast)About 0.65 points per month
- Jul 2026 to Mar 2030: the remaining 89.46 points spread evenly over the 1,340 days to the 31 March 2030 registered completion of the whole registration (arithmetic, not a forecast)About 2.00 points per month
Side by side, the two figures describe where the shared site stands rather than how it will finish. The 0.65 average folds roughly 16 months of mobilisation, enabling and foundation works into one number, and that kind of below-ground work moves a register percentage slowly; the 2.00 figure is only what the remaining 89.46 points would take if spread evenly to 31 March 2030. Neither is set against the Q1 2029 handover quarter of Skyvue Stellar, because both readings cover four buildings together. For an end user, the signal worth waiting for is the second dated reading, which turns this record into a measured curve; for an investor, that first measured pace, not this opening average, is the figure to compare with Sobha Realty's quarter.
Get the Next Inspection Figure First
Tell me you are tracking Skyvue Stellar and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About Skyvue Stellar at Sobha Hartland 2
A register reading for four buildings only matters next to what this one tower will deliver. The full project guide sets out what Skyvue Stellar buyers are tracking toward:

Skyvue Stellar by Sobha Realty: 449 Residences, 1 to 4 Bedrooms
Skyvue Stellar is a Sobha Realty tower in Sobha Hartland 2 within the Skyvue development, offering 1 to 4 bedroom layouts.
View the Skyvue Stellar Project GuideConsidering an Early-Stage Entry?
Availability at Skyvue Stellar moves with each Sobha Realty release while the shared site is still in enabling and foundation works. If this record is what brought you here, ask me for current availability before you settle on a layout, a floor and a side of the tower.
Ask About Remaining Availability on WhatsAppStage Record
Skyvue Stellar Build Stages, Mapped to the Inspections
Only the first two stages below have register evidence so far. The later three are framed by what the record already fixes rather than by readings: the developer's configuration for Skyvue Stellar, its Q1 2029 handover quarter, and a register that reports one percentage for all four Skyvue buildings.
Registration and Site Activation
The Skyvue registration entered the DLD register on 25 February 2025, five weeks before the 01 April 2025 registered construction start that opens this record.
Mobilisation, Enabling and Foundations
The 30 July 2026 monitoring report notes mobilisation still under way, enabling and foundation works progressing and structure works ongoing as well, at 10.54% for the whole registration, after an undated earlier reading of 5.11%.
Tower Structure
Skyvue Stellar is planned as a ground floor, 77 upper floors and a roof per the developer's factbook. Structure works are noted across the registration, but the register does not say which building they belong to.
Facade, Fit-Out and Building Services
The factbook specifies a double-glazed floor-to-ceiling glass curtain wall, district cooling with fan coil units and home automation provisions; these are Sobha Realty's stated specifications and may change.
Finishing, Commissioning and Handover
Apartment finishing, systems commissioning and handover of the 449 residences, which Sobha Realty schedules for Q1 2029; each register reading on the way is dated here as it is published.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Skyvue Stellar's own record.
Buyer Position
Tracking Your Position at Skyvue Stellar
This page is one of four project resources that together cover a Skyvue Stellar purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Skyvue Stellar Construction Updates
This page: every dated Skyvue register reading for Skyvue Stellar, from registered start to Q1 2029.

Skyvue Stellar Golden Visa: Qualifying From the 2 Bedroom Apartment
Skyvue Stellar by Sobha Realty lists 1.5, 2, 3, 3.5 and 4 bedroom types above the AED 2M threshold.
Read the Skyvue Stellar Golden Visa Guide
Skyvue Stellar Escrow: Plot 451 in Bukadra, DLD Project 3435
Skyvue Stellar's 449 units use the Skyvue escrow at Dubai Islamic Bank, DLD project 3435, read 10.54% in July 2026.
Verify the Skyvue Stellar Escrow AccountApproaching Handover
Between 10.54% and Handover: What Skyvue Stellar Buyers Should Do Now
At the July 2026 reading the shared Skyvue site is still in enabling and foundation works, so the decisions that count for a Skyvue Stellar buyer concern paperwork and payments, not the finished tower. Construction payments fall due on the dates your SPA sets, not when a new reading appears here, so the three steps below belong before your next transfer rather than after it.
First, before any construction transfer, match the account details against the Skyvue Stellar escrow account page, which shows how to find the Dubai Islamic Bank account under the register name Skyvue.
Second, if residency is part of your plan, check your unit type against the threshold in the Skyvue Stellar Golden Visa guide, since eligibility follows the final purchase price of the specific unit.
Third, follow the record itself: the July 2026 Skyvue Stellar construction update explains the first dated reading in full, and every later reading on the Skyvue register is added to this page with its date.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore Sobha Hartland 2 Structure
A register reading for four buildings says little on its own about the district Skyvue Stellar will hand over into. These three pages put the build in its market, community and developer context:

Sobha Hartland 2 Properties for Sale: Riverside Crescent and Skyscape Apartments
Explore Sobha Hartland 2 properties for sale, comparing Riverside Crescent and Skyscape apartments, payment plans, handover dates and availability.
See Sobha Hartland 2 Properties for Sale
Sobha Hartland 2: A Swimmable Lagoon Master Community in Bukadra
Sobha Hartland 2 is Sobha Realty's second MBR City master community, with 15 named projects around a swimmable lagoon.
Explore the Sobha Hartland 2 Community
Sobha Realty: In-House Construction, From High-Grade Materials to the Façade Panels
Sobha Realty controls every stage of construction itself, from producing high-grade materials to the marble flooring and façade panels.
View the Sobha Realty Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
Skyvue Stellar Construction Updates Frequently Asked Questions
Skyvue Stellar is in the mobilisation, enabling and foundations stage of its shared DLD registration: project 3435, listed as Skyvue, read 10.54% on 30 July 2026, a figure covering all four buildings of that registration rather than this tower alone. The dated record is in the inspection timeline above.
The register reading for the whole Skyvue registration rose 5.43 points, from a previous 5.11% to 10.54% recorded on 30 July 2026. The register lists the 5.11% reading without a date, so the rise cannot be turned into a monthly pace. That inspection is covered in full in the Skyvue Stellar July 2026 construction report.
Sobha Realty's handover quarter for Skyvue Stellar is Q1 2029, while 31 March 2030 is the registered completion date of the whole multi-tower Skyvue registration, project 3435, in the DLD record as of 30 July 2026, about a year after that quarter. The registered date applies to every building in the registration, registered dates can be revised, and this page's record is updated as each new reading is published.
Skyvue Stellar holds 449 residences per Sobha Realty, while the DLD registration it belongs to, project 3435 Skyvue, covers four buildings, so the register's own unit and area totals describe the whole development and are not presented here as the tower's figures. No separate built-up area for Skyvue Stellar appears in the register, which is why this page shows the tower's unit count and its Q1 2029 handover quarter instead.
As arithmetic rather than a forecast, the whole Skyvue registration averaged about 0.65 points per month from its 01 April 2025 registered start to 10.54% on 30 July 2026, and reaching 100% by the 31 March 2030 registered completion would take about 2.00 points per month. Both figures describe all four buildings; the pace analysis above sets out the working.
The DLD record shows the Skyvue registration, project 3435, registered on 25 February 2025 and its construction started on 01 April 2025, five weeks later. The first dated reading in the register is 10.54% on 30 July 2026, 485 days after that start.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the Skyvue Stellar construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.