Arancia at The Yards Construction Update May 2026 featuring contemporary residential buildings surrounding a landscaped courtyard with water features Presented by Tohid Fetrat

Beyond Developments · The Yards · Construction Update

Arancia at The Yards Construction Update - May 2026

May 2026 Inspection Sets a 0% Baseline for Arancia at The Yards in City of Arabia

The 18 May 2026 inspection found no construction activity yet at Arancia at The Yards, with the DLD register recording the build start for 30 October 2026.

Direct advisor access. Every message answered personally, never by a call center.

0%DLD Register Reading
18 May 2026Inspection Date
Q1 2029Expected Handover
4480DLD Project Number

DLD Register Data

Arancia at The Yards Construction Snapshot

A 0% first reading on 18 May 2026 fixes the starting line for Arancia at The Yards: the record captures the project before any site works, and every later inspection will be measured against this baseline.

Project Name

Arancia at The Yards by Beyond Developments

Project Number

4480

Project Status

Active

Construction Progress

0%

Inspection Date

18 May 2026

Construction Start

30 October 2026

Total Units

272 residences

Total Built Area

24,212.04 sq m

Expected Completion

30 October 2028

Data source: Dubai Land Department project register reading for project 4480 from the RERA inspection of 18 May 2026; no earlier reading appears in the record. Construction tracking against RERA inspection data runs across the full tohidfetrat.com project portfolio and is reviewed after every published cycle. The hero image above is a developer rendering of the finished project, not a site photograph. Last updated: May 2026.

Want each new reading the day it publishes? Message me on WhatsApp and I will send it to you directly: one message per inspection cycle, nothing else. Message me on WhatsApp

This Inspection Cycle

Arancia at The Yards Construction Progress Summary

The 18 May 2026 inspection record for project 4480 states that "no construction activity had commenced at the time of inspection", so this 0% is a starting line rather than a measure of pace. With the construction start recorded on the DLD register for 30 October 2026, 165 days after the visit, the record describes Arancia in its pre-construction stage: registered, priced and offered off-plan, with its three buildings yet to break ground.

On Record
  • Project 4480 registered with the DLD, status Active
  • Baseline RERA inspection dated 18 May 2026 at 0%
  • Building configuration recorded as G+7, G+7 and G+6
Status at 0%
  • Pre-construction: no works recorded at the May 2026 inspection
  • Off-plan sales of 272 residences in 1, 2 and 3 bedroom layouts
  • Payments held in the DLD regulated escrow account for project 4480
Ahead of Handover
  • Construction start recorded for 30 October 2026
  • Enabling works, foundations and structure for Buildings A, B and C
  • Registered completion date of 30 October 2028, with handover expected in Q1 2029
Next inspectionNo date is recorded; the next reading is published in the DLD project register after the next RERA site visit, and figures on this page are as of 18 May 2026.
Construction start30 October 2026 per the DLD register, 165 days after this inspection.
Completion targetRegistered completion date 30 October 2028 per the current DLD record; the developer's expected handover is Q1 2029.
Remaining distanceThe full 100 percentage points lie between the 18 May 2026 baseline and completion.

Payment Linked Progress

What 0% Progress Means for Arancia at The Yards Buyers

The developer's launch payment plan for Arancia splits the price into 10% at booking (plus the 4% DLD registration fee), 30% through construction and 60% at completion. With the register at 0% on 18 May 2026, the booking share is the only fixed amount due before construction instalments begin, and four actions matter most at this point.

Before Your Booking Payment

Verify the escrow account

The 10% booking payment and every construction instalment should go only to the DLD regulated escrow account registered for project 4480. Arancia at The Yards escrow account verification is the step before any transfer; the lookup itself takes about two minutes against the official DLD project record.

Before Signing the SPA

Read how your SPA schedules the 30%

The launch plan sets the shares but not the dates, so your sale and purchase agreement is where the construction instalments are scheduled: check whether they fall on fixed dates or on recorded progress, and how the Q1 2029 handover is defined. Not sure how your instalments map to a 0% start? Send me your SPA schedule and I will map it against the DLD register milestones.

After Booking

Confirm your Oqood registration

Once the booking is processed, your unit should appear on the DLD off-plan register, known as Oqood, under project 4480 and in your name. Check that the project number, unit and price on the registration match your SPA before the first construction instalment falls due.

Every Cycle

Watch the first readings after the start

The readings that follow the 30 October 2026 registered start will show whether works begin on the date recorded. Arancia at The Yards construction updates collects each reading as it publishes.

General framework, not legal advice: milestone definitions, instalment dates, and fee obligations are set by your individual SPA and the DLD record, and both should be read directly.

Buying at the 0% Baseline?

Entering before construction starts trades certainty for runway: nothing is built yet, but with 10% at booking and 30% through construction, 60% of the price waits until completion. Every payment goes to the DLD-registered escrow account for project 4480, released against construction progress recorded on the DLD register.

Entering at the 0% Baseline
  • Recorded at 0% on 18 May 2026, before the registered construction start
  • Launch price list from AED 1.00M ≈ USD 272K
  • 60% of the 40/60 plan due on completion in Q1 2029
Typical Late Stage Entry
  • Structure standing and recorded progress well advanced
  • Shorter wait to handover, with less time to spread instalments
  • Fewer remaining units and less choice of layout or floor
AED 1.00M ≈ USD 272KStarting Price
40/60 Plan60% Due on Completion
Q1 2029Expected Handover
Ask What Is Available at Arancia

Units listed as Available on the Arancia at The Yards project page as of this update, with no count published; availability shifts between cycles.

About the Development

Arancia at The Yards Project Details

Aerial masterplan view of Arancia at The Yards by Beyond Developments with landscaped courtyards and green terraces Presented by Tohid Fetrat
The Yards · Beyond Developments

At its 0% baseline, Arancia at The Yards exists on the register and on plan: 272 residences in three low-rise buildings, configured G+7, G+7 and G+6 around a central green valley, with 1, 2 and 3 bedroom apartments. Starting prices: AED 1.00M ≈ USD 272K.

For buyers entering before the 30 October 2026 registered start, the trade off is the longest wait in the build cycle against launch-stage pricing and the full payment runway, with handover expected in Q1 2029.

Arancia at The Yards by Beyond Developments Project Guide

Site Context This Cycle

Explore Arancia at The Yards Location on Dubai Map

Arancia opens The Yards, the 165,000 sq m Beyond masterplan in City of Arabia beside Sheikh Mohammed Bin Zayed Road (E311): it is the first development planned to rise there, with Buildings A, B and C set around a central green valley. As the opening phase it is the community's starting point rather than an infill site, and the May 2026 record reflects that: a 0% reading taken months before the registered start.

Around the masterplan, the developer's location map puts IMG World 3 minutes and Global Village 10 minutes away, while the community's own nursery, school, clinic, mosque and sports hub exist only in the plans for now. For buyers at this stage that means weighing the road network that exists now against community services that arrive with later phases. See the project’s position on the interactive Dubai real estate map.

Interactive Dubai real estate map preview
Click to view Arancia at The Yards by Beyond Developments on Dubai Map

Buyer Resources for This Project

Investing in Arancia at The Yards Before Construction Starts

Before the first construction instalment, payment protection, residency planning and the inspection record carry the most weight. Each resource below is matched to where Arancia stands at its 0% baseline.

Arancia at The Yards Construction Updates showing an aerial view of the development layout, residential buildings, landscaped areas, and water features Presented by Tohid Fetrat
You Are Here

Arancia at The Yards Construction Updates

This page: the 18 May 2026 DLD register reading for Arancia, a 0% pre-construction baseline.

Arancia at The Yards Golden Visa image featuring contemporary residences, landscaped gardens, and a UAE Golden Visa card Presented by Tohid Fetrat

Arancia at The Yards Golden Visa: Two of Three Apartment Types

Arancia at The Yards, Beyond's 272 apartments in three low-rise buildings, qualifies at 2 and 3 bedrooms but not 1 bedroom.

Read Arancia at The Yards Golden Visa Guide
Arancia at The Yards escrow account illustration featuring secure residential buildings with shield and lock protection symbols Presented by Tohid Fetrat

Arancia at The Yards Escrow: Beyond's Account at ADCB

Arancia at The Yards by Beyond, DLD project 4480: 284 units paying into Abu Dhabi Commercial Bank escrow.

Verify Arancia at The Yards Escrow Account

Update Timeline

Other Arancia at The Yards Construction Updates

This May 2026 record opens the Arancia inspection history; each later reading joins the hub as it publishes, building the timeline from this 0% baseline.

All Arancia at The Yards Construction Updates

FAQs

Arancia at The Yards Construction Progress in May 2026: Frequently Asked Questions

As of the RERA inspection dated 18 May 2026, Arancia at The Yards (DLD project 4480, status Active) stands at 0% in the Dubai Land Department project register. No earlier reading appears in the record, so there is no previous figure to compare it with and no rate of progress to calculate from this month.

No change is recorded. The developer's expected handover remains Q1 2029, while the DLD register as of 18 May 2026 carries a registered completion date of 30 October 2028, about five months earlier. Both dates can be revised between inspection cycles and any revision would appear in a later update; how the register dates relate across the full build is tracked on the Arancia at The Yards construction updates hub.

The 18 May 2026 inspection found no construction under way at Arancia at The Yards. The visit took place 165 days before the construction start date recorded on the DLD register, so the reading documents the site before works rather than a slowdown, and nothing in the record points to a delay.

The DLD register records 30 October 2026 as the construction start for project 4480, 165 days after the 18 May 2026 inspection. At the time of this update that date was still ahead, so this page describes Arancia before the build; whether works began on that date will show in the first reading taken after it.

No. The image at the top of this page is a developer rendering of the finished courtyard and buildings, showing what is planned rather than what exists. At the 18 May 2026 inspection the site showed no construction, and site conditions are documented by the DLD inspection record, not by marketing imagery.

No date for the next inspection is recorded. New readings appear in the Dubai Land Department project register after each RERA site visit, and the first one dated after 30 October 2026 will be the first to fall inside the registered construction period for Buildings A, B and C.

A Question the FAQ Can Not Answer?

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is helping you read the May 2026 inspection record for Arancia at The Yards correctly before your next payment decision. Client identities and transactions are never published or referenced. Message me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

Get Progress Alerts