Nakheel · Dubai Islands
Bay Grove Residences Phase 4 Construction Updates
The Register Record of the Final Bay Grove Release on Island B
The DLD register placed Bay Grove Residences Phase 4 at 0.04% on 24 July 2026, the mobilisation baseline for every later reading on this Island B plot.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
Bay Grove Residences Phase 4 at a Glance
Bay Grove Residences Phase 4 is Nakheel's closing release of Bay Grove on Island B: 257 residences in four buildings, from four to twenty upper floors, over one combined basement and ground level. The register dates its construction start to 17 August 2025, and its only dated reading, 0.04% in the DLD register on 24 July 2026, came with inspection notes of mobilisation works and no construction activity started yet. Because this last Bay Grove plot at the end of the bay was first read before anything stood on it, the record here begins at ground level, with the register and the inspection notes as its only evidence so far.
3785
Active
17 August 2025 (DLD)
257 residential units
34,809.75 sq m
15 September 2028 (DLD)
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
Bay Grove Residences Phase 4 Construction Update Timeline
So far this record holds a single dated entry: 0.04% in the DLD register on 24 July 2026, following a previous inspection figure of 0% that the register gives without a date. That is why the track below carries one dot sitting almost on its starting edge, and why the table has one row, linked to the July 2026 update that covers the inspection cycle in full. The July entry is illustrated with a developer rendering of the planned poolside buildings, not a site or inspection photograph.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| July 2026 | 0.04% | 24 July 2026 | View the July 2026 update |
Pace Analysis
How Fast Bay Grove Residences Phase 4 Has Been Built
A pace figure needs two dated readings, and the Bay Grove Residences Phase 4 register holds one. What the record does support is plain arithmetic, set out below with its sources:
- Undated previous figure to 24 Jul 2026: 0% to 0.04% in the DLD register+0.04 points, no dated span
- Registered start 17 Aug 2025 to the 24 Jul 2026 inspection, whose notes record no construction activity started yet341 days apart
- Published 70/30 schedule to August 2026 (20% + 10% + 5% + 10%) against the 0.04% DLD register reading of 24 Jul 202645% of the price due by date
- From the 0.04% DLD register reading of 24 Jul 2026 to 100% at handover in June 202999.96 points still to record
Nothing in this record can be read as a curve yet. A points-per-month figure divides a change by the time between two dated inspections, and because the register gives its 0% no date, the 0.04 point step has no span to divide by; a rate built from it, or from the 17 August 2025 registered start, would be invented precision rather than measurement. The second dated reading for project 3785 is what opens the first measurable interval. Until then, the numbers worth holding are calendar ones: the published schedule places 45% of the price by August 2026 while the DLD register stood at 0.04% on 24 July 2026, two figures from separate published sources set side by side as arithmetic, with the SPA setting the actual schedule for any purchase. For an end user, that makes June 2029 the date to plan around rather than anything on site; for an investor, the first genuine read on delivery pace at this Island B plot is still one dated inspection away.
Get the Next Inspection Figure First
Tell me you are tracking Bay Grove Residences Phase 4 and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About Bay Grove Residences Phase 4 at Island B
A DLD register reading of 0.04% on 24 July 2026 describes a plot, not a home. The project guide covers what the four buildings on that plot are planned to deliver:

Bay Grove Residences Phase 4, the Closing Chapter of Bay Grove
Bay Grove Residences Phase 4 spreads 257 Nakheel residences across four buildings of different heights on one shared podium and basement.
View the Bay Grove Residences Phase 4 Project GuideConsidering a Pre-Construction Entry?
Buying before any structure rises means choosing from more of the Phase 4 release, and that choice narrows as other buyers commit across the four buildings. If this record is what brought you here, ask me what is currently available and how each tier's dated instalments would fall for you.
Ask About Remaining Availability on WhatsAppStage Record
Bay Grove Residences Phase 4 Build Stages, Mapped to the Inspections
Each stage below is pinned to the register date or inspection that defines it for project 3785, so the record shows where Bay Grove Residences Phase 4 actually stands: past registration and a recorded start, inside mobilisation, with every structural stage of the four buildings still ahead.
Registration in the DLD Register
Project 3785 was registered on 20 June 2025 for plot 3029, with Mashreq Bank PSC recorded as the trust account bank for buyer payments.
Registered Start and Site Mobilisation
The register dates the start to 17 August 2025; at the 24 July 2026 inspection, mobilisation works were ongoing, no construction activity had started, and the DLD register read 0.04%.
Shared Basement and Ground Level
One combined basement and one combined ground level are planned to carry all four buildings; no register reading covers this stage yet.
Four Building Structures
BG 12 (B+G+13+R), BG 13 (B+G+17+R), BG 14 (B+G+20+R) and BG 15 (B+G+04+R) are designed to rise from the podium; no structural reading exists yet.
Facades, Finishing and Handover
The registered completion date in the DLD register is 15 September 2028; handover of the 257 residences is scheduled for June 2029.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Bay Grove Residences Phase 4's own record.
Buyer Position
Tracking Your Position at Bay Grove Residences Phase 4
This page is one of four project resources that together cover a Bay Grove Residences Phase 4 purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Bay Grove Residences Phase 4 Construction Updates
This page: each dated DLD register reading for Bay Grove Residences Phase 4, logged through handover.

Bay Grove Residences Phase 4 Golden Visa: The Final Release
Bay Grove Residences Phase 4, 257 Nakheel residences, qualifies at three of four tiers; 1 bedroom apartments sit below.
Read the Bay Grove Residences Phase 4 Golden Visa Guide
Bay Grove Residences Phase 4: The Fourth Phase's Mashreq Escrow
Mashreq keeps Bay Grove Residences Phase 4 escrow under DLD project 3785: 257 units, certified 0.04% in July 2026.
Verify the Bay Grove Residences Phase 4 Escrow AccountApproaching Handover
Between 0.04% and Handover: What Bay Grove Residences Phase 4 Buyers Should Do Now
With the DLD register at 0.04% on 24 July 2026 and the inspection notes recording mobilisation only, the Bay Grove Residences Phase 4 plot gives a buyer little to inspect yet, while the published plan keeps running by calendar date through December 2026, April 2027 and August 2027. That is why the three checks below belong before each dated instalment, not after the first floors appear.
First, confirm that every dated instalment goes only to the escrow account registered for project 3785 at Mashreq Bank PSC; the Bay Grove Residences Phase 4 escrow account page sets out how to verify it against the DLD record.
Second, if residency matters to your purchase, check your tier in the Bay Grove Residences Phase 4 Golden Visa guide, since the 1 bedroom tier is priced under the threshold while the 2, 3 and 4 bedroom tiers start above it.
Third, read the July 2026 construction update for Bay Grove Residences Phase 4 for the full inspection cycle behind the 0.04% register reading, then return here when the register posts a second dated figure and a real interval can be measured.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore Island B Structure
Phase 4 closes out a Bay Grove community planned across earlier releases on Island B, so its register record reads best next to the community, the island and the developer. These three pages supply that context:

Island B: Seven Waterfront Projects by Nakheel, Ellington and Beyond
Island B, on the eastern side of Dubai Islands, is a villa and beachfront residence district with seven projects for sale.
See Island B Properties for Sale
Island B Community Overview
Discover Island B within Dubai Islands, featuring waterfront residences, beach access, hospitality destinations, promenades, and planned lifestyle infrastructure by Nakheel.
Explore the Island B Community
Nakheel: The Master Developer of Dubai's Island Living and Reclaimed Coastline
Founded in 2003, Nakheel created Palm Jumeirah and Dubai Islands, adding over 300 kilometers of coastline and building complete waterfront communities.
View the Nakheel Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
Bay Grove Residences Phase 4 Construction Updates Frequently Asked Questions
Bay Grove Residences Phase 4 is at the mobilisation stage: the DLD register recorded 0.04% for project 3785 on 24 July 2026, and the RERA inspection notes of that date describe mobilisation in progress and no construction activity begun on the plot. The project status in the register is Active, and every dated entry is laid out in the register timeline above.
One dated reading so far: 0.04% in the DLD register on 24 July 2026, which sits 0.04 points above a previous inspection figure of 0% that the register leaves undated. With only one reading carrying a date, the Bay Grove Residences Phase 4 record has no measured interval yet, and the pace analysis above shows why no rate is given.
Two dates are on record: the registered completion date in the DLD register for project 3785 is 15 September 2028, and handover of Bay Grove Residences Phase 4 is scheduled for June 2029, which is also the estimated construction completion printed on the published payment plan. Both are shown here as recorded, next to the latest register reading of 0.04% on 24 July 2026, and this page is updated when a newer reading is posted.
Bay Grove Residences Phase 4 comprises 257 residences in four buildings, BG 12 (B+G+13+R), BG 13 (B+G+17+R), BG 14 (B+G+20+R) and BG 15 (B+G+04+R), set over one combined basement and one combined ground level, as described in the RERA inspection report of 24 July 2026. The DLD register lists the same 257 units for project 3785.
Bay Grove Residences Phase 4 is DLD project 3785, recorded under the register name Bay Grove Residences D - Dubai Islands on plot 3029, registered on 20 June 2025 and listed with status Active. The Dubai REST app entry under that number is the source of every percentage on this page, including the 0.04% of 24 July 2026.
Two sources dated 24 July 2026 make up the Bay Grove Residences Phase 4 record: the DLD project register, which supplies the 0.04% reading and the undated 0% previous figure, and the RERA Independent Progress Monitoring Report, which gives the status Pre-Construction, Progressing and the site notes but prints no percentage. Every percentage on this page is therefore the register figure, never the report.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the Bay Grove Residences Phase 4 construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.