Peninsula Four Construction Update - February 2025
February 2025 Inspection Confirms Peninsula Four Reaches 50.21% Construction Progress in Business Bay
Superstructure, exterior envelope, and MEP installation now drive site activity at Peninsula Four, verified at 50.21 percent in the February 2025 RERA inspection cycle.
Direct advisor access. Every message answered personally, never by a call center.
Verified DLD Inspection Data
Peninsula Four Construction Snapshot
A 44.28 point rise since the June 2023 inspection brought Peninsula Four to the envelope and MEP stage by February 2025, the mid plan point where escrow verification and milestone mapping matter most.
Peninsula Four The Plaza
2461
Active
50.21%
21 February 2025
01 October 2022
1,025 residential units
114,514.32 sq m
01 February 2026
Data source: RERA inspection conducted on 21 February 2025, tracked against DLD inspection records. Construction tracking against RERA inspection data runs across the full tohidfetrat.com project portfolio and is reviewed after every published cycle. Last updated: July 2026.
This page records the February 2025 cycle. Peninsula Four has since advanced to 95.59% at the 15 April 2026 inspection and is approaching handover. Message me on WhatsApp for the current status and the newer inspection readings.
This Inspection Cycle
Peninsula Four Construction Progress Summary
Between the June 2023 and February 2025 inspections, Peninsula Four moved from 5.93% to 50.21%, a 44.28 point gain that carried the two 52 storey waterfront towers from early piling through the structural build and into exterior envelope and MEP works. By this reading, site activity had shifted from raising the towers to enclosing and servicing them.
- Enabling, piling, and foundation works across the Dubai Canal plot
- Podium infrastructure connecting the two waterfront towers
- Structural superstructure on the lower and middle tower floors
- Superstructure and floor plate framing on the upper levels
- Exterior envelope and facade packages on the canal frontage
- MEP first fix: mechanical, electrical, and plumbing rough in
- Early interior works across the 1,025 residential units
- Full structural topping and envelope close on both towers
- Interior finishes, amenities, and waterfront landscaping
- Remaining RERA cycles toward 100% and completion certification
Payment Linked Progress
What 50.21% Progress Means for Peninsula Four Buyers
Most Dubai off plan payment plans tie installments to construction milestones or to handover, so a verified reading of 50.21% is more than a status line: it signals which obligations and protections apply next. At the mid plan stage Peninsula Four had reached by February 2025, four actions mattered most.
Verify the escrow account
Any installment drawn against a construction milestone should reach only the DLD regulated escrow account registered for project 2461. Peninsula Four escrow account verification is the step before any transfer; the lookup takes about two minutes against the official DLD project record.
Reread your SPA milestone schedule
Check how your sale and purchase agreement links installments to construction stages and to the recorded completion date. Not sure how your installments map to this reading? Send me your SPA schedule and I will map it against the certified milestones.
Plan the snagging window early
Snagging is not yet due at 50.21%, but the pre handover inspection window opens once a project passes roughly 70%. The Peninsula Four snagging inspection guide is worth reading now so booking is ready when the window opens.
Track the remaining inspection cycles
Several inspection readings still separated this cycle from completion. The Peninsula Four construction updates hub keeps the path to handover free of surprises.
General framework, not legal advice: milestone definitions, notice periods, and fee obligations are set by your individual SPA and the DLD record, and both should be read directly.
Considering Peninsula Four Now?
This page documents the February 2025 cycle, but Peninsula Four has since reached 95.59% at the April 2026 inspection and is approaching handover. For a buyer today, that shifts the trade off from construction runway to certainty, with only a small pool of units still available. Every payment still goes to the DLD-registered escrow account for project 2461, released against certified construction progress.
- Certified structure: 95.59% recorded at the April 2026 inspection
- Minimal construction wait to the Q3 2026 handover window
- The 40% completion tranche due near delivery, not spread over years
- Construction risk carried from excavation to handover
- Two to four years of waiting is the usual delivery horizon
- Longer installment runway, priced at launch levels
02 units listed available on the project page as of this update; availability shifts between cycles.
About the Development
Peninsula Four Project Details

At the February 2025 inspection, Peninsula Four stood at 50.21%, its two 52-storey towers mid-build with envelope and MEP works advancing across 1,025 canal-facing residential units. Starting prices: AED 1.30M ≈ USD 353K.
The project has since advanced to near completion, with handover expected in Q3 2026 per the current DLD record; the 01 February 2026 date recorded at this inspection has passed. Entering now trades payment plan runway for a short, certain delivery window.
Peninsula Four The Plaza Project GuideSite Context This Cycle
Explore Peninsula Four Location on Dubai Map
Peninsula Four rises on a Dubai Canal plot within the Peninsula master community in Business Bay, its two towers oriented toward the Downtown Dubai skyline, which shapes how finishing is sequenced: the exterior envelope and facade packages on the exposed canal frontage were among the most visible items in this inspection cycle.
Because Business Bay is an established district with completed roads, canal promenade, and utilities, Peninsula Four was rising into a functioning waterfront neighborhood rather than an emerging one, which mattered for buyers weighing rental or occupancy plans against the completion timeline. See the project's position on the interactive Dubai real estate map.

Buyer Resources for This Project
Investing in Peninsula Four During Mid Construction Progress
The mid plan stage is where residency planning, payment protection, and handover preparation start to converge. Each resource below is matched to where Peninsula Four stood at this reading.

Peninsula Four Construction Updates
This page: the verified February 2025 inspection record for Peninsula Four at the mid plan stage.
Peninsula Four Golden Visa
Check whether a qualifying Peninsula Four purchase supports 10 year UAE Golden Visa residency eligibility.
Read Peninsula Four Golden Visa Guide
Peninsula Four Escrow Account
Confirm the DLD registered escrow account for project 2461 before releasing any construction linked installment.
Verify Peninsula Four Escrow Account
Peninsula Four Snagging Inspection
At 50.21% the snagging window is still ahead; read the guide to prepare defect documentation early.
Book Peninsula Four SnaggingUpdate Timeline
Other Peninsula Four Construction Updates
Follow the full inspection history to see how Peninsula Four moved through each construction phase, reading by reading.
Where This Update Fits
Explore Peninsula Structure
This monthly report is one node in the wider record: the waterfront community around the site, the developer delivering it, and the listings competing with it.

Peninsula Waterfront Properties for Sale
Compare available Peninsula waterfront listings while Peninsula Four moves through its construction cycles toward handover.
Peninsula Waterfront Properties for Sale
About Business Bay Master Community
See how Business Bay canal frontage, roads, and retail maturity frame the Peninsula Four waterfront setting.
Business Bay Community Guide
Select Group Developer Profile
Review Select Group's delivery record across Dubai waterfront towers before your remaining payment decisions.
Select Group Developer ProfileFAQs
Peninsula Four Construction Progress in February 2025: Frequently Asked Questions
The RERA inspection conducted on 21 February 2025 recorded Peninsula Four at 50.21% construction progress in the DLD project register, up 44.28 points from the 5.93% logged at the June 2023 inspection.
Yes. Expected completion dates in the DLD project register can be revised between inspection cycles. The 01 February 2026 date recorded at this inspection has since passed, and the current project record shows handover expected in Q3 2026.
At the 50.21% reading, site activity centered on upper level superstructure framing, exterior envelope and facade packages on the canal frontage, MEP first fix, and early interior works across both towers.
It marked the mid plan stage where the during construction tranche of a typical Peninsula Four plan is drawn against milestones. The practical steps were to confirm the project 2461 escrow account before any transfer and to reread the SPA milestone schedule.
It is one point on the DLD verified path that runs from 5.93% in June 2023 to 95.59% in April 2026. The full inspection history is tracked on the Peninsula Four construction updates hub.
The project has since advanced to 95.59% at the 15 April 2026 inspection and is approaching handover. The 04 December 2025 reading of 88.45% is the cycle that immediately followed this one.
A Question the FAQ Can Not Answer?

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is helping you read the February 2025 inspection record for Peninsula Four correctly before your next payment decision. Client identities and transactions are never published or referenced. Message me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.