Peninsula Four The Plaza construction update February 2025 showing luxury residences with Burj Khalifa skyline views in Business Bay Dubai Presented by Tohid Fetrat

Select Group · Business Bay · Construction Update

Peninsula Four Construction Update - February 2025

February 2025 Inspection Confirms Peninsula Four Reaches 50.21% Construction Progress in Business Bay

Superstructure, exterior envelope, and MEP installation now drive site activity at Peninsula Four, verified at 50.21 percent in the February 2025 RERA inspection cycle.

Direct advisor access. Every message answered personally, never by a call center.

50.21%Construction Progress
21 February 2025Inspection Date
01 February 2026Anticipated Completion (Date Passed)
2461DLD Project Number

Verified DLD Inspection Data

Peninsula Four Construction Snapshot

A 44.28 point rise since the June 2023 inspection brought Peninsula Four to the envelope and MEP stage by February 2025, the mid plan point where escrow verification and milestone mapping matter most.

Project Name

Peninsula Four The Plaza

Project Number

2461

Project Status

Active

Construction Progress

50.21%

Inspection Date

21 February 2025

Construction Start

01 October 2022

Total Units

1,025 residential units

Total Built Area

114,514.32 sq m

Anticipated Completion

01 February 2026

Data source: RERA inspection conducted on 21 February 2025, tracked against DLD inspection records. Construction tracking against RERA inspection data runs across the full tohidfetrat.com project portfolio and is reviewed after every published cycle. Last updated: July 2026.

This page records the February 2025 cycle. Peninsula Four has since advanced to 95.59% at the 15 April 2026 inspection and is approaching handover. Message me on WhatsApp for the current status and the newer inspection readings.

This Inspection Cycle

Peninsula Four Construction Progress Summary

Between the June 2023 and February 2025 inspections, Peninsula Four moved from 5.93% to 50.21%, a 44.28 point gain that carried the two 52 storey waterfront towers from early piling through the structural build and into exterior envelope and MEP works. By this reading, site activity had shifted from raising the towers to enclosing and servicing them.

Completed
  • Enabling, piling, and foundation works across the Dubai Canal plot
  • Podium infrastructure connecting the two waterfront towers
  • Structural superstructure on the lower and middle tower floors
In Progress at 50.21%
  • Superstructure and floor plate framing on the upper levels
  • Exterior envelope and facade packages on the canal frontage
  • MEP first fix: mechanical, electrical, and plumbing rough in
  • Early interior works across the 1,025 residential units
Ahead of Handover
  • Full structural topping and envelope close on both towers
  • Interior finishes, amenities, and waterfront landscaping
  • Remaining RERA cycles toward 100% and completion certification
Next inspectionThe following published reading recorded 88.45% on 04 December 2025; view the December 2025 update for that cycle.
Completion target01 February 2026 per the DLD record at this inspection. That date has since passed; the current project record shows handover expected in Q3 2026.
Remaining distance49.79 percentage points separated the February 2025 reading from full completion certification.

Payment Linked Progress

What 50.21% Progress Means for Peninsula Four Buyers

Most Dubai off plan payment plans tie installments to construction milestones or to handover, so a verified reading of 50.21% is more than a status line: it signals which obligations and protections apply next. At the mid plan stage Peninsula Four had reached by February 2025, four actions mattered most.

Before Construction Linked Installments

Verify the escrow account

Any installment drawn against a construction milestone should reach only the DLD regulated escrow account registered for project 2461. Peninsula Four escrow account verification is the step before any transfer; the lookup takes about two minutes against the official DLD project record.

Before the Next Milestone Draw

Reread your SPA milestone schedule

Check how your sale and purchase agreement links installments to construction stages and to the recorded completion date. Not sure how your installments map to this reading? Send me your SPA schedule and I will map it against the certified milestones.

Later, Past 70%

Plan the snagging window early

Snagging is not yet due at 50.21%, but the pre handover inspection window opens once a project passes roughly 70%. The Peninsula Four snagging inspection guide is worth reading now so booking is ready when the window opens.

Every Cycle

Track the remaining inspection cycles

Several inspection readings still separated this cycle from completion. The Peninsula Four construction updates hub keeps the path to handover free of surprises.

General framework, not legal advice: milestone definitions, notice periods, and fee obligations are set by your individual SPA and the DLD record, and both should be read directly.

Considering Peninsula Four Now?

This page documents the February 2025 cycle, but Peninsula Four has since reached 95.59% at the April 2026 inspection and is approaching handover. For a buyer today, that shifts the trade off from construction runway to certainty, with only a small pool of units still available. Every payment still goes to the DLD-registered escrow account for project 2461, released against certified construction progress.

Entering Now Near Handover
  • Certified structure: 95.59% recorded at the April 2026 inspection
  • Minimal construction wait to the Q3 2026 handover window
  • The 40% completion tranche due near delivery, not spread over years
Typical Launch Entry
  • Construction risk carried from excavation to handover
  • Two to four years of waiting is the usual delivery horizon
  • Longer installment runway, priced at launch levels
AED 1.30M ≈ USD 353KStarting Price
20/40/40 Plan40% Due on Completion
Q3 2026Expected Handover
Ask What Is Available at Peninsula Four

02 units listed available on the project page as of this update; availability shifts between cycles.

About the Development

Peninsula Four Project Details

Peninsula Four The Plaza by Select Group waterfront towers with Burj Khalifa skyline views along Dubai Canal in Business Bay Dubai Presented by Tohid Fetrat
Business Bay · Select Group

At the February 2025 inspection, Peninsula Four stood at 50.21%, its two 52-storey towers mid-build with envelope and MEP works advancing across 1,025 canal-facing residential units. Starting prices: AED 1.30M ≈ USD 353K.

The project has since advanced to near completion, with handover expected in Q3 2026 per the current DLD record; the 01 February 2026 date recorded at this inspection has passed. Entering now trades payment plan runway for a short, certain delivery window.

Peninsula Four The Plaza Project Guide

Site Context This Cycle

Explore Peninsula Four Location on Dubai Map

Peninsula Four rises on a Dubai Canal plot within the Peninsula master community in Business Bay, its two towers oriented toward the Downtown Dubai skyline, which shapes how finishing is sequenced: the exterior envelope and facade packages on the exposed canal frontage were among the most visible items in this inspection cycle.

Because Business Bay is an established district with completed roads, canal promenade, and utilities, Peninsula Four was rising into a functioning waterfront neighborhood rather than an emerging one, which mattered for buyers weighing rental or occupancy plans against the completion timeline. See the project's position on the interactive Dubai real estate map.

Interactive Dubai real estate map preview
Click to view Peninsula Four The Plaza on Dubai Map

Buyer Resources for This Project

Investing in Peninsula Four During Mid Construction Progress

The mid plan stage is where residency planning, payment protection, and handover preparation start to converge. Each resource below is matched to where Peninsula Four stood at this reading.

Peninsula Four The Plaza tower view in Business Bay Dubai showing completed exterior architecture and landscaped surroundings during the June 2026 construction update Captured by Tohid Fetrat
You Are Here

Peninsula Four Construction Updates

This page: the verified February 2025 inspection record for Peninsula Four at the mid plan stage.

Peninsula Four The Plaza in Business Bay Dubai with UAE Golden Visa investment concept Presented by Tohid Fetrat

Peninsula Four Golden Visa

Check whether a qualifying Peninsula Four purchase supports 10 year UAE Golden Visa residency eligibility.

Read Peninsula Four Golden Visa Guide
Peninsula Four The Plaza escrow account and secure Dubai property investment concept in Business Bay Presented by Tohid Fetrat

Peninsula Four Escrow Account

Confirm the DLD registered escrow account for project 2461 before releasing any construction linked installment.

Verify Peninsula Four Escrow Account
Peninsula Four Why Snagging Matters at This Stage showing residential towers and landscaped podium during inspection on 19 June 2026 in Dubai Captured by Tohid Fetrat

Peninsula Four Snagging Inspection

At 50.21% the snagging window is still ahead; read the guide to prepare defect documentation early.

Book Peninsula Four Snagging

Update Timeline

Other Peninsula Four Construction Updates

Follow the full inspection history to see how Peninsula Four moved through each construction phase, reading by reading.

All Peninsula Four Construction Updates

FAQs

Peninsula Four Construction Progress in February 2025: Frequently Asked Questions

The RERA inspection conducted on 21 February 2025 recorded Peninsula Four at 50.21% construction progress in the DLD project register, up 44.28 points from the 5.93% logged at the June 2023 inspection.

Yes. Expected completion dates in the DLD project register can be revised between inspection cycles. The 01 February 2026 date recorded at this inspection has since passed, and the current project record shows handover expected in Q3 2026.

At the 50.21% reading, site activity centered on upper level superstructure framing, exterior envelope and facade packages on the canal frontage, MEP first fix, and early interior works across both towers.

It marked the mid plan stage where the during construction tranche of a typical Peninsula Four plan is drawn against milestones. The practical steps were to confirm the project 2461 escrow account before any transfer and to reread the SPA milestone schedule.

It is one point on the DLD verified path that runs from 5.93% in June 2023 to 95.59% in April 2026. The full inspection history is tracked on the Peninsula Four construction updates hub.

The project has since advanced to 95.59% at the 15 April 2026 inspection and is approaching handover. The 04 December 2025 reading of 88.45% is the cycle that immediately followed this one.

A Question the FAQ Can Not Answer?

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is helping you read the February 2025 inspection record for Peninsula Four correctly before your next payment decision. Client identities and transactions are never published or referenced. Message me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

Get Progress Alerts