Peninsula Four Construction Update - June 2023

June 2023 Inspection Confirms Peninsula Four Reaches 5.93% Construction Progress in Business Bay

Enabling works, piling, and site mobilization dominate activity at Peninsula Four, verified at 5.93 percent in the June 2023 RERA inspection on the Business Bay canal front.

Direct advisor access. Every message answered personally, never by a call center.

5.93%Construction Progress
19 June 2023Inspection Date
01 February 2026Expected Completion
2461DLD Project Number

Verified DLD Inspection Data

Peninsula Four Construction Snapshot

The first verified inspection since the October 2022 construction start records Peninsula Four at 5.93%, placing it in the early enabling and foundations band where escrow protection and payment structure matter most for buyers.

Project Name

Peninsula Four The Plaza

Project Number

2461

Project Status

Active

Construction Progress

5.93%

Inspection Date

19 June 2023

Construction Start

01 October 2022

Total Units

1,025 residential units

Total Built Area

114,514.32 sq m

Expected Completion

01 February 2026

Data source: RERA inspection conducted on 19 June 2023, tracked against DLD inspection records. Construction tracking against RERA inspection data runs across the full tohidfetrat.com project portfolio and is reviewed after every published cycle. Last updated: July 2026.

Want each new reading the day it publishes? Message me on WhatsApp and I will send it to you directly: one message per inspection cycle, nothing else.

This Inspection Cycle

Peninsula Four Construction Progress Summary

At the 19 June 2023 inspection, Peninsula Four moved from 0% to 5.93%, the first verified reading since construction began on 01 October 2022. Activity is concentrated in enabling, piling, and site preparation across the Business Bay waterfront plot rather than in any vertical structure yet.

Completed
  • Project registration and construction start recorded 01 October 2022
  • DLD escrow account activation for project 2461
  • Site mobilization across the Business Bay canal front plot
In Progress at 5.93%
  • Enabling and piling operations on the waterfront plot
  • Excavation and early foundation preparation
  • Site preparation supporting the next structural phase
Ahead of Handover
  • Tower superstructure and podium infrastructure
  • MEP, facade, and interior finishing across the 1,025 residential units
  • Canal facing landscaping, then remaining RERA cycles to 100%
Next inspectionThe next verified reading, February 2025, recorded 50.21%; the full inspection cadence is tracked on the hub.
Completion target01 February 2026 was the DLD register date at this inspection; that date has since passed and later hub cycles show construction continuing beyond it.
Remaining distance94.07 percentage points separated the June 2023 reading from 100% handover readiness.

Payment Linked Progress

What 5.93% Progress Means for Peninsula Four Buyers

Most Dubai off plan payment plans tie early installments to registration and construction milestones, so a verified reading of 5.93% is not just a status update: it marks the stage where escrow protection and your payment structure matter most. At this early point in Peninsula Four, four actions matter.

Before Any Early Installment

Verify the escrow account

Any early installment should go only to the DLD regulated escrow account registered for project 2461. Peninsula Four escrow account verification is the step before any transfer; the lookup itself takes about two minutes against the official DLD project record.

At Booking and Oqood

Map your payment schedule and Oqood

Confirm how your sale and purchase agreement ties early installments to registration and construction milestones, and that your Oqood is registered against the unit. Not sure how your installments map to this early reading? Send me your payment schedule and I will map it against the certified milestones.

Later, Near Handover

Plan the snagging inspection ahead

Snagging comes much later than 5.93%, but knowing the process early avoids a rushed handover. The Peninsula Four snagging inspection guide covers the defect documentation you will arrange before you accept the unit.

Every Cycle

Track the remaining cycles

Many inspection readings remain between 5.93% and completion certification. The Peninsula Four construction updates hub keeps the full stretch to handover free of surprises.

General framework, not legal advice: milestone definitions, notice periods, and fee obligations are set by your individual SPA and the DLD record, and both should be read directly.

Considering Peninsula Four The Plaza?

In June 2023 Peninsula Four was at its earliest verified stage, 5.93% recorded, carrying the longest payment runway this project would offer. Every payment goes to the DLD-registered escrow account for project 2461, released against certified construction progress. The project has since advanced through later inspection cycles tracked on the hub.

Entering at 5.93% in June 2023
  • Longest installment runway, spread across the full build
  • Escrow-protected payments tied to certified milestones
  • Construction risk carried from foundations through to handover
Late-Stage Entry
  • Short runway: most of the price due near completion
  • Structure already certified, little build risk remaining
  • Priced at later-cycle levels rather than launch
5.93% · June 2023Recorded Progress
01 October 2022Construction Start
1,025 ResidencesTotal in the Project
Ask About Peninsula Four Options

Pricing and availability shift across construction cycles; message me for the current picture on Peninsula Four.

About the Development

Peninsula Four The Plaza Project Details

Peninsula Four The Plaza by Select Group waterfront towers with Burj Khalifa skyline views along Dubai Canal in Business Bay Dubai Presented by Tohid Fetrat
Business Bay · Select Group

At 5.93% in June 2023, Peninsula Four The Plaza was a waterfront development still in enabling and piling, planned with 1,025 residential units across apartments, duplex lofts, and penthouses on the Business Bay canal front within Select Group's Peninsula master community.

For buyers entering at this early stage, the trade off is the longest payment runway on the plan against a full construction cycle still ahead, with the DLD register at this inspection showing an expected completion of 01 February 2026, a date since passed.

Peninsula Four The Plaza Project Guide

Site Context This Cycle

Explore Peninsula Four Location on Dubai Map

Peninsula Four rises on a canal facing plot within the Peninsula master community in Business Bay, its towers oriented toward the Dubai Canal and the Downtown skyline. At 5.93% in June 2023, that position shapes the cycle directly: enabling and piling on the waterfront plot are the first items an inspection can verify.

Because Business Bay is an established district with completed roads, the canal promenade, and mature utility infrastructure, Peninsula Four is being built into a functioning waterfront neighborhood rather than an emerging one, which matters for buyers weighing the long payment runway that early stage entry implies. See the project's position on the interactive Dubai real estate map.

Interactive Dubai real estate map preview
Click to view Peninsula Four The Plaza on Dubai Map

Buyer Resources for This Project

Investing in Peninsula Four During Early Construction Progress

The early construction band is where residency planning, payment protection, and escrow verification converge. Each resource below is matched to where Peninsula Four stood in June 2023.

Peninsula Four The Plaza tower view in Business Bay Dubai showing completed exterior architecture and landscaped surroundings during the June 2026 construction update Captured by Tohid Fetrat
You Are Here

Peninsula Four Construction Updates

This page: the verified 19 June 2023 inspection record for Peninsula Four, its first construction reading.

Peninsula Four The Plaza in Business Bay Dubai with UAE Golden Visa investment concept Presented by Tohid Fetrat

Peninsula Four Golden Visa

Check whether a qualifying Peninsula Four purchase could support ten-year UAE Golden Visa residency eligibility.

Read Peninsula Four Golden Visa Guide
Peninsula Four The Plaza escrow account and secure Dubai property investment concept in Business Bay Presented by Tohid Fetrat

Peninsula Four Escrow Account

Confirm the DLD-registered escrow account for project 2461 before releasing any early-stage installment payments.

Verify Peninsula Four Escrow Account
Peninsula Four Why Snagging Matters at This Stage showing residential towers and landscaped podium during inspection on 19 June 2026 in Dubai Captured by Tohid Fetrat

Peninsula Four Snagging Inspection

At 5.93% early progress, understand the snagging inspection you will schedule before eventual Peninsula Four handover.

Book Peninsula Four Snagging

Update Timeline

Other Peninsula Four Construction Updates

Follow the full inspection history to see how Peninsula Four moved from this first reading through each construction phase, cycle by cycle.

All Peninsula Four Construction Updates

FAQs

Peninsula Four Construction Progress in June 2023: Frequently Asked Questions

As of the RERA inspection conducted on 19 June 2023, Peninsula Four stood at 5.93% construction progress in the DLD project register, its first recorded reading.

The June 2023 inspection recorded Peninsula Four advancing from 0% to 5.93% since construction began on 01 October 2022, with enabling and piling works underway on the Business Bay canal front plot.

The DLD project register listed 01 February 2026 as the expected completion date at the June 2023 inspection. That date has since passed; later inspection cycles on the Peninsula Four construction updates hub record construction continuing beyond it.

Yes. Expected completion dates in the DLD register can be revised between cycles, and in this case the 01 February 2026 figure was later overtaken as construction continued through 2025 and 2026.

At the 19 June 2023 inspection, activity centered on enabling works, piling operations, excavation, and site preparation across the Business Bay waterfront plot, ahead of vertical tower construction.

At this early band, the priorities were confirming the DLD-registered escrow account for project 2461, verifying Oqood registration, and understanding a payment plan whose installments were tied to construction milestones still largely ahead.

A Question the FAQ Can Not Answer?

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is helping you read the June 2023 inspection record for Peninsula Four correctly before your next payment decision. Client identities and transactions are never published or referenced. Message me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

Get Progress Alerts