
Emaar Properties · Grand Polo Club & Resort
Selvara 3 at Grand Polo Construction Updates
The Inspection Record for 138 G+2 Villas Beside the Grand Polo Green Core
Selvara 3 read 2.98% at the 6 May 2026 RERA inspection, opening a record that will follow 138 Grand Polo villas from infrastructure works to handover.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
Selvara 3 at Grand Polo at a Glance
Selvara 3 is Emaar Properties' collection of 138 four bedroom villas on plot 4660 in Dubai Investment Park Second, following Selvara and Selvara 2 inside the Grand Polo Club & Resort masterplan and within reach of the Green Core, where the polo fields, Clubhouse and Stables sit. The DLD register logged the project on 15 July 2025 and its construction start on 2 November 2025, and the six figures below are the anchors every later reading on this page is measured against. Because all 138 homes repeat one G+2 villa type, each percentage in this record describes a single building form multiplied across the plot rather than a mix of formats moving at different speeds.
3866
Active
2 November 2025
138 villas
47,672.31 sq m
31 May 2029 (DLD)
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
Selvara 3 at Grand Polo Construction Update Timeline
The Selvara 3 record holds one dated reading so far: 2.98% at the 6 May 2026 inspection, 185 days after the 2 November 2025 start. The same DLD entry carries a Previous Inspection figure of 1.23% with no date attached, so it appears on the track below as an unlabelled marker rather than a month, and the table lists only the dated May 2026 reading with its full monthly update.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| May 2026 | 2.98% | 6 May 2026 | View the May 2026 update |
Pace Analysis
How Fast Selvara 3 at Grand Polo Has Been Built
With a single dated inspection on file, Selvara 3 has no measured pace yet. What its record does support is three plain calculations, each labelled for exactly what it is:
- 2 Nov 2025 start to 6 May 2026: enabling and infrastructure works, 0% to 2.98% over 185 days (arithmetic average, not a measured pace)About 0.49 points per month
- Undated Previous Inspection to 6 May 2026: 1.23% to 2.98% (no interval in the register, so no monthly rate)Plus 1.75 points
- 6 May 2026 to 31 May 2029 registered completion: 2.98% to 100% over 1,121 days (arithmetic requirement, not a forecast)About 2.6 points per month
Read together, those three lines describe a starting position, not a curve. The 1.75 point gain up to the 6 May 2026 inspection is real, but with no date on the earlier 1.23% figure it cannot be turned into a velocity, so this page does not publish one. The two averages frame the task instead: 2.98 points logged in the first 185 days after the 2 November 2025 start, against 97.02 points still to be recorded before 31 May 2029. That gap is ordinary for a plot where the monitoring report still describes infrastructure works, and it says nothing yet about whether Emaar is ahead of or behind the registered date. An end user should read it as a long runway to a May 2029 handover; an investor should wait for the second dated inspection, the first point at which the 138-villa record can show a measured pace at all.
Get the Next Inspection Figure First
Tell me you are tracking Selvara 3 at Grand Polo and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About Selvara 3 at Grand Polo at Grand Polo Dubai
The 2.98% reading of 6 May 2026 means more once you know what the remaining 97.02 points are meant to deliver. The project guide sets out the finished villas this record is tracking toward:

Selvara 3 at Grand Polo: G+2 Villas Near the Clubhouse and Stables
Selvara 3 at Grand Polo is an Emaar phase of 138 four bedroom villas, each built ground plus two.
View the Selvara 3 at Grand Polo Project GuideConsidering an Entry at Enabling Works?
Selvara 3 is listed as EOI Registration Open at this update, and the choice of villas shifts from one release cycle to the next. If the record on this page is what brought you here, ask me what is available now before you settle on a plot.
Ask About Remaining Availability on WhatsAppStage Record
Selvara 3 at Grand Polo Build Stages, Mapped to the Inspections
Selvara 3 has entered only the second of the five stages below, reading 2.98% on 6 May 2026, so this record mixes windows the DLD register has already dated with windows the launch payment plan only estimates. Every estimated window is marked as the plan's own estimate and will be replaced with inspection dates as readings are published.
Registration and Construction Start
Registered with the DLD as project 3866 on 15 July 2025, with the register's construction start following on 2 November 2025 for the 138-villa plot in Dubai Investment Park Second.
Enabling and Infrastructure Works
The Independent Progress Monitoring Report for 6 May 2026 gives the status as enabling works progressing, with the note "At the time of inspection found infra works are progressing." Across this stage the register moved from an undated 1.23% to 2.98%.
Foundations and Villa Structures
Not yet in the record. The launch payment plan ties its fourth instalment to 30% construction completion and estimates that milestone for March 2027; the inspection that actually records it will replace the estimate here.
Facades, Roof Lounges, and External Works
The plan links instalments to 50%, 70%, and 90% completion, estimated for August 2027, January 2028, and July 2028: the window covering the three levels of each G+2 villa up to its second-floor roof lounge and terrace.
Completion and Handover
The final 20% instalment is linked to 100% completion, estimated for May 2029, coinciding with the Selvara 3 handover month and the 31 May 2029 completion date registered for project 3866.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Selvara 3 at Grand Polo's own record.
Buyer Position
Tracking Your Position at Selvara 3 at Grand Polo
This page is one of four project resources that together cover a Selvara 3 at Grand Polo purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Selvara 3 at Grand Polo Construction Updates
This page: the Selvara 3 inspection record, tracked from the November 2025 start to handover.

Selvara 3 at Grand Polo Golden Visa: 138 Villas, One Typology
All 138 villas at Selvara 3 at Grand Polo share one 4 bedroom typology, so each Emaar villa qualifies individually.
Read the Selvara 3 at Grand Polo Golden Visa Guide
Selvara 3 at Grand Polo: The Third Selvara Escrow Account
Selvara 3 at Grand Polo escrows 138 units at Abu Dhabi Commercial Bank under DLD project 3866, certified 2.98% May 2026.
Verify the Selvara 3 at Grand Polo Escrow AccountApproaching Handover
Between 2.98% and Handover: What Selvara 3 at Grand Polo Buyers Should Do Now
At 2.98% on 6 May 2026, Selvara 3 sits ahead of every construction-linked instalment: the three dated instalments of the launch schedule fell in October 2025, March 2026, and August 2026, and the fourth waits on 30% construction completion, pencilled in by the plan for March 2027. The paperwork behind that trigger is far easier to settle while the site is still at infrastructure works than in the weeks after the register records it, so the three steps below belong in this window.
First, confirm that every payment you have made or will make lands in the account registered for project 3866; the Selvara 3 escrow account page shows how to check it against the DLD record.
Second, read how your SPA words the 30%, 50%, 70%, 90%, and 100% construction triggers, because the plan's calendar dates for them are estimates and the recorded percentage is what moves each payment.
Third, follow the Selvara 3 inspection timeline as each new reading is added, since the second dated inspection is the first that will show how quickly the 138 villas are moving toward that 30% trigger.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore Grand Polo Dubai Structure
A 138-villa build record reads differently once you see the masterplan it sits in. These three pages place the Selvara 3 inspection record in its market, community, and developer context:

Grand Polo Dubai Properties for Sale
Browse villas and townhouses for sale at Grand Polo Club & Resort, comparing Equiterra, Selvara and Chevalia.
See Grand Polo Dubai Properties for Sale
Grand Polo Dubai Community Overview
Read the Grand Polo Club & Resort guide: Emaar's 60 million sq ft equestrian estate community of villas and townhouses.
Explore the Grand Polo Dubai Community
Emaar Properties: Burj Khalifa, Downtown Dubai and Twenty Master Communities
Emaar, founded in 1997, built Burj Khalifa and Downtown Dubai and has delivered over 85,000 homes across twenty master communities.
View the Emaar Properties Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
Selvara 3 at Grand Polo Construction Updates Frequently Asked Questions
Selvara 3 at Grand Polo Club & Resort is an active DLD project (number 3866) in its enabling and infrastructure stage, read at 2.98% in the DLD register after the RERA inspection of 6 May 2026. Both of its readings are set out in the Selvara 3 inspection record above.
The 6 May 2026 inspection put Selvara 3 at 2.98% in the DLD register, 1.75 points above the 1.23% shown as the Previous Inspection figure, which the register lists without a date. The cycle is documented in the Selvara 3 May 2026 construction update.
The DLD register gives 31 May 2029 as the completion date for project 3866, a date that lines up with the May 2029 handover and with the final 20% instalment of the launch plan. That date has not passed; with 97.02 points left after the 2.98% reading of 6 May 2026, plain arithmetic puts the required rate at about 2.6 points per month over the remaining 1,121 days, and this page's record is updated as each new inspection is published.
Selvara 3 includes 138 villas under DLD project 3866, with a total built area of 47,672.31 sq m recorded in the register. All 138 are four bedroom villas of the same G+2 type, so the whole figure is spread across one repeated building design on plot 4660.
Construction at Selvara 3 began on 2 November 2025 according to the DLD register, 110 days after the project was registered on 15 July 2025. The first dated reading came 185 days after that start, at the 6 May 2026 inspection, which recorded 2.98%.
Each of the 138 Selvara 3 villas is recorded as G+2, a ground floor plus two upper floors, with a roof lounge and terrace crowning the top level. None of those levels had entered the construction record by the 6 May 2026 inspection at 2.98%, when the monitoring report still described infrastructure works on the plot.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the Selvara 3 at Grand Polo construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.