Selvara 4 at Grand Polo Club & Resort by Emaar Properties contemporary villa exterior with construction updates visual in Dubai. Presented by Tohid Fetrat

Emaar Properties · Grand Polo Club & Resort

Selvara 4 at Grand Polo Construction Updates

Tracking 173 Three-Level Villas From Enabling Works Near the Grand Polo Green Core

Selvara 4 recorded 2.88% at its 06 May 2026 RERA inspection, an opening reading that shows enabling and infrastructure works preparing plot 4349 for 173 villas.

Construction tracking against RERA inspection data, updated after every recorded inspection.

Direct advisor access. Every message answered personally, never by a call center.

2.88%Construction Progress
06 May 2026Latest RERA Inspection
173 villas (G+2)Total Units
Project 3875DLD Registration

Construction Snapshot

Selvara 4 at Grand Polo at a Glance

Selvara 4, numbered 12 on Emaar's Grand Polo Club & Resort masterplan, is a cluster of 173 four bedroom villas on plot 4349 in Dubai Investment Park Second, registered with the DLD as project 3875 on 21 July 2025. Construction started on 02 November 2025, and the 06 May 2026 inspection placed the cluster at 2.88% with enabling works progressing. Because every home here repeats one three-level (G+2) villa typology, the record ahead will measure 173 villas advancing side by side rather than a single building rising in stages, which is why these first readings speak to ground and infrastructure before anything else.

DLD Project Number

3875

Project Status

Active

Construction Start

02 November 2025

Total Units

173 villas (G+2)

Total Built-Up Area

56,180.97 sq m

Registered Completion Date

31 May 2029 (DLD)

Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.

Inspection Record

Selvara 4 at Grand Polo Construction Update Timeline

The DLD register holds two Selvara 4 readings so far: 1.23% at a previous inspection that the register leaves undated, and 2.88% at the 06 May 2026 inspection, a spread of 1.65 points that sits entirely within enabling and infrastructure works. With both dots within three points of the start of the track, only the dated May 2026 reading carries a label; the table lists both, and the May 2026 row links the full monthly update for this cluster.

Inspection MonthConstruction ProgressInspection DateFull Update
May 20262.88%06 May 2026View the May 2026 update

Pace Analysis

How Fast Selvara 4 at Grand Polo Has Been Built

The Selvara 4 register holds two readings, but only one of them carries a date, and that decides what can honestly be said about pace at this point:

  • Previous Inspection (undated) to 06 May 2026: enabling works, 1.23% to 2.88%+1.65 points recorded
  • 06 May 2026 to Handover 100%, with DLD completion on 31 May 202997.12 points still to record

Because the 1.23% reading has no inspection date in the register, the 1.65-point step cannot be divided into a monthly rate, and this page does not estimate one. What the record does fix is the timing around the dated reading: construction started on 02 November 2025, the 06 May 2026 inspection came about six months later at 2.88%, and the status for that visit was enabling works, progressing. At this stage the percentage reflects ground preparation and infrastructure across plot 4349 rather than any of the 173 villas, so the first pace figure worth reading will come from the next dated inspection measured against 06 May 2026. For an end user, that is the reading likely to show villa construction beginning; for an investor, it is the first real input for comparing Selvara 4 with the other Grand Polo clusters on this site.

Get the Next Inspection Figure First

Tell me you are tracking Selvara 4 at Grand Polo and I will send you the next recorded figure and site photos directly, ahead of the page update.

Get the Next Update on WhatsApp

Project Profile

About Selvara 4 at Grand Polo at Grand Polo Dubai

The 2.88% recorded on 06 May 2026 only means something next to what it is building toward. The full project guide covers the villas this record will follow from enabling works to handover:

Selvara 4 at Grand Polo Club and Resort by Emaar, a modern luxury villa exterior with landscaped garden and covered parking in Dubai. Presented by Tohid Fetrat.

Selvara 4 at Grand Polo: Three-Level Villas by the Green Core

Selvara 4 at Grand Polo is a cluster of 173 four bedroom Emaar villas near the polo fields, clubhouse and stables.

View the Selvara 4 at Grand Polo Project Guide

Considering an Early-Construction Entry?

Selvara 4 is offered in a limited release, with availability on request, and the villas on offer shift from one release to the next. If the record on this page is what brought you here, ask me for current availability before choosing your next step.

Ask About Remaining Availability on WhatsApp

Stage Record

Selvara 4 at Grand Polo Build Stages, Mapped to the Inspections

Each stage below is tied to a date the Selvara 4 record actually contains, from the 21 July 2025 registration to the 31 May 2029 completion, with the stages still ahead anchored to the construction triggers and estimated dates in Emaar's payment plan of record.

Jul 2025 to Nov 2025

Registration and Site Activation

DLD registration of project 3875 on 21 July 2025 came a little over three months before the recorded 02 November 2025 construction start on plot 4349, with the project trust account placed at Abu Dhabi Commercial Bank.

Current PhaseNov 2025 onward, 2.88% at last reading

Enabling and Infrastructure Works

Recorded at 1.23% at the undated previous inspection and 2.88% on 06 May 2026, when the status read Enabling Works, Progressing and the inspection note reported that "infra works are progressing" across the site.

Ahead: to 30%, Emaar estimate Mar 2027

Villa Construction Across the Cluster

Not yet recorded: work on the 173 villas themselves, each planned over ground, first and second floors (G+2). The plan of record ties a 10% installment to 30% completion, with March 2027 as Emaar's estimated date.

Ahead: 30% to 90%, Emaar estimates Mar 2027 to Jul 2028

Villa Build-Out and Cluster Amenities

Four construction triggers fall in this band, at 30%, 50%, 70% and 90%, alongside the community center, mosque, playground, fitness area and walking trail shown on Emaar's cluster plan.

Ahead: 90% to 100%, DLD completion 31 May 2029

Completion and Handover

The final 20% installment falls due upon 100% construction completion, estimated by Emaar for May 2029 and matching the 31 May 2029 completion date in the DLD register as of the 06 May 2026 reading.

What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Selvara 4 at Grand Polo's own record.

Buyer Position

Tracking Your Position at Selvara 4 at Grand Polo

This page is one of four project resources that together cover a Selvara 4 at Grand Polo purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Selvara 4 at Grand Polo Club & Resort by Emaar Properties contemporary villa exterior with construction updates visual in Dubai. Presented by Tohid Fetrat
You Are Here

Selvara 4 at Grand Polo Construction Updates

This page: the DLD inspection record for Selvara 4, from the November 2025 start to handover.

Selvara 4 at Grand Polo Club & Resort by Emaar Properties modern villa exterior with Golden Visa residency by investment card in Dubai. Presented by Tohid Fetrat

Selvara 4 at Grand Polo Golden Visa, Well Clear of the Threshold

Selvara 4 at Grand Polo is a cluster of 173 Emaar villas, each a 4 bedroom G+2 typology qualifying individually.

Read the Selvara 4 at Grand Polo Golden Visa Guide
Selvara 4 at Grand Polo Club & Resort by Emaar Properties modern villa exterior with escrow account protection icons in Dubai. Presented by Tohid Fetrat

Selvara 4 at Grand Polo Escrow, Registered With the DLD

Abu Dhabi Commercial Bank holds Selvara 4 at Grand Polo escrow: DLD project 3875, 173 units, 2.88% certified May 2026.

Verify the Selvara 4 at Grand Polo Escrow Account

Approaching Handover

Between 2.88% and Handover: What Selvara 4 at Grand Polo Buyers Should Do Now

At 2.88% on 06 May 2026, Selvara 4 is years from handover, so the useful work for a buyer now concerns payments and paperwork rather than a finished villa. On the launch schedule of record, the dated installments of October 2025, March 2026 and August 2026 have already passed, and the next is the 10% linked to 30% construction completion, which Emaar estimates for March 2027; the three steps below belong before that trigger is reached, not after it.

First, confirm that every installment goes only to the account registered for project 3875; the Selvara 4 escrow account page shows how to check it against the DLD record before each transfer.

Second, if UAE residency is part of your plan, read the Golden Visa guide for Selvara 4 buyers early, since the route to an application depends on the stage your purchase has reached.

Third, follow each new reading as it publishes, starting from the May 2026 inspection report for Selvara 4, so the first villa construction figures reach you before the construction-linked installments fall due.

Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.

The Wider Picture

Explore Grand Polo Dubai Structure

A build record is only half the picture; the other half is what is taking shape around it. These three pages put the Selvara 4 record in its market, community, and developer context:

Grand Polo Villas and Townhouses for Sale luxury villa with private pool and outdoor lounge at Grand Polo Club and Resort Dubai Presented by Tohid Fetrat

Grand Polo Dubai Properties for Sale

Browse villas and townhouses for sale at Grand Polo Club & Resort, comparing Equiterra, Selvara and Chevalia.

See Grand Polo Dubai Properties for Sale
Grand Polo Club and Resort by Emaar clubhouse overlooking the polo fields with palm lined landscape in Dubai Presented by Tohid Fetrat

Grand Polo Dubai Community Overview

Read the Grand Polo Club & Resort guide: Emaar's 60 million sq ft equestrian estate community of villas and townhouses.

Explore the Grand Polo Dubai Community
Emaar Properties developer showcasing Downtown Dubai skyline with Burj Khalifa and surrounding residential and commercial towers at dusk Presented by Tohid Fetrat

Emaar Properties: Burj Khalifa, Downtown Dubai and Twenty Master Communities

Emaar, founded in 1997, built Burj Khalifa and Downtown Dubai and has delivered over 85,000 homes across twenty master communities.

View the Emaar Properties Developer Profile

Construction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.

FAQs

Selvara 4 at Grand Polo Construction Updates Frequently Asked Questions

Selvara 4 at Grand Polo is an active DLD-registered project (number 3875) in its enabling works stage, recorded at 2.88% at the RERA inspection of 06 May 2026, when the progress status read Enabling Works, Progressing. The full record is in the inspection timeline above.

The 06 May 2026 inspection recorded 2.88% construction progress at Selvara 4, 1.65 points above the 1.23% shown for the previous inspection, a reading the DLD register lists without a date. The inspection note for that visit reports infrastructure works progressing on plot 4349, and the report is summarized in the Selvara 4 May 2026 construction update.

The DLD-registered completion date for project 3875 is 31 May 2029, and handover is scheduled for May 2029, the same month the final 20% installment falls due under the payment plan of record. The latest inspection on 06 May 2026 recorded 2.88% progress, so the registered date has not lapsed and the build is at its opening stage; this page's record is updated as each new inspection is recorded.

Selvara 4 at Grand Polo includes 173 villas, the unit count registered for DLD project 3875, and every one is a four bedroom home planned over ground, first and second floors (G+2). On Emaar's figures each villa averages about 3,805 sq ft (353 sq m) of built-up area, and the cluster plan spreads the 173 homes across several villa layouts.

Construction at Selvara 4 started on 02 November 2025 according to the DLD project register, a little over three months after the project was registered as number 3875 on 21 July 2025. The earliest dated reading in the register is 2.88% at the 06 May 2026 inspection, while an earlier 1.23% reading appears as the previous inspection with no date; the dated reading is covered in the May 2026 Selvara 4 inspection update.

Selvara 4 is numbered 12 on the 5.54 million sq m Grand Polo Club & Resort masterplan: 173 villas on plot 4349 in Dubai Investment Park Second, set close to the Green Core of three polo fields, the Clubhouse and the Stables. Emaar's cluster plan places a community center, mosque, playground, fitness area and walking trail inside the cluster, with Montura 3 beside it; the villa layouts are set out in the Selvara 4 at Grand Polo project guide.

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is keeping the Selvara 4 at Grand Polo construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

WhatsApp +971543443597
Get the Latest Status