Verified RERA Progress, Inspection Dates, and Delivery Milestones Across Island B at Dubai Islands
This page tracks Island B at Dubai Islands construction updates against official RERA inspection data, on a central island of Nakheel’s five-island master development along Dubai’s northern coastline. On a new island the useful signal is sequence: a plot can only move as fast as the roads, utilities and cooling networks built around it.
Each Island B card pairs the latest RERA reading with its inspection date and registered completion. Read the three together: on a young island, how recent the inspection is matters as much as the percentage beside it.

Track SHIONE at SIORA by Beyond through official RERA inspections, DLD construction progress records, dated updates and completion milestones.

Bay Villas, Nakheel's 636 homes in five collections along the Island B shore, read 22.76% on 19 August 2026.

Bay Grove Residences Phase 4, Nakheel's closing release of 257 residences in four buildings, stood at 0.04% on 24 July 2026.

I am Tohid Fetrat, a Dubai luxury real estate advisor based at The Opus by Omniyat in Business Bay. My office is inside this district, these are the cranes outside my window, and every update on this page comes from data I personally verify before publishing.
This index sets each tracked Island B project beside its progress, latest inspection and registered completion, so the island reads as one delivery pipeline rather than a run of separate launches. A long gap since the last inspection deserves as much attention as a low figure.
| Project | Progress | Inspection | Completion | Report |
|---|---|---|---|---|
| SHIONE at SIORA by Beyond | 0% | 03 November 2026 | Q4 2030 | View ReportAsk |
| Bay Villas | 22.76% | 19 August 2026 | Q2 2027 | View ReportAsk |
| Bay Grove Residences Phase 4 | 0.04% | 24 July 2026 | Q2 2029 | View ReportAsk |
| Bay Grove Residences Phase 3 | 5.7% | 22 July 2026 | Q1 2029 | View ReportAsk |
| Bay Grove Residences Phase 2 | 5.72% | 21 July 2026 | Q4 2028 | View ReportAsk |
| Bay Grove Residences Phase 1 | 6.6% | 21 July 2026 | Q3 2028 | View ReportAsk |
| HADO at SIORA | 0.01% | 16 June 2026 | Q3 2029 | View ReportAsk |
| Meriva Sunset | 0% | 25 February 2026 | Q2 2030 | View ReportAsk |
Progress figures reflect official RERA project inspection data.
Following a project on this page? Just reply with a project name and I will send you the verified progress and inspection updates directly on WhatsApp as they are published.
Get My Project Updates on WhatsAppIsland B projects move through the same construction stages as any Dubai development, with one added layer: each plot depends on the island’s own roads, utilities and district cooling links being ready around it. Knowing the stage a project has reached shows you which risks are still open and which are already behind it.
Each plot starts with contractor mobilization, authority approvals and coordination with the island’s primary roads and utility networks. A first RERA reading above zero is the sign that a project has moved from approvals to real site work.
Excavation, piling and foundation works set the base for buildings close to the coastline. Percentages move slowly at this stage, so steady movement across two or three inspections says more than any single figure.
Slabs, columns and cores rise level by level, usually the stretch where progress figures climb fastest. A consistent gain between inspections here is the clearest early test of whether a registered completion date will hold.
Glazing, cladding and balconies seal each building against sea air and summer heat. Interior trades wait on a closed envelope, so a slow façade usually delays every stage behind it.
Cooling, electrical and plumbing systems go in, followed by the finishes inside each unit. Figures rise in small steps here, and the quality of the finishing deserves more scrutiny than the speed.
Roads, landscaping, promenades and beach access are completed around each plot alongside the island’s shared networks. A building can be structurally finished while its surroundings still lag, which matters if you plan to move in at handover.
Authority inspections, systems testing and the completion certificate come before keys are released. An independent snagging inspection belongs before you accept the keys, while defects remain the developer’s responsibility.
Most buyer disputes start between stages, not at handover. Knowing which stage your project is in is what makes an inspection worth booking.
Not sure which stage your project is in?
Check My Project Stage on WhatsAppIsland B adds residential and hospitality supply in phases as its infrastructure comes online, so the order in which projects complete shapes what the island offers at any point. For an end user, the construction record shows when daily life on the island genuinely begins; for an investor, it shows when a unit can be leased and which handovers will compete with it.

Tracking progress is only one part of protecting an off plan purchase. These are the three areas buyers ask me to manage most.
Confirm your payments flow into the project’s registered escrow account, not anywhere else.
Ask About EscrowPlan a professional snagging inspection before you sign for handover.
Ask About SnaggingGet the latest inspection data on your project as it is published.
Ask About HandoverReview verified Island B at Dubai Islands construction update locations across beachfront residences, hospitality and mixed use developments, and active off plan projects connected to ongoing inspection activity and island infrastructure growth throughout Dubai Islands.

Island B is a central part of Nakheel’s Dubai Islands masterplan, and its growth follows infrastructure rather than the launch calendar: residential, hospitality and mixed use plots open up as primary roads and utilities are completed. My read is that buyers here are positioning early in a new coastal district, so the realistic horizon is the island maturing as a whole, not a single handover.

Island B at Dubai Islands construction updates track RERA progress readings, inspection dates and registered completion timelines for the projects being built on Island B. Each figure is checked against official inspection data before publishing, so the page shows where construction actually stands rather than where a launch schedule places it.
Construction activity shows how quickly Island B is moving from masterplan to a lived-in community. For end users it signals when daily life on the island can realistically begin; for investors it shows when units can be leased and which completions will compete for the same tenants.
The updates cover Island B projects that carry official RERA inspection readings, from beachfront residential buildings to hospitality and mixed use plots as they enter construction. Each tracked project links to its own report with its full inspection history.
Reports are refreshed when a new RERA inspection is recorded for a project or a milestone such as a completion certificate is confirmed. The inspection date shown beside each figure indicates how current it is, which matters as much as the percentage itself.
Nakheel, part of Dubai Holding Real Estate, is the master developer of Dubai Islands, the five-island destination on Dubai’s northern coastline formerly known as Deira Islands. Nakheel delivers Island B’s primary roads and utility networks, which frame how quickly individual plots can be built and occupied.
Buildings on Island B rely on the island’s roads, water, power, drainage and district cooling networks before they can be occupied. A project’s progress figure is therefore best read alongside the island’s infrastructure works, since moving in depends on both being ready.