Pearl House 4 by Imtiaz: JVC Tower From the Foundations Up
Pearl House 4 by Imtiaz, a 209-apartment retail and residential tower in Jumeirah Village Circle, read 17.93% in October 2026.

Verified Building Progress, Inspection Activity, and Handover Timing Across Nakheel’s JVC Master Community
Jumeirah Village Circle construction updates on this page follow the residential buildings rising plot by plot inside Nakheel’s circular master plan, each one measured against official RERA inspection data. Because many independent developers build here side by side, the real signal is the developer and contractor rather than the address: neighboring plots can sit years apart on progress.
Tracked from The Opus by Omniyat, inside Business BayEach card shows a Jumeirah Village Circle project at its most recent RERA inspection, with the progress figure, the inspection date and the expected completion side by side. Read the date beside the figure, not the figure alone: in a community built by many independent developers, a reading that has not moved since the last inspection says more than a high percentage.

Pearl House 4 by Imtiaz, a 209-apartment retail and residential tower in Jumeirah Village Circle, read 17.93% in October 2026.

Luxor by Imtiaz, a 356-residence B+G+4P+31 tower in Jumeirah Village Circle, read 90.02% in the DLD register on 17 September 2026.

Binghatti Etherea, a 282-residence Binghatti tower in Jumeirah Village Circle, read 7.24% on 15 September 2026 at foundation level.

I am Tohid Fetrat, a Dubai luxury real estate advisor based at The Opus by Omniyat in Business Bay. My office is inside this district, these are the cranes outside my window, and every update on this page comes from data I personally verify before publishing.
This index brings every tracked Jumeirah Village Circle project into one table, so progress, inspection timing and completion quarters can be compared across developers at a glance. The comparison is the point: a JVC project running well behind others with a similar completion quarter is the one to question first.
| Project | Progress | Inspection | Completion | Report |
|---|---|---|---|---|
| Pearl House 4 | 17.93% | 07 October 2026 | Q1 2028 | View ReportAsk |
| Luxor | 90.02% | 17 September 2026 | Q4 2026 | View ReportAsk |
| Binghatti Etherea | 7.24% | 15 September 2026 | Q3 2027 | View ReportAsk |
| The Portman | 78.67% | 7 August 2026 | Q3 2025 | View ReportAsk |
| Binghatti Ruby | 46.43% | 23 July 2026 | Q4 2026 | View ReportAsk |
| Hillmont Residences | 26.29% | 22 July 2026 | Q4 2026 | View ReportAsk |
| Binghatti Amberhall | 38.03% | 30 April 2026 | Q4 2026 | View ReportAsk |
| Binghatti Circle | 10.33% | 30 April 2026 | Q2 2027 | View ReportAsk |
Progress figures reflect official RERA project inspection data.
Following a project on this page? Just reply with a project name and I will send you the verified progress and inspection updates directly on WhatsApp as they are published.
Get My Project Updates on WhatsAppJumeirah Village Circle projects pass through the same inspection stages as any Dubai residential build, but most are mid rise buildings on compact plots, so the structural phase is relatively short and the finishing stages often decide the handover date. Judge each reading against its stage: a building that tops out early can still spend months in fit out and authority approvals.
The developer secures plot approvals, appoints the main contractor and sets up hoarding, site offices and temporary utilities before any structure starts. Readings sit near zero here, so the useful signal is how soon a first inspection is logged after launch.
Excavation, shoring and piling prepare the plot for basement or podium parking, and most of the work stays below street level. A JVC site can look idle from the road during this stage, which is why movement between two inspections tells you more than a drive past.
Columns, slabs and podium levels rise floor by floor, and on a mid rise building this is usually the quickest climb in the progress figure. A reading that stalls here rarely stays contained: structural slippage tends to move the completion quarter with it.
Blockwork, glazing, cladding and balcony works close the building in once the frame is far enough ahead. This is the first stage where you can compare the real exterior with the launch renders and judge the quality of the external finish.
Mechanical, electrical and plumbing systems go in alongside flooring, kitchens, joinery and apartment finishes. Many trades share the building at once, so the monthly gain usually narrows; consistency between inspections matters more than the size of each jump.
Plot landscaping, parking, utility connections and the link to the community road network are completed around the building. Late service connections can hold back an otherwise finished building, so their status is worth checking before planning a move or a tenancy.
Authority inspections, life safety testing and the completion certificate are the final gates before handover notices go out to buyers. The gap between notice and key collection is short, so a snagging inspection is best arranged before the notice arrives rather than after.
Most buyer disputes start between stages, not at handover. Knowing which stage your project is in is what makes an inspection worth booking.
Not sure which stage your project is in?
Check My Project Stage on WhatsAppJumeirah Village Circle is built by many independent developers on individual plots within one Nakheel master plan, so its construction record is really a set of separate delivery records sharing a single address. For an end user the updates show when a home, its parking and its road connections will be ready; for an investor they show when units can start earning and how much new supply reaches the same rental market together.

Tracking progress is only one part of protecting an off plan purchase. These are the three areas buyers ask me to manage most.
Confirm your payments flow into the project’s registered escrow account, not anywhere else.
Ask About EscrowPlan a professional snagging inspection before you sign for handover.
Ask About SnaggingGet the latest inspection data on your project as it is published.
Ask About HandoverReview verified Jumeirah Village Circle construction update locations across mid rise apartment buildings, townhouse and villa clusters, mixed use developments, and active off plan projects connected to ongoing inspection activity and community infrastructure growth throughout Dubai.

Jumeirah Village Circle sits between Al Khail Road and Sheikh Mohammed Bin Zayed Road with direct links to Hessa Street, and its master plan leaves room for a long pipeline of plot by plot development by private developers. My read is that access and entry price do most of the heavy lifting here: buyers come for a central New Dubai address with parks, schools and daily retail already in place. For an end user that means a maturing community; for an investor it means steady tenant depth, balanced against a supply pipeline that rarely pauses.

Jumeirah Village Circle construction updates track verified progress, inspection dates and expected completion for residential projects under construction in JVC, based on official RERA inspection data. Because the community is built plot by plot by many developers, the updates give a project by project view rather than a single community figure.
Nakheel is the master developer of Jumeirah Village Circle and planned its road network, parks and community facilities, including Circle Mall. Many of the residential buildings are delivered by independent developers on individual plots, so build quality and delivery pace depend on each project’s own developer.
The updates cover apartment buildings, mixed use developments and townhouse or villa projects under construction across the community’s districts. Mid rise apartment buildings make up most of the activity, in line with the community’s overall housing mix.
Each project is updated when a new RERA inspection reading or a confirmed milestone is published, so refresh timing differs from one project to the next. A reading that stays unchanged across several inspections is itself useful information about the pace of that site.
Each project in Jumeirah Village Circle has its own developer, contractor, launch date and escrow schedule, even when the plots sit on the same street. Completion dates therefore follow each project’s own timeline rather than a single community schedule, which is why every building is tracked separately.
Yes. Because many developers build inside the same master community, JVC allows delivery pace to be compared under similar conditions of access, plot size and building height. Projects with similar launch dates and completion quarters can be read side by side to see which sites keep moving between inspections.