Address Villas Tierra at The Oasis: Villa Build Progress Tracker
Address Villas Tierra at The Oasis, Emaar's 487-villa release, logged 6.81% at its first dated RERA inspection in July 2026.

Verified Villa Progress, Inspection Activity, and Lagoon Community Milestones Across The Oasis by Emaar
This page follows The Oasis construction updates across Emaar’s lagoon side villa and mansion clusters, with every reading taken from official RERA inspection data. The real signal is pace: in a villa cluster, steady movement between two inspections says more about handover than any launch date.
The Oasis is released cluster by cluster around its lakes and canals, so each project runs on its own construction clock rather than one shared schedule. Reading the most recent inspection for each cluster shows where the community is genuinely moving and where a handover date still rests on a sales brochure.

Address Villas Tierra at The Oasis, Emaar's 487-villa release, logged 6.81% at its first dated RERA inspection in July 2026.

Palmiera at The Oasis, Emaar's 216 four-bedroom and 49 five-bedroom villas, climbed from 41.78% to 81.72% by July 2026.

Palace Villas Ostra, Emaar's Palace-branded enclave of 526 stand-alone villas inside The Oasis, logged 6.54% in July 2026.

I am Tohid Fetrat, a Dubai luxury real estate advisor based at The Opus by Omniyat in Business Bay. My office is inside this district, these are the cranes outside my window, and every update on this page comes from data I personally verify before publishing.
Each row links to a full report with the RERA reading, the inspection date and the expected completion for that cluster. Read the table for pace rather than position: a villa project that stalls between inspections is a bigger warning than one that simply started later.
| Project | Progress | Inspection | Completion | Report |
|---|---|---|---|---|
| Address Villas Tierra at The Oasis | 6.81% | 21 July 2026 | Q2 2029 | View ReportAsk |
| Palmiera at The Oasis | 81.72% | 20 July 2026 | Q4 2027 | View ReportAsk |
| Palace Villas Ostra | 6.54% | 20 July 2026 | Q3 2029 | View ReportAsk |
| Mareva 2 at The Oasis | 1.32% | 06 July 2026 | Q1 2030 | View ReportAsk |
| Mirage at The Oasis | 46.94% | 29 June 2026 | Q2 2028 | View ReportAsk |
| Mareva at The Oasis | 2.05% | 16 June 2026 | Q1 2030 | View ReportAsk |
| Palmiera 3 at The Oasis | 72.62% | 09 June 2026 | Q3 2028 | View ReportAsk |
| Lavita at The Oasis | 20.13% | 02 June 2026 | Q1 2029 | View ReportAsk |
Progress figures reflect official RERA project inspection data.
Following a project on this page? Just reply with a project name and I will send you the verified progress and inspection updates directly on WhatsApp as they are published.
Get My Project Updates on WhatsAppVilla communities are built differently from towers: many homes rise on separate plots at once, while lakes, roads and parks have to keep pace around them. The seven stages below describe what happens at each point of a villa build in The Oasis and the signal worth watching.
Land grading, authority approvals, contractor mobilization and temporary site utilities come first across the cluster. The signal to watch is how quickly the first RERA reading moves off zero once work begins on site.
Each villa plot is excavated and set on foundations, while underground services and drainage are laid beneath the streets. Percentages move slowly here, so steady progress between inspections matters more than the headline figure.
Concrete frames, blockwork and roof slabs rise across the cluster, usually in batches of plots rather than one villa at a time. Readings should climb fastest at this stage; a flat reading here is the earliest warning of delay.
External finishes, glazing, cladding and boundary walls close each villa against the weather and give the street its final look. Build quality becomes visible in site photography at this point, well before any handover notice.
Mechanical, electrical and plumbing systems go in, followed by joinery, flooring, kitchens and bathrooms. Finishing quality is decided here, which is why a snagging plan starts to matter long before the keys.
Lakes, water canals, internal roads, parks and jogging tracks are built out alongside the homes. A villa is only as livable as the streets around it, so infrastructure that lags the houses deserves attention before handover.
Authority inspections, utility connections, completion certification and the developer’s handover notices close out the build. The window between completion and key collection is when an independent snagging inspection protects the buyer most.
Most buyer disputes start between stages, not at handover. Knowing which stage your project is in is what makes an inspection worth booking.
Not sure which stage your project is in?
Check My Project Stage on WhatsAppThe Oasis is delivered in phases, so the buyer’s question is not whether the community gets finished but which phase you are entering and how far along it is. For an end user that sets the move in date and how much construction remains next door; for an investor it sets when rent or resale becomes realistic.

Tracking progress is only one part of protecting an off plan purchase. These are the three areas buyers ask me to manage most.
Confirm your payments flow into the project’s registered escrow account, not anywhere else.
Ask About EscrowPlan a professional snagging inspection before you sign for handover.
Ask About SnaggingGet the latest inspection data on your project as it is published.
Ask About HandoverLocate The Oasis construction updates on the Dubai map alongside every other community tracked on this site. Seeing the villa clusters in context makes it easier to judge driving routes, neighboring master plans and where future supply will come from.

The Oasis grows outward from its water: Emaar’s masterplan gives a quarter of the land to lakes, canals, parks and open space, so new clusters join a setting rather than crowd it. My read is that this is its real distinction against denser villa launches: buyers are paying for plot size and open water, not for volume.

The Oasis construction updates track verified progress, inspection dates and expected completion for the villa and mansion projects Emaar is delivering inside the community. Every figure comes from official RERA inspection data, so a buyer can see how far a cluster has actually moved rather than relying on a launch timeline.
Construction activity shows whether a cluster is moving at a pace that supports its stated handover date. For investors that affects when rental income or a resale becomes realistic; for end users it sets the move in date and how much building work will still surround the home.
The updates cover the villa and mansion clusters Emaar is building around the community’s lakes and canals, along with the infrastructure that serves them. Because the homes are low rise villas rather than towers, the construction stages and warning signs differ from those in a high rise district.
A report is updated when a new RERA inspection reading is published or a project reaches a major construction stage. Gaps between inspections are normal, but a long gap with little movement is worth investigating before relying on a handover date.
Yes. Comparing inspection readings across successive phases of The Oasis shows how consistently the developer moves clusters from groundworks to handover. That record is a more reliable measure of delivery than launch announcements.
Each report sets out the latest progress percentage, the inspection date, the expected completion and the stage the build has reached, from structure through finishing and external works. Comparing two readings over time also shows the pace of work, which is the clearest early signal of delay.