Park Greens 2 by DAMAC at DAMAC Hills 2: Twin Villa Tracker
Park Greens 2 by DAMAC at DAMAC Hills 2 counts 274 twin villas, logged at 30.81% in June 2026.

Villa, Townhouse and Apartment Construction Progress Across DAMAC Hills 2 in Dubailand
This page follows DAMAC Hills 2 construction updates across the villa, townhouse and apartment clusters of DAMAC Properties’ master community in Dubailand, each measured against official RERA inspection data. Because the community grows one cluster at a time, the useful question is not whether DAMAC Hills 2 is built but how fast your own cluster moves between inspections.
The most recently inspected DAMAC Hills 2 projects lead this section, each with its RERA progress figure, inspection date and expected completion. My rule is to read the inspection date as carefully as the percentage: a high figure from an old inspection says less about the site today than a modest figure from a recent one.

Park Greens 2 by DAMAC at DAMAC Hills 2 counts 274 twin villas, logged at 30.81% in June 2026.

Violet 3 is DAMAC's 616-townhouse cluster in DAMAC Hills 2, with superstructure rising and 36.2% recorded on 16 May 2026.

The Farmhouses at DAMAC Hills 2, DAMAC's 13 country villas, rose from 58.96% to 83.02% by May 2026.

I am Tohid Fetrat, a Dubai luxury real estate advisor based at The Opus by Omniyat in Business Bay. My office is inside this district, these are the cranes outside my window, and every update on this page comes from data I personally verify before publishing.
Each DAMAC Hills 2 project tracked here links to its own report, with progress, inspection date and completion drawn from RERA data. Reading clusters side by side shows which are nearing handover and which are still in structural works. For an end user that difference sets a realistic move-in date; for an investor it sets the first month a unit can be leased.
| Project | Progress | Inspection | Completion | Report |
|---|---|---|---|---|
| Park Greens 2 by DAMAC at DAMAC Hills 2 | 30.81% | 19 June 2026 | Q1 2027 | View ReportAsk |
| Violet 3 | 36.2% | 16 May 2026 | Q2 2027 | View ReportAsk |
| The Farmhouses at DAMAC Hills 2 | 83.02% | 14 May 2026 | Q3 2025 | View ReportAsk |
| Verona at Damac Hills 2 | 100% | 14 May 2026 | Ready | View ReportAsk |
| Natura at DAMAC Hills 2 | 85.57% | 13 May 2026 | Q2 2026 | View ReportAsk |
| Violet 4 at DAMAC Hills 2 | 14.17% | 13 May 2026 | Q3 2027 | View ReportAsk |
| Park Greens at DAMAC Hills 2 | 21.69% | 13 May 2026 | Q1 2027 | View ReportAsk |
| Evergreens at DAMAC Hills 2 | 26.43% | 5 May 2026 | Q4 2026 | View ReportAsk |
| ELO at DAMAC Hills 2 | 21.5% | 15 April 2026 | Q4 2026 | View ReportAsk |
| Elo 2 & Elo 3 at DAMAC Hills 2 | 6.36% | 15 April 2026 | Q2 2027 | View ReportAsk |
| Violet at DAMAC Hills 2 | 85.44% | 14 April 2026 | Q2 2026 | View ReportAsk |
| Violet 2 at DAMAC Hills 2 | 45.08% | 10 April 2026 | Q1 2027 | View ReportAsk |
| Camelia at Damac Hills 2 | 100% | 30 October 2025 | Ready | View ReportAsk |
Progress figures reflect official RERA project inspection data.
Following a project on this page? Just reply with a project name and I will send you the verified progress and inspection updates directly on WhatsApp as they are published.
Get My Project Updates on WhatsAppDAMAC Hills 2 projects pass through the same inspection stages whether a cluster holds villas or townhouses, from site preparation to final handover. What changes in a community built cluster by cluster is where delays hide: the late roads, landscaping and amenity works often set the real handover date rather than the homes themselves.
Each new cluster starts with plot clearing, surveys, utility routing and contractor mobilization beside the existing community. The signal to watch is the first RERA reading after launch: a figure above zero shows work has moved beyond hoardings and signage.
Excavation, footings, ground beams and utility sleeves are laid across the cluster, plot by plot. Progress moves in small steps here, so a reading that stays flat across two inspections deserves a question before the next payment falls due.
Columns, slabs, block walls and roof structures rise along each row of villas and townhouses. This is usually the fastest stretch of the progress curve and the clearest test of how well the site is staffed.
External plaster, cladding, windows, doors and roof waterproofing close each home against the weather while boundary walls and hard landscaping begin. Interior trades can only start once the shell is sealed, so a delay here pushes every later stage back with it.
Electrical, plumbing, air conditioning, kitchens, flooring and joinery go in, followed by testing of each system. Percentages climb slowly at this stage because finishing work is detailed, and it is where workmanship quality is decided.
Internal roads, street lighting, parks, pools and cluster amenities are finished around the homes and tied into the wider community. A villa can look complete while its cluster is not, and handover usually waits until these works are signed off.
Authority inspections, completion certificates, snagging and handover documentation close out the build. This is the window for a professional snagging inspection, while defects are still the developer’s responsibility to fix.
Most buyer disputes start between stages, not at handover. Knowing which stage your project is in is what makes an inspection worth booking.
Not sure which stage your project is in?
Check My Project Stage on WhatsAppDAMAC Hills 2 is built as clusters of homes sharing parks, water features and sports facilities, so a unit’s value depends on the whole cluster being finished, not just the home. For an end user, the updates show when daily life in the cluster will work; for an investor, when a unit can be leased or resold as a finished home.

Tracking progress is only one part of protecting an off plan purchase. These are the three areas buyers ask me to manage most.
Confirm your payments flow into the project’s registered escrow account, not anywhere else.
Ask About EscrowPlan a professional snagging inspection before you sign for handover.
Ask About SnaggingGet the latest inspection data on your project as it is published.
Ask About HandoverReview verified DAMAC Hills 2 construction update locations across residential clusters, Water Town, Sports Town, infrastructure works, and active off plan projects connected to ongoing inspection activity throughout Dubailand.

DAMAC Hills 2 grows by adding new clusters of villas, townhouses and apartments inside an established community rather than by building on an empty plot. My read is that this is its real advantage: each new phase opens beside a mall, parks and leisure facilities already in use, not amenities that exist only on a masterplan.

DAMAC Hills 2 construction updates are progress reports on the villa, townhouse and apartment projects being built inside DAMAC Properties’ master community in Dubailand. Each report records the RERA progress figure, inspection date and expected completion, so a buyer sees how far a cluster has actually moved rather than relying on a launch timeline.
Construction pace decides when a DAMAC Hills 2 unit can be handed over, leased or resold as a completed home. Following inspection readings over time shows whether a cluster is moving steadily or stalling, which matters more for planning than the completion date printed in a sales plan.
The updates cover residential projects under construction across DAMAC Hills 2, from villa clusters and townhouse phases to apartment buildings. Each project is listed with its own report once official RERA inspection data is available for it.
Reports are updated as new RERA inspection data is published for each project and as major construction milestones are reached. The gap between two inspections is worth reading too, since a long silence can point to a slower site.
Yes. Comparing RERA readings across successive inspections shows whether a DAMAC Hills 2 project is gaining ground steadily or stalling, and how its pace compares with its stated completion date. A project that is near completion on paper but slow between inspections usually needs more time than its listed date suggests.
DAMAC Hills 2 combines villas, townhouses and apartments with community facilities that already operate, including Water Town, sports areas, parks and a community mall. For a long-term buyer the variable is less the community and more the individual cluster: its construction pace and handover timing decide when a home can be lived in or leased.