Fairway Villas 2 at Emaar South: Golf Villa Construction Updates
Fairway Villas 2 sets 309 Emaar villas around the Emaar South fairways, recorded at 92.16% at the 17 August 2026 inspection.

Verified Construction Progress Across the Villas, Townhouses, and Apartments of Emaar South
Emaar South construction updates follow Emaar’s golf course community in Dubai South, near Al Maktoum International Airport, with every project read against official RERA inspection data. For a district still in its build out years, the real question is less whether a site has started and more how steadily it moves between inspections.
Emaar South is delivered phase by phase, so each card pairs one project’s latest RERA reading with its inspection date and expected completion. A low figure early in a project’s life is normal; the signal to watch is whether the next inspection shows the site moving.

Fairway Villas 2 sets 309 Emaar villas around the Emaar South fairways, recorded at 92.16% at the 17 August 2026 inspection.

Golf Fields at Emaar South, a single Emaar building of 181 residences on plot 7096, read 0% again in August 2026.

Greenspoint 2 at Emaar South, a 244-townhouse Emaar phase on plot 7309, read 40.09% at the 03 August 2026 inspection.

I am Tohid Fetrat, a Dubai luxury real estate advisor based at The Opus by Omniyat in Business Bay. My office is inside this district, these are the cranes outside my window, and every update on this page comes from data I personally verify before publishing.
Each tracked Emaar South project gets one row here, with its progress, latest inspection and expected completion linked to the full report. Read completion against progress rather than either alone: a near date beside a low figure is the pairing that deserves a second look.
| Project | Progress | Inspection | Completion | Report |
|---|---|---|---|---|
| Fairway Villas 2 | 92.16% | 17 August 2026 | Q4 2026 | View ReportAsk |
| Golf Fields at Emaar South | 0% | 06 August 2026 | Q3 2030 | View ReportAsk |
| Greenspoint 2 at Emaar South | 40.09% | 03 August 2026 | Q1 2029 | View ReportAsk |
| Greenway 2 at Emaar South | 34.37% | 29 July 2026 | Q2 2028 | View ReportAsk |
| Golf Verge at Emaar South | 4.22% | 22 July 2026 | Q2 2029 | View ReportAsk |
| Greenspoint by Emaar at Emaar South | 42.9% | 21 July 2026 | Q1 2029 | View ReportAsk |
| Greenway at Emaar South | 39.06% | 20 July 2026 | Q3 2028 | View ReportAsk |
| Golf Hills 2 at Emaar South | 4.16% | 20 July 2026 | Q3 2029 | View ReportAsk |
| Golf Meadow at Emaar South | 4.54% | 19 July 2026 | Q3 2029 | View ReportAsk |
| GreenVille 2 at Emaar South | 47.31% | 19 July 2026 | Q1 2029 | View ReportAsk |
| Fairway Villas 3 by Emaar at Emaar South | 48.52% | 07 July 2026 | Q1 2028 | View ReportAsk |
| Golf Trails at Emaar South by Emaar | 0% | 1 July 2026 | Q4 2030 | View ReportAsk |
| Golf Hills at Emaar South | 3.67% | 23 June 2026 | Q3 2029 | View ReportAsk |
| Golf Acres at Emaar South | 3.47% | 23 June 2026 | Q4 2028 | View ReportAsk |
| Golf Lane at Emaar South | 30.05% | 18 June 2026 | Q4 2028 | View ReportAsk |
| Greenridge at Emaar South | 35.6% | 17 June 2026 | Q4 2028 | View ReportAsk |
| GreenVille at Emaar South | 46.02% | 14 May 2026 | Q1 2029 | View ReportAsk |
| Golf Dale at Emaar South | 0.27% | 30 April 2026 | Q4 2028 | View ReportAsk |
| Golf Vale at Emaar South | 0% | 24 February 2026 | Q1 2030 | View ReportAsk |
| Grove Ridge at Emaar South | 0% | 04 November 2025 | Q3 2029 | View ReportAsk |
| Vista Ridge at Emaar South | 0% | 04 November 2025 | Q3 2029 | View ReportAsk |
| Fairway Villas at Emaar South | 100% | 07 October 2025 | Q3 2026 | View ReportAsk |
| Golf Point at Emaar South | 4.78% | 30 June 2025 | Q4 2028 | View ReportAsk |
| Golf Edge at Emaar South | 0% | 5 November 2024 | Q1 2029 | View ReportAsk |
Progress figures reflect official RERA project inspection data.
Following a project on this page? Just reply with a project name and I will send you the verified progress and inspection updates directly on WhatsApp as they are published.
Get My Project Updates on WhatsAppEmaar South projects pass through seven broad stages, but the rhythm differs by product: villa and townhouse clusters spread across many plots, while an apartment building climbs floor by floor. The stage a project has reached, more than its percentage, shows a buyer what still has to go right.
The plot is graded, utility routes are planned and the contractor mobilizes, often while nearby phases of the master plan are still being serviced. The first date worth noting is the registered construction start, since early readings only carry meaning once that date has passed.
Excavation, foundations and underground services are laid for the apartment buildings, townhouses and villas that follow. Low rise foundations move faster than a tower’s, so a site that stays near zero for several inspections after its start date deserves a question.
Concrete frames and slabs go up across the plot, and villa or townhouse clusters are often framed in parallel rather than one after another. Structural work carries much of the percentage, so a project that gains little across two readings here is falling behind its own schedule.
External walls, glazing, roofs and cladding close each building, and landscaping starts to take shape between the plots. The signal to watch is whether exterior works follow soon after the frame; a finished structure left open for months points to a contractor stretched across too many plots.
Cooling, electrical and plumbing systems are installed, then kitchens, flooring and the finishes inside each home. Readings rise slowly here even on a well run site; what matters more is whether the finishes match the specification in the sales agreement.
Roads, parks, golf links, schools and retail are delivered around the homes, usually on a master developer timetable that runs separately from each project. For an end user the question is whether the street, the school run and the nearest shops will be ready on the day the keys arrive.
Authority inspections, systems testing and the completion certificate come before the developer sends out handover notices. A defect list is worth most when it is written before the keys change hands, because after acceptance every repair becomes a negotiation.
Most buyer disputes start between stages, not at handover. Knowing which stage your project is in is what makes an inspection worth booking.
Not sure which stage your project is in?
Check My Project Stage on WhatsAppEmaar South is still filling in around its golf course, so the value of a home depends partly on what is finished around it: roads, parks, retail and the plots next door. For an end user, the construction record shows when daily life there genuinely works; for an investor, it shows when a unit can be let into a finished setting.

Tracking progress is only one part of protecting an off plan purchase. These are the three areas buyers ask me to manage most.
Confirm your payments flow into the project’s registered escrow account, not anywhere else.
Ask About EscrowPlan a professional snagging inspection before you sign for handover.
Ask About SnaggingGet the latest inspection data on your project as it is published.
Ask About HandoverReview verified Emaar South construction update locations across villas, townhouses, apartment communities, golf facing developments, and active infrastructure projects connected to ongoing inspection activity and construction progress throughout Dubai South.

Emaar South grows with Dubai South, not on its own: a new passenger terminal approved for Al Maktoum International Airport is set to take over Dubai International’s operations in the coming years. My read is that the airport does most of the heavy lifting here, so the projects that keep pace on site are the ones ready when that demand arrives.

Emaar South construction updates track how each villa, townhouse and apartment project in the community is advancing, using official RERA inspection readings. They show where a site stands, when it was last inspected and when completion is expected, which turns a handover promise into something that can be checked.
Construction pace in Emaar South decides when a home can be occupied, leased or resold as a finished property rather than an off plan contract. In a community that is still filling in, it also shows when the surrounding roads, parks and amenities will be ready to support the rent or price an investor expects.
The updates cover residential projects across Emaar South, from apartment buildings to townhouse and villa clusters set around the golf course. Each type follows a different build sequence, so progress figures compare most fairly between projects of the same kind.
An Emaar South report changes when a new RERA inspection reading is published for that project. The inspection date deserves a look before the percentage, because a figure that is several months old describes the site as it was rather than as it stands today.
Yes. With Emaar as the developer behind the community, comparing inspection records across its projects shows how consistently one developer moves similar homes from launch to handover. A project that trails others at the same stage is the clearest signal worth questioning.
A report sets out the latest RERA progress percentage, the inspection date, the registered completion date and the construction stage, along with earlier readings where they exist. Taken as a set, they show whether a project’s pace supports the completion date it is working toward, something no single reading can show on its own.
Question not covered here? Ask me directly.
Ask Me About Your Project