Ocean Star at Rashid Yachts & Marina: Mina Rashid Waterfront Tracker
Ocean Star at Rashid Yachts & Marina, a 154-apartment Emaar waterfront release, logged 30.46% at the 11 August 2026 inspection.

Verified Construction Progress, Inspection Data, and Handover Timing Across the Port Rashid Waterfront
This page tracks Rashid Yachts & Marina construction updates across Emaar’s marina community on historic Port Rashid, with every waterfront project measured against official RERA inspection data. The number worth watching is the movement between two readings, not the reading itself: steady gains point to a realistic handover, while a reading that barely moves is the earliest sign of delay.
Each card shows the most recent RERA reading for a Rashid Yachts & Marina project, alongside its inspection date and registered completion quarter. Read the three together rather than apart: a high percentage carries little weight when the inspection behind it is several months old.

Ocean Star at Rashid Yachts & Marina, a 154-apartment Emaar waterfront release, logged 30.46% at the 11 August 2026 inspection.

Avonlea at Rashid Yachts & Marina, Emaar's 163-residence address on plot 468, reached 63.71% with fit-out under way in July 2026.

Bayline at Rashid Yachts & Marina, Emaar's 151-residence building beside The Canal Pool, reached 61.31% in July 2026.

I am Tohid Fetrat, a Dubai luxury real estate advisor based at The Opus by Omniyat in Business Bay. My office is inside this district, these are the cranes outside my window, and every update on this page comes from data I personally verify before publishing.
The directory lists each tracked Rashid Yachts & Marina project in its own row, with progress, latest inspection, and completion quarter side by side. Read each row from right to left: the completion quarter sets the deadline, and the inspection date tells you how current the progress figure really is.
| Project | Progress | Inspection | Completion | Report |
|---|---|---|---|---|
| Ocean Star at Rashid Yachts & Marina | 30.46% | 11 August 2026 | Q3 2028 | View ReportAsk |
| Avonlea at Rashid Yachts & Marina | 63.71% | 21 July 2026 | November 2027 | View ReportAsk |
| Bayline at Rashid Yachts & Marina | 61.31% | 19 July 2026 | Q4 2027 | View ReportAsk |
| Baystar by Vida at Rashid Yachts & Marina | 6.3% | 16 June 2026 | Q4 2029 | View ReportAsk |
| Sera 2 at Rashid Yachts & Marina | 0.04% | 02 June 2026 | Q4 2029 | View ReportAsk |
| Sera 1 at Rashid Yachts & Marina | 0.04% | 02 June 2026 | Q4 2029 | View ReportAsk |
| Porto View at Rashid Yachts & Marina | 6.26% | 02 June 2026 | Q4 2028 | View ReportAsk |
| Pier Point 2 at Rashid Yachts & Marina | 8.48% | 14 May 2026 | Q4 2028 | View ReportAsk |
| Pier Point 1 at Rashid Yachts & Marina | 8.27% | 14 May 2026 | Q4 2028 | View ReportAsk |
| Seascape at Rashid Yachts & Marina | 79.13% | 06 May 2026 | Q4 2026 | View ReportAsk |
| Marina Views at Rashid Yachts & Marina | 7.09% | 5 May 2026 | Q4 2028 | View ReportAsk |
| Ocean Point at Rashid Yachts & Marina | 26.95% | 21 April 2026 | Q2 2028 | View ReportAsk |
| Clearpoint at Rashid Yachts & Marina | 45.05% | 21 April 2026 | Q3 2027 | View ReportAsk |
| Marina Place 2 at Rashid Yachts & Marina | 1.52% | 21 April 2026 | Q4 2028 | View ReportAsk |
| Ocean Views at Rashid Yachts & Marina | 6.18% | 21 April 2026 | Q3 2028 | View ReportAsk |
| Ocean Cove at Rashid Yachts & Marina | 17.93% | 14 April 2026 | Q3 2028 | View ReportAsk |
| Marina Place 1 at Rashid Yachts & Marina | 4.23% | 3 April 2026 | Q4 2028 | View ReportAsk |
| Sunridge at Rashid Yachts & Marina | 100% | 17 March 2026 | Q1 2027 | View ReportAsk |
| Portside Square | 0% | 12 January 2026 | Q4 2029 | View ReportAsk |
| Fior 1 at Rashid Yachts & Marina | 0% | 11 December 2025 | Q3 2030 | View ReportAsk |
| Aurea at Rashid Yachts & Marina | 0% | 23 September 2025 | Q2 2030 | View ReportAsk |
| Seagate at Rashid Yachts & Marina | 100% | 14 April 2025 | Q3 2025 | View ReportAsk |
Progress figures reflect official RERA project inspection data.
Following a project on this page? Just reply with a project name and I will send you the verified progress and inspection updates directly on WhatsApp as they are published.
Get My Project Updates on WhatsAppRashid Yachts & Marina projects move through seven construction stages, and on a marina site part of that work happens at the water’s edge as well as on the plot. Knowing the stage matters more than the headline figure: the same percentage reads very differently during frame works than during finishing.
Contractors mobilize, approvals are secured, and utilities are planned, with marine works coordinated around plots on the marina edge. The first signal is a RERA reading that moves off zero, confirming the main contract is under way.
Piling, retaining walls, and basement works run below ground, so real progress is made even when little shows from the promenade. Readings climb slowly here, which is why pace is best judged across several inspections rather than one.
Concrete frames and podium slabs rise floor by floor, making this the most visible stage from the waterfront. The signal is consistency: readings that climb steadily between inspections say more than one large jump.
Glazing, balconies, and the external envelope close each building in against sea air and summer heat. Once the façade is sealed, attention moves indoors and the pace of finishing becomes the variable that decides handover.
Mechanical, electrical, and cooling systems go in alongside flooring, joinery, and kitchens in every home. This is where buyers start to feel delays, because a high percentage can still hide months of detailed finishing work.
Marina access, landscaped promenades, retail frontage, and shared amenities are completed around the buildings. For an end user this decides how the community feels on day one; for an investor it shapes how quickly a home can be leased after handover.
Authority inspections, system testing, and the completion certificate come before the developer issues handover notices. The snagging window opens here, and defects recorded now are fixed while the developer is still responsible.
Most buyer disputes start between stages, not at handover. Knowing which stage your project is in is what makes an inspection worth booking.
Not sure which stage your project is in?
Check My Project Stage on WhatsAppRashid Yachts & Marina construction updates show whether waterfront homes are tracking toward their registered completion or drifting away from it. For an end user that sets a realistic moving date; for an investor it sets when rent can begin and how much of the payment plan still carries construction risk.

Tracking progress is only one part of protecting an off plan purchase. These are the three areas buyers ask me to manage most.
Confirm your payments flow into the project’s registered escrow account, not anywhere else.
Ask About EscrowPlan a professional snagging inspection before you sign for handover.
Ask About SnaggingGet the latest inspection data on your project as it is published.
Ask About HandoverReview verified Rashid Yachts & Marina construction update locations across marina facing residences, waterfront towers, hospitality developments, yacht infrastructure, and active coastal projects connected to ongoing inspection activity and construction progress throughout Dubai.

Rashid Yachts & Marina trades on its setting: a yacht marina community on historic Port Rashid, positioned near both Old Dubai and Downtown Dubai. My read is that location is the settled part of the decision here; what still varies from one building to the next is finish quality and handover timing.

Rashid Yachts & Marina construction updates track the build progress of waterfront projects in Emaar’s marina community on Port Rashid, using official RERA inspection data. Each update records the progress percentage, the inspection date, and the registered completion timeline, so a project can be followed from foundations to handover. The directory also includes completed projects.
Construction activity shows whether a waterfront project is on course for its registered completion, which decides when rent can start and when the final payments fall due. Following each inspection also exposes delays early, while there is still time to plan around them.
The updates cover waterfront residences, marina facing towers, hospitality developments, and mixed use projects across Rashid Yachts & Marina. Each tracked project links to its own report page, so stages can be compared across the community in one place.
Reports are refreshed whenever a new RERA inspection reading is recorded for a project, so the timing follows the inspection cycle rather than a fixed calendar. The inspection date beside each figure shows exactly how current the reading is.
Yes. A run of dated inspection readings shows whether a developer holds a steady pace and delivers close to its registered completion dates, which is a firmer test than launch announcements. Across Rashid Yachts & Marina, that record builds one project and one inspection at a time.
Each report gives the RERA progress percentage, the inspection date, the expected completion quarter, and the construction stage the project has reached. Read together, these show both how far a building has come and how much work remains before handover.
Question not covered here? Ask me directly.
Ask Me About Your Project